QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

West and east sides of

Nextpower lower strensham limited at Feckenham 66 11Kv S Stn

NGED Embedded Capacity Register, August 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
12 Jan 2029
Status
Accepted to connect
Customer
Nextpower lower strensham limited
Site name
West and east sides of
Address
Baughton Hill, Worcester, WR8 9DT
Grid reference
Easting 3897490000000000, northing 2413480
Licence area
West Midlands
Grid supply point
Feckenham 66 11Kv S Stn
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
66 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 65 MW registered
Energy source 2
Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 13 MW registered
Registered capacity
78 MW
Change to maximum export capacity
0 MW
Change to maximum import capacity
Not stated
Flexible connection
Not published by NGED
In a connection queue
Not published by NGED
Date accepted
29 Nov 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by NGED
Transmission reinforcement reference
Not published by NGED
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
6 Aug 2026
Tracked since
August 2026 edition

Change history

Tracked since the August 2026 edition, the only one QueueWatch holds so far.

Changes to the details QueueWatch tracks, newest first.

Changes will show from the next edition.

Also at Feckenham 66 11Kv S Stn

GSP view

49 other sites at this grid supply point in the August 2026 edition. In all, the sites here total 678 MW: 398 MW connected, 280 MW accepted to connect.

See all 49

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?