National Grid Electricity Distribution

Embedded Capacity Register, August 2026 edition

2,042sites of 1 MW and over
42.3 GWcapacity
10.7 GWconnected (1,239 sites)
31.6 GWaccepted to connect (803 sites)

Capacity by edition month

Total capacity of sites of 1 MW and over, month by month. Months not covered by NGED's own files use Northern Powergrid's copy of all six registers.

0 GW25 GW50 GW75 GW100 GWFeb 2024February 2024: 9.3 GW connected, 46.7 GW accepted to connect (National ECR Archive, a secondary source)March 2024: 9.3 GW connected, 47.1 GW accepted to connect (National ECR Archive, a secondary source)April 2024: 10 GW connected, 47.4 GW accepted to connect (National ECR Archive, a secondary source)May 2024: 10 GW connected, 49.2 GW accepted to connect (National ECR Archive, a secondary source)June 2024: 9.6 GW connected, 48.8 GW accepted to connect (National ECR Archive, a secondary source)July 2024: no edition heldAugust 2024: 9.5 GW connected, 48.5 GW accepted to connect (National ECR Archive, a secondary source)September 2024: 9.2 GW connected, 48 GW accepted to connect (National ECR Archive, a secondary source)October 2024: no edition heldNovember 2024: no edition heldDecember 2024: no edition heldJan 2025January 2025: 10.9 GW connected, 49.2 GW accepted to connect (National ECR Archive, a secondary source)February 2025: 10.9 GW connected, 49 GW accepted to connect (National ECR Archive, a secondary source)March 2025: 10.9 GW connected, 48 GW accepted to connect (National ECR Archive, a secondary source)April 2025: 11 GW connected, 47.7 GW accepted to connect (National ECR Archive, a secondary source)May 2025: 9.6 GW connected, 47.8 GW accepted to connect (National ECR Archive, a secondary source)June 2025: no edition heldJuly 2025: no edition heldAugust 2025: no edition heldSeptember 2025: no edition heldOctober 2025: no edition heldNovember 2025: 9.8 GW connected, 47 GW accepted to connect (National ECR Archive, a secondary source)December 2025: no edition heldJan 2026January 2026: 10.2 GW connected, 46.8 GW accepted to connect (National ECR Archive, a secondary source)February 2026: no edition heldMarch 2026: no edition heldApril 2026: no edition heldMay 2026: no edition heldJune 2026: no edition heldJuly 2026: no edition heldAugust 2026: 10.7 GW connected, 31.6 GW accepted to connect (NGED's own edition)

ConnectedAccepted to connectNGED's own editionNational ECR Archive, a secondary sourceNo edition held

The figures, month by month
Edition monthSourceSitesConnectedAccepted to connectTotal
August 2026NGED's own edition2,04210.7 GW31.6 GW42.3 GW
July 2026No edition held––––
June 2026No edition held––––
May 2026No edition held––––
April 2026No edition held––––
March 2026No edition held––––
February 2026No edition held––––
January 2026National ECR Archive, a secondary source2,25310.2 GW46.8 GW57 GW
December 2025No edition held––––
November 2025National ECR Archive, a secondary source2,2559.8 GW47 GW56.8 GW
October 2025No edition held––––
September 2025No edition held––––
August 2025No edition held––––
July 2025No edition held––––
June 2025No edition held––––
May 2025National ECR Archive, a secondary source2,2619.6 GW47.8 GW57.4 GW
April 2025National ECR Archive, a secondary source2,26911 GW47.7 GW58.7 GW
March 2025National ECR Archive, a secondary source2,26810.9 GW48 GW58.9 GW
February 2025National ECR Archive, a secondary source2,27310.9 GW49 GW59.9 GW
January 2025National ECR Archive, a secondary source2,27110.9 GW49.2 GW60.1 GW
December 2024No edition held––––
November 2024No edition held––––
October 2024No edition held––––
September 2024National ECR Archive, a secondary source2,2709.2 GW48 GW57.2 GW
August 2024National ECR Archive, a secondary source2,2679.5 GW48.5 GW58 GW
July 2024No edition held––––
June 2024National ECR Archive, a secondary source2,2849.6 GW48.8 GW58.4 GW
May 2024National ECR Archive, a secondary source2,32610 GW49.2 GW59.2 GW
April 2024National ECR Archive, a secondary source2,31110 GW47.4 GW57.4 GW
March 2024National ECR Archive, a secondary source2,2139.3 GW47.1 GW56.4 GW
February 2024National ECR Archive, a secondary source2,2099.3 GW46.7 GW56 GW

What changed between editions

Changes to sites found in both of two consecutive monthly editions.

QueueWatch holds one edition of NGED's register so far, the August 2026 edition, so there is nothing to compare yet.

Grid supply points in the August 2026 edition

Each grid supply point the edition names, the largest first, with the capacity of its sites connected and accepted to connect. “Not stated” is the sites whose register gives no grid supply point.

Bicker Fen 132Kv S Stn460.3 GW2.1 GW
Ratcliffe On Soar 132Kv S Stn600.2 GW2 GW
Grendon 132Kv S Stn810.4 GW1.6 GW
Iron Acton 132Kv S Stn720.4 GW1.4 GW
Coventry 132Kv S Stn750.4 GW1.4 GW
Indian Queens Sgp1160.5 GW1 GW
Chesterfield 132Kv S Stn1000.5 GW0.9 GW
Alverdiscott Sgp800.5 GW0.9 GW
East Claydon 132Kv S Stn580.3 GW1 GW
Swansea North Grid870.6 GW0.6 GW

Sites in the August 2026 edition

2,042 sites, 42.3 GW: 10.7 GW connected, 31.6 GW accepted to connect

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Former rafridge clean energy ltdEast MidlandsSolarAccepted to connect480Bicker Fen 132Kv S Stn
Land atbsr appplications limitedEast MidlandsSolarAccepted to connect299.7Bicker Fen 132Kv S Stn
Home farm, proposed energy storage @cellarhead bess ltdWest MidlandsStorageAccepted to connect280Cellarhead 132Kv
248mw lincoln battery storageforepower lincoln (250) limitedEast MidlandsStorageAccepted to connect248Bicker Fen 132Kv S Stn
Painsbrook solar, wind and storageBsr applications limitedWest MidlandsSolarAccepted to connect240Shrewsbury 132Kv S Stn
Ansty house farm bessRe project developmentEast MidlandsStorageAccepted to connect200Coventry 132Kv S Stn
Land at, stockhills farm storageBsr applications limitedWest MidlandsStorageAccepted to connect200Iron Acton 132Kv S Stn
J026arwe renewables uk solar and storage ltdSouth WalesSolarAccepted to connect199.88Uskmouth
Land south ofpace psr renewable energy hold co ltdWest MidlandsSolarAccepted to connect199.8Lea Marston 132Kv S Stn
Poplar & villa farm pv & bessBsr applications limitedEast MidlandsSolarAccepted to connect199.8Bicker Fen 132Kv S Stn

QueueWatch holds one NGED edition, August 2026.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.