QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / Sites / Customer

Quintas Energy UK

Customer named in the DNOs’ registers

In NGED’s August 2026, SPEN’s September 2026 and ENWL’s October 2026 editions

The registers spell this customer’s name more than one way: “Quintas Energy UK” (6 sites), “Quintas energy uk ltd” (2 sites) and “QUINTAS ENERGY UK LTD” (1 site).

9sites of 1 MW and over
109 MWcapacity
60 MWconnected (6 sites)
49 MWaccepted to connect (3 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
NGEDAugust 2026 edition211.2 MW–11.2 MW
SPENSeptember 2026 edition659.5 MW59.5 MW–
ENWLOctober 2026 edition138 MW–38 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar9109 MW60 MW49 MW

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs’ latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
SOWERBY LODGE FARMENWLHARKER/HUTTONSolarAccepted to connect38
Bryn-Yr-Odin Solar ParkSPENWylfaSolarConnected15
Parciau Solar ParkSPENPentirSolarConnected15
Tai Moelion Solar ParkSPENWylfaSolarConnected15
StonebarrowNGEDAxminster SgpSolarAccepted to connect5.87
Witches solar park, 756593 witches solar park, 11kv metering mpan importNGEDBishops Wood 132Kv S StnSolarAccepted to connect5.3
Trench Farm Solar FarmSPENLegacySolarConnected5
Lochcraigs Solar ParkSPENSaltcoats ASolarConnected4.75
The Grange (plas Bennion Rd)SPENLegacySolarConnected4.75

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
HARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUPENWL1–38 MW
WylfaSPEN230 MW–
PentirSPEN115 MW–
LegacySPEN29.8 MW–
Axminster SgpNGED1–5.9 MW
Bishops Wood 132Kv S StnNGED1–5.3 MW
Saltcoats ASPEN14.8 MW–

What changed recently

Changes to its sites found in both editions of each pair, newest first.

Tracking NGED’s register since its August 2026 edition. Changes will show from its next edition.

SPEN, August 2026 edition to September 2026 edition, for this customer’s sites: 6 sites matched. Every August site and every September site had a match in the other edition.

ENWL, September 2026 edition to October 2026 edition, for this customer’s sites: 1 site matched. Every September site and every October site had a match in the other edition.

  • SOWERBY LODGE FARMENWL, September 2026 editionCapacity stated as 38 MW (not stated in the May 2026 edition)
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?