Barry solar farm
Wallace wood solar farm limited at Aberthaw Power Station
NGED Embedded Capacity Register, August 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 7 Jul 2027
- Status
- Accepted to connect
- Customer
- Wallace wood solar farm limited
- Site name
- Barry solar farm
- Address
- Barry, CF5 6BE
- Grid reference
- Easting 3117284, northing 1714654
- Licence area
- South Wales
- Grid supply point
- Aberthaw Power Station
- Bulk supply point
- Not stated
- Primary substation
- Not stated
- Connection voltage
- 132 kV
- Technology group
- Solar
- Energy source 1
- Solar, Photovoltaic: 42 MW registered
- Registered capacity
- 42 MW
- Change to maximum export capacity
- 42 MW
- Change to maximum import capacity
- 0.5 MW
- Flexible connection
- Not published by NGED
- In a connection queue
- Not published by NGED
- Date accepted
- 1 Oct 2021
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by NGED
- Transmission reinforcement reference
- Not published by NGED
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 6 Aug 2026
- Tracked since
- August 2026 edition
Change history
Tracked since the August 2026 edition, the only one QueueWatch holds so far.
Changes to its status, capacity, technology or customer, newest first.
Changes will show from the next edition.
Also at Aberthaw Power Station
GSP view21 other sites at this grid supply point in the August 2026 edition. In all, the sites here total 259 MW: 75 MW connected, 184 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose