Distribution / Sites / Customer

VIRIDIS ENERGY (NORGEN) LIMITED

Customer named in the DNOs’ registers

In UKPN’s November 2026, NGED’s August 2026, SSEN’s November 2026 and ENWL’s October 2026 editions

The registers spell this customer’s name more than one way: “VIRIDIS ENERGY (NORGEN) LIMITED” (7 sites), “Viridis Energy (Norgen) Limited” (1 site) and “Viridis energy (norgen) limited” (1 site).

9sites of 1 MW and over
17.1 MWcapacity
17.1 MWconnected (9 sites)
–accepted to connect (0 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
UKPNNovember 2026 edition13 MW3 MW–
NGEDAugust 2026 edition10.4 MW0.4 MW–
SSENNovember 2026 edition23 MW3 MW–
ENWLOctober 2026 edition510.7 MW10.7 MW–

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Bioenergy and waste816.7 MW16.7 MW–
Other or not stated10.4 MW0.4 MW–

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs’ latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
CLITHEROE WORKSENWLPENWORTHAM WEST GSP / STANAH GSP GROUPBioenergy and wasteConnected6.118
Warboys Landfill SiteUKPNEaton SoconBioenergy and wasteConnected3
VIRIDIS ENERGY (NORGEN) LIMITEDSSENLUNANHEADBioenergy and wasteConnected1.9
HESPIN WOOD LANDFILLENWLHARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUPBioenergy and wasteConnected1.33
SALT AYRE LANDFILLENWLHEYSHAM GSPBioenergy and wasteConnected1.15
SALT AYRE LANDFILL 3ENWLHEYSHAM GSPBioenergy and wasteConnected1.15
VIRIDIS ENERGY (NORGEN) LIMITEDSSENMANNINGTON GSPBioenergy and wasteConnected1.093
SALT AYRE LANDFILL 2ENWLHEYSHAM GSPBioenergy and wasteConnected1
Generation siteNGEDIron Acton 132Kv S StnOther or not statedConnected0.4

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
PENWORTHAM WEST GSP / STANAH GSP GROUPENWL16.1 MW–
HEYSHAM GSPENWL33.3 MW–
Eaton SoconUKPN13 MW–
LUNANHEADSSEN11.9 MW–
HARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUPENWL11.3 MW–
MANNINGTON GSPSSEN11.1 MW–
Iron Acton 132Kv S StnNGED10.4 MW–

What changed recently

Changes to its sites found in both editions of each pair, newest first.

UKPN, October 2026 edition to November 2026 edition, for this customer’s sites: 1 site matched. Every October site and every November site had a match in the other edition.

Tracking NGED’s register since its August 2026 edition. Changes will show from its next edition.

SSEN, October 2026 edition to November 2026 edition, for this customer’s sites: 2 sites matched. Every October site and every November site had a match in the other edition.

ENWL, September 2026 edition to October 2026 edition, for this customer’s sites: 5 sites matched. Every September site and every October site had a match in the other edition.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose