QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Laurel farm, hasland solar farm

hasland green limited owned verdant at Chesterfield 132Kv S Stn

NGED Embedded Capacity Register, August 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
28 Apr 2027
Status
Accepted to connect
Planning consent
Granted 8 Dec 2021
North East Derbyshire, reference 20/01283/FL · Source: REPD
Contract for Difference
Allocation Round 4
Customer
hasland green limited owned verdant
Site name
Laurel farm, hasland solar farm
Address
Calow, Chesterfield, S44 5XH
Grid reference
Easting 440695, northing 369960
NGED’s register gives it in tenths of a metre.
Licence area
East Midlands
Grid supply point
Chesterfield 132Kv S Stn
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
132 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 50 MW registered
Registered capacity
50 MW
Change to maximum export capacity
50 MW
Change to maximum import capacity
0.1 MW
Flexible connection
Not published by NGED
In a connection queue
Not published by NGED
Date accepted
11 Sep 2020
Date connected
Not stated
Distribution reinforcement reference
Not published by NGED
Transmission reinforcement reference
Not published by NGED
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
6 Aug 2026
Tracked since
August 2026 edition

Change history

Tracked since the August 2026 edition, the only one QueueWatch holds so far.

Changes to the details QueueWatch tracks, newest first.

Changes will show from the next edition.

Also at Chesterfield 132Kv S Stn

GSP view

99 other sites at this grid supply point in the August 2026 edition. In all, the sites here total 1.4 GW: 0.5 GW connected, 0.9 GW accepted to connect.

See all 99

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition. QueueWatch matched the site to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.