Distribution / NGED / Grid supply point

Ironbridge 132Kv S Stn

Grid supply point in West Midlands

NGED Embedded Capacity Register, August 2026 edition

27sites of 1 MW and over
371 MWcapacity
92 MWconnected (18 sites)
279 MWaccepted to connect (9 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar18299 MW72 MW227 MW
Storage149.9 MW–49.9 MW
Bioenergy and waste410 MW7.5 MW2.5 MW
Gas and other fossil38.7 MW8.7 MW–
Other or not stated13 MW3 MW–

Storage capacity in MWh: not published by NGED.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the August 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Ketley 132Kv S Stn36.3 MW–
Ketley 132Kv S Stn15.1 MW–
Ketley 132Kv S Stn11.6 MW–
Ketley 132Kv S Stn49.5 MW25 MW
Ironbridge 132 33Kv S Stn14.1 MW–
Ironbridge 132 33Kv S Stn13.6 MW–
Ironbridge 132 33Kv S Stn13 MW–
Ironbridge 132 33Kv S Stn433 MW–
Ironbridge 400/132Kv36.5 MW2.5 MW
Not stated819 MW252 MW

Search and filter all 27 sites at Ironbridge 132Kv S Stn

What changed recently

Changes to sites here found in both editions of each pair, newest first.

Tracking NGED’s register since its August 2026 edition. Changes will show from its next edition.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.