QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Furzen solar

rwe renewables uk solar and storage ltd at East Claydon 132Kv S Stn

NGED Embedded Capacity Register, August 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
13 Apr 2027
Status
Accepted to connect
Customer
rwe renewables uk solar and storage ltd
Site name
Furzen solar
Address
East Claydon Road, Aylesbury Vale, Buckinghamshire, MK18 3NF
Grid reference
Easting 475044, northing 225943
NGED’s register gives it in tenths of a metre.
Licence area
East Midlands
Grid supply point
East Claydon 132Kv S Stn
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
132 kV
Technology group
Storage
Energy source 1
Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 49.9 MW registered
Registered capacity
49.9 MW
Change to maximum export capacity
49.9 MW
Change to maximum import capacity
49.9 MW
Flexible connection
Not published by NGED
In a connection queue
Not published by NGED
Date accepted
11 Jun 2020
Date connected
Not stated
Distribution reinforcement reference
Not published by NGED
Transmission reinforcement reference
Not published by NGED
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
6 Aug 2026
Tracked since
August 2026 edition

What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?

Change history

Tracked since the August 2026 edition, the only one QueueWatch holds so far.

Changes to the details QueueWatch tracks, newest first.

Changes will show from the next edition.

Also at East Claydon 132Kv S Stn

GSP view

57 other sites at this grid supply point in the August 2026 edition. In all, the sites here total 1.3 GW: 0.3 GW connected, 1.0 GW accepted to connect.

See all 57

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?