Swansea North Grid
Grid supply point in South Wales
NGED Embedded Capacity Register, August 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Solar | 48 | 516 MW | 248 MW | 268 MW |
| Wind | 19 | 385 MW | 223 MW | 162 MW |
| Hydro and marine | 3 | 116 MW | 7 MW | 109 MW |
| Storage | 4 | 99.1 MW | 74.4 MW | 24.7 MW |
| Gas and other fossil | 7 | 82.7 MW | 62.7 MW | 20 MW |
| Bioenergy and waste | 3 | 19.7 MW | 4.7 MW | 15 MW |
| Other or not stated | 3 | 11.4 MW | 11.4 MW | – |
Storage capacity in MWh: not published by NGED.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the August 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Swansea North Bsp | 12 | 64 MW | 129 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12 sites, 193 MW: 64 MW connected, 129 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Rhos Grid | 2 | 4.3 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 4.3 MW: 4.3 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Rhos Grid | 1 | 2 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 2 MW: 2 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Rhos Grid | 5 | 41 MW | 109 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5 sites, 150 MW: 41 MW connected, 109 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Hirwaun Grid | 3 | 16.6 MW | 15 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 31.6 MW: 16.6 MW connected, 15 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Hirwaun Grid | 2 | 4.4 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 4.4 MW: 4.4 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Hirwaun Grid | 5 | 62.8 MW | 14.1 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5 sites, 76.9 MW: 62.8 MW connected, 14.1 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Trostre Grid | 2 | 1.1 MW | 26 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 27.1 MW: 1.1 MW connected, 26 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Trostre Grid | 1 | 10 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 10 MW: 10 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Trostre Grid | 6 | 27.3 MW | 44.7 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
6 sites, 72 MW: 27.3 MW connected, 44.7 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Briton Ferry Grid | 1 | 3.1 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 3.1 MW: 3.1 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Briton Ferry Grid | 1 | 0.3 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 0.3 MW: 0.3 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Briton Ferry Grid | 6 | 64.2 MW | 26 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
6 sites, 90.2 MW: 64.2 MW connected, 26 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Ammanford Grid | 1 | 1 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1 MW: 1 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Ammanford Grid | 7 | 91.6 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
7 sites, 91.6 MW: 91.6 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Ystradgynlais Grid | 7 | 15.3 MW | 40.3 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
7 sites, 55.6 MW: 15.3 MW connected, 40.3 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Lampeter Grid | 1 | 10.3 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 10.3 MW: 10.3 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Lampeter Grid | 1 | – | 5 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 5 MW: 5 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Lampeter Grid | 1 | 3.5 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 3.5 MW: 3.5 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Lampeter Grid | 3 | 4.2 MW | 28.9 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 33.1 MW: 4.2 MW connected, 28.9 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Tir John Power Station | 1 | – | 2.5 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 2.5 MW: 2.5 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Tir John Power Station | 1 | 1 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1 MW: 1 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Tir John Power Station | 2 | 33.3 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 33.3 MW: 33.3 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Carmarthen Grid | 1 | – | 9.9 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 9.9 MW: 9.9 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Carmarthen Grid | 4 | 14.1 MW | 9.8 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
4 sites, 23.9 MW: 14.1 MW connected, 9.8 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Llanarth Grid | 1 | – | 17.5 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 17.5 MW: 17.5 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Swansea West Grid | 1 | 1.2 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.2 MW: 1.2 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Swansea West Grid | 1 | 4 MW | – | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 4 MW: 4 MW connected
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 7 | 151 MW | 120 MW | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
7 sites, 271 MW: 151 MW connected, 120 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
What changed recently
Changes to the sites here found in both of two consecutive monthly editions, the latest first.
QueueWatch holds one edition of NGED's register so far, the August 2026 edition, so there is nothing to compare yet.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.