Distribution / NGED / Grid supply point

Enderby 132Kv S Stn

Grid supply point in East Midlands

NGED Embedded Capacity Register, August 2026 edition

36sites of 1 MW and over
577 MWcapacity
197 MWconnected (23 sites)
380 MWaccepted to connect (13 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar24446 MW116 MW330 MW
Storage3112 MW62 MW50 MW
Gas and other fossil27.3 MW7.3 MW–
Other or not stated46.2 MW6.2 MW–
Bioenergy and waste23.6 MW3.6 MW–
Wind11.5 MW1.5 MW–

Storage capacity in MWh: not published by NGED.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the August 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Coalville 33Kv S Stn37.5 MW3.6 MW
Coalville 33Kv S Stn26.8 MW–
Coalville 33Kv S Stn1–6 MW
Coalville 33Kv S Stn13.8 MW–
Coalville 33Kv S Stn11.5 MW–
Coalville 33Kv S Stn11.1 MW–
Coalville 33Kv S Stn739 MW78 MW
Wigston 33Kv S Stn33.5 MW1.9 MW
Wigston 33Kv S Stn1–10 MW
Leicester East 33Kv S Stn26.2 MW–
Leicester East 33Kv S Stn13.2 MW–
Leicester 33Kv S Stn16.7 MW–
Wigston 132Kv (M42) 132Kv S Stn13 MW–
Leicester North 33Kv S Stn11.6 MW–
Leicester North 33Kv S Stn11.2 MW–
Not stated9111 MW281 MW

Search and filter all 36 sites at Enderby 132Kv S Stn

What changed recently

Changes to sites here found in both editions of each pair, newest first.

Tracking NGED’s register since its August 2026 edition. Changes will show from its next edition.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.