Mynydd y gwair wind farm, felindre, swansea
Rwe renewables uk swindon limited at Swansea North Grid
NGED Embedded Capacity Register, August 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Date connected
- 3 Dec 2018
- Status
- Connected
- Planning consent
- Granted 8 Feb 2013
Swansea, reference 2012/1221 · Source: REPD - Contract for Difference
- Allocation Round 1
- Customer
- Rwe renewables uk swindon limited
- Site name
- Mynydd y gwair wind farm, felindre, swansea
- Address
- Mynydd Y Gwair, Ammanford, Swansea, SA4 8DX
- Grid reference
- Easting 264500, northing 207800
NGED’s register gives it in tenths of a metre. - Licence area
- South Wales
- Grid supply point
- Swansea North Grid
- Bulk supply point
- Not stated
- Primary substation
- Not stated
- Connection voltage
- 132 kV
- Technology group
- Wind
- Energy source 1
- Wind, Onshore wind turbines: 32.8 MW registered
- Registered capacity
- 32.8 MW
- Maximum export capacity
- 31.16 MW
- Maximum import capacity
- 0.19 MW
- Flexible connection
- Not published by NGED
- In a connection queue
- Not published by NGED
- Date accepted
- Not stated
- Target energisation date
- Not stated
- Distribution reinforcement reference
- Not published by NGED
- Transmission reinforcement reference
- Not published by NGED
- Export MPAN
- 2100041453141
- Import MPAN
- 2100041453132
- Last updated
- 6 Aug 2026
- Tracked since
- August 2026 edition
Change history
Tracked since the August 2026 edition, the only one QueueWatch holds so far.
Changes to the details QueueWatch tracks, newest first.
Changes will show from the next edition.
Also at Swansea North Grid
GSP view86 other sites at this grid supply point in the August 2026 edition. In all, the sites here total 1.2 GW: 0.6 GW connected, 0.6 GW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
Planning consent
The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.
How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.
Contract for Difference
The Contracts for Difference allocation round for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition. QueueWatch matched the site to that record.
How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.