QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Mill farm

nightshade devco limited at Ratcliffe On Soar 132Kv S Stn

NGED Embedded Capacity Register, August 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
20 May 2027
Status
Accepted to connect
Customer
nightshade devco limited
Site name
Mill farm
Address
Cotes, Loughborough, LE12 5TL
Grid reference
Easting 455721, northing 320648
NGED’s register gives it in tenths of a metre.
Licence area
East Midlands
Grid supply point
Ratcliffe On Soar 132Kv S Stn
Bulk supply point
Loughborough 33Kv S Stn
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 22 MW registered
Registered capacity
22 MW
Change to maximum export capacity
22 MW
Change to maximum import capacity
0.05 MW
Flexible connection
Not published by NGED
In a connection queue
Not published by NGED
Date accepted
20 Jun 2018
Date connected
Not stated
Distribution reinforcement reference
Not published by NGED
Transmission reinforcement reference
Not published by NGED
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
6 Aug 2026
Tracked since
August 2026 edition

Change history

Tracked since the August 2026 edition, the only one QueueWatch holds so far.

Changes to the details QueueWatch tracks, newest first.

Changes will show from the next edition.

Also at Ratcliffe On Soar 132Kv S Stn

GSP view

59 other sites at this grid supply point in the August 2026 edition. In all, the sites here total 2.2 GW: 0.2 GW connected, 2.0 GW accepted to connect.

See all 59

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?