QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / Sites / Customer

Conrad Energy

Customer named in the DNOs’ registers

In UKPN’s November 2026, NGED’s August 2026, SSEN’s November 2026, SPEN’s September 2026 and ENWL’s October 2026 editions

The registers spell this customer’s name more than one way: “Conrad Energy” (6 sites), “CONRAD ENERGY” (2 sites), “CONRAD ENERGY LTD” (1 site) and “Conrad energy” (1 site).

10sites of 1 MW and over
165 MWcapacity
38 MWconnected (6 sites)
127 MWaccepted to connect (4 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
UKPNNovember 2026 edition428.1 MW28.1 MW–
NGEDAugust 2026 edition117.2 MW–17.2 MW
SSENNovember 2026 edition14.1 MW–4.1 MW
SPENSeptember 2026 edition210 MW10 MW–
ENWLOctober 2026 edition2106 MW–106 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage175.7 MW–75.7 MW
Solar351.3 MW–51.3 MW
Gas and other fossil638.1 MW38.1 MW–

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs’ latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
ADSWOOD BESSENWLBREDBURY GSPStorageAccepted to connect75.7
HAZEL GROVE PV SOLAR FARMENWLBREDBURY GSPSolarAccepted to connect30
Keynsham pv plantNGEDSeabank SgpSolarAccepted to connect17.16
London RoadUKPNWarleyGas and other fossilConnected10
Land West Of B579UKPNSundonGas and other fossilConnected6.08
Abbess RoadUKPNPelhamGas and other fossilConnected6
Commerce WayUKPNSundonGas and other fossilConnected6
Aber Park Gas GenerationSPENConnahs QuayGas and other fossilConnected5
FERODO (Swn y Mor)SPENPentirGas and other fossilConnected5
BOURNEMOUTH AIRPORT SOLAR PV PLANTSSENMANNINGTON GSPSolarAccepted to connect4.1

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
BREDBURY GSPENWL2–106 MW
Seabank SgpNGED1–17.2 MW
SundonUKPN212.1 MW–
WarleyUKPN110 MW–
PelhamUKPN16 MW–
Connahs QuaySPEN15 MW–
PentirSPEN15 MW–
MANNINGTON GSPSSEN1–4.1 MW

What changed recently

Changes to its sites found in both editions of each pair, newest first.

UKPN, October 2026 edition to November 2026 edition, for this customer’s sites: 4 sites matched. Every October site and every November site had a match in the other edition.

Tracking NGED’s register since its August 2026 edition. Changes will show from its next edition.

SSEN, October 2026 edition to November 2026 edition, for this customer’s sites: 1 site matched. Every October site and every November site had a match in the other edition.

SPEN, August 2026 edition to September 2026 edition, for this customer’s sites: 2 sites matched. Every August site and every September site had a match in the other edition.

ENWL, September 2026 edition to October 2026 edition, for this customer’s sites: 2 sites matched. Every September site and every October site had a match in the other edition.

No change to any detail QueueWatch tracks for its sites so far.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips