Distribution / NGED / Grid supply point

Willington 132Kv S Stn

Grid supply point in East Midlands

NGED Embedded Capacity Register, August 2026 edition

39sites of 1 MW and over
665 MWcapacity
167 MWconnected (28 sites)
498 MWaccepted to connect (11 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar19320 MW42 MW278 MW
Storage4220 MW–220 MW
Gas and other fossil671.9 MW71.9 MW–
Bioenergy and waste531.5 MW31.5 MW–
Wind521.8 MW21.8 MW–

Storage capacity in MWh: not published by NGED.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the August 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Heanor 33Kv S Stn17.2 MW–
Heanor 33Kv S Stn15 MW–
Heanor 33Kv S Stn12.6 MW–
Heanor 33Kv S Stn12.1 MW–
Heanor 33Kv S Stn28 MW40 MW
Spondon B 33Kv S Stn15.2 MW–
Spondon B 33Kv S Stn23.4 MW–
Spondon B 33Kv S Stn11.3 MW–
Spondon B 33Kv S Stn140 MW–
Stanton 33Kv S Stn214.2 MW–
Stanton 33Kv S Stn1–32.9 MW
Uttoxeter 33Kv S Stn36.2 MW–
Uttoxeter 33Kv S Stn14.2 MW–
Uttoxeter 33Kv S Stn13.9 MW–
Uttoxeter 33Kv S Stn417.8 MW–
Winster 33Kv S Stn212.7 MW–
Winster 33Kv S Stn21.5 MW2.6 MW
Winster 33Kv S Stn12.5 MW–
Winster 33Kv S Stn14.4 MW–
Derby South 33Kv S Stn119.5 MW–
Derby 33Kv S Stn15 MW–
Derby 33Kv S Stn1–10 MW
Burnaston 132Kv S Stn1–13.5 MW
Not stated6–399 MW

What changed recently

Changes to the sites here found in both of two consecutive monthly editions, the latest first.

QueueWatch holds one edition of NGED's register so far, the August 2026 edition, so there is nothing to compare yet.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.