Distribution / NGED / Grid supply point

Exeter Main Sgp

Grid supply point in South West

NGED Embedded Capacity Register, August 2026 edition

64sites of 1 MW and over
1.1 GWcapacity
0.2 GWconnected (36 sites)
0.9 GWaccepted to connect (28 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar41711 MW102 MW609 MW
Storage8292 MW43 MW249 MW
Wind436.5 MW–36.5 MW
Gas and other fossil425.5 MW15.6 MW9.9 MW
Bioenergy and waste512.4 MW11.4 MW1 MW
Other or not stated26.3 MW6.3 MW–

Storage capacity in MWh: not published by NGED.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the August 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Exeter Main Bsp723 MW149 MW
Tiverton Bsp67 MW10.8 MW
Tiverton Bsp27.7 MW–
Tiverton Bsp26.7 MW–
Tiverton Bsp1–6.3 MW
Tiverton Bsp12.8 MW–
Tiverton Bsp22.7 MW–
Tiverton Bsp11.5 MW–
Tiverton Bsp717.6 MW74.9 MW
Exeter City Bsp2–7.8 MW
Exeter City Bsp17.1 MW–
Exeter City Bsp26.2 MW–
Exeter City Bsp21.1 MW4.9 MW
Exeter City Bsp12.9 MW–
Exeter City Bsp12 MW–
Exeter City Bsp42.2 MW46.6 MW
Sowton Bsp15 MW–
Sowton Bsp13 MW–
Sowton Bsp12.7 MW–
Sowton Bsp12.6 MW–
Sowton Bsp1–1.9 MW
Sowton Bsp11.1 MW–
Sowton Bsp512.7 MW44.9 MW
Exmouth Bsp19.9 MW–
Exmouth Bsp39.5 MW9.9 MW
Not stated742 MW548 MW

What changed recently

Changes to the sites here found in both of two consecutive monthly editions, the latest first.

QueueWatch holds one edition of NGED's register so far, the August 2026 edition, so there is nothing to compare yet.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.