Distribution / NGED / Grid supply point

Alverdiscott Sgp

Grid supply point in South West

NGED Embedded Capacity Register, August 2026 edition

80sites of 1 MW and over
1.4 GWcapacity
0.5 GWconnected (60 sites)
0.9 GWaccepted to connect (20 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar54927 MW381 MW546 MW
Wind14238 MW133 MW105 MW
Storage6232 MW7 MW225 MW
Bioenergy and waste37.9 MW7.6 MW0.3 MW
Other or not stated12.7 MW2.7 MW–
Gas and other fossil12 MW2 MW–
Hydro and marine11.3 MW1.3 MW–

Storage capacity in MWh: not published by NGED.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the August 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Pyworthy Bsp21 MW100 MW
Pyworthy Bsp210.1 MW–
Pyworthy Bsp27.7 MW–
Pyworthy Bsp14.9 MW–
Pyworthy Bsp24.3 MW–
Pyworthy Bsp22.3 MW–
Pyworthy Bsp22.2 MW–
Pyworthy Bsp21.9 MW0.2 MW
Pyworthy Bsp21113 MW96 MW
Barnstaple Bsp36.4 MW1.5 MW
Barnstaple Bsp12.5 MW–
Barnstaple Bsp11.3 MW–
Barnstaple Bsp947 MW133 MW
East Yelland Bsp14.2 MW–
East Yelland Bsp14.1 MW–
East Yelland Bsp12 MW–
East Yelland Bsp11.7 MW–
East Yelland Bsp1034.3 MW55.6 MW
Fullabrook Windfarm166 MW–
North Tawton Bsp1–4.9 MW
North Tawton Bsp227 MW–
Not stated12190 MW486 MW

What changed recently

Changes to the sites here found in both of two consecutive monthly editions, the latest first.

QueueWatch holds one edition of NGED's register so far, the August 2026 edition, so there is nothing to compare yet.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.