Distribution / Sites / Customer

Infinis Limited

Customer named in the DNOs’ registers

In UKPN’s November 2026, NGED’s August 2026, SSEN’s November 2026 and SPEN’s September 2026 editions

The registers spell this customer’s name more than one way: “Infinis Limited” (10 sites), “Infinis” (6 sites), “Infinis ltd” (6 sites), “INFINIS LIMITED” (4 sites), “INFINIS” (3 sites), “Infinis limited” (2 sites) and “Infinis Ltd” (1 site).

32sites of 1 MW and over
256 MWcapacity
155 MWconnected (24 sites)
101 MWaccepted to connect (8 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
UKPNNovember 2026 edition1387.3 MW46 MW41.3 MW
NGEDAugust 2026 edition954.8 MW15.8 MW39 MW
SSENNovember 2026 edition636.2 MW23.7 MW12.5 MW
SPENSeptember 2026 edition477.3 MW69.3 MW8 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Bioenergy and waste1989.7 MW75.7 MW14 MW
Solar786.8 MW–86.8 MW
Wind266.8 MW66.8 MW–
Other or not stated412.3 MW12.3 MW–

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs’ latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
Minsca WindfarmSPENChapelcrossWindConnected36.8
Dalswinton WindfarmSPENDumfriesWindConnected30
WeldonNGEDGrendon 132Kv S StnSolarAccepted to connect25
(ANM -N/A) Green LaneUKPNSundonSolarAccepted to connect17.3
(ANM) Sandy LaneUKPNWarleySolarAccepted to connect15
SUTTON COURTENAY LANDFILL SITESSENCOWLEY GSPBioenergy and wasteConnected14.25
Bletchley landfill siteNGEDEast Claydon 132Kv S StnBioenergy and wasteAccepted to connect14
The Power Station (S& M)UKPNSundonBioenergy and wasteConnected13.75
SUTTON COURTENAYSSENCOWLEY GSPSolarAccepted to connect12.5
Brogborough Power Station T1, T2, T3, T4UKPNSundonBioenergy and wasteConnected10.5

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
SundonUKPN426.5 MW17.3 MW
ChapelcrossSPEN136.8 MW–
DumfriesSPEN130 MW–
COWLEY GSPSSEN214.3 MW12.5 MW
Grendon 132Kv S StnNGED1–25 MW
WarleyUKPN38.1 MW15 MW
East Claydon 132Kv S StnNGED36.4 MW14 MW
CapenhurstSPEN1–8 MW
WalpoleUKPN1–7 MW
Northfleet EastUKPN16 MW–

What changed recently

Changes to its sites found in both editions of each pair, newest first.

UKPN, October 2026 edition to November 2026 edition, for this customer’s sites: 13 sites matched. Every October site and every November site had a match in the other edition.

Tracking NGED’s register since its August 2026 edition. Changes will show from its next edition.

SSEN, October 2026 edition to November 2026 edition, for this customer’s sites: 6 sites matched. Every October site and every November site had a match in the other edition.

SPEN, August 2026 edition to September 2026 edition, for this customer’s sites: 4 sites matched. Every August site and every September site had a match in the other edition.

  • INFINISSSEN, April 2025 editionTechnology stated as Bioenergy and waste (not stated in the March 2025 edition)
  • INFINIS LIMITEDSSEN, April 2025 editionTechnology stated as Bioenergy and waste (not stated in the March 2025 edition)
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose