Distribution / NGED / Grid supply point

Port Ham 132Kv S Stn

Grid supply point in West Midlands

NGED Embedded Capacity Register, August 2026 edition

46sites of 1 MW and over
1.1 GWcapacity
0.3 GWconnected (25 sites)
0.8 GWaccepted to connect (21 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar30751 MW222 MW529 MW
Storage7263 MW3 MW260 MW
Gas and other fossil639.3 MW39.3 MW–
Bioenergy and waste38.9 MW8.9 MW–

Storage capacity in MWh: not published by NGED.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the August 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Castle Meads 33Kv S Stn597 MW11 MW
Castle Meads 33Kv S Stn1–20 MW
Castle Meads 33Kv S Stn10.6 MW–
Castle Meads 33Kv S Stn3–67 MW
Lydney 33Kv S Stn1–12 MW
Lydney 33Kv S Stn25.4 MW–
Lydney 33Kv S Stn14.1 MW–
Lydney 33Kv S Stn11.5 MW–
Lydney 33Kv S Stn11.4 MW–
Lydney 33Kv S Stn210 MW–
Cheltenham 66Kv S Stn48 MW5 MW
Cheltenham 66Kv S Stn13.9 MW–
Cheltenham 66Kv S Stn11.1 MW–
Commercial Rd 33 11Kv S Stn412 MW–
Montpellier 132Kv S Stn15.6 MW–
Tewkesbury Grid 132/11Kv13.3 MW–
Eastern Avenue 132Kv S Stn1–1.5 MW
Not stated15119 MW673 MW

What changed recently

Changes to the sites here found in both of two consecutive monthly editions, the latest first.

QueueWatch holds one edition of NGED's register so far, the August 2026 edition, so there is nothing to compare yet.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.