QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Mercedes amg high performance powertrains ltd

Mercedes amg high performance powertrains ltd at Grendon 132Kv S Stn

NGED Embedded Capacity Register, August 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
1 Jan 2026
Status
Connected
Customer
Mercedes amg high performance powertrains ltd
Site name
Mercedes amg high performance powertrains ltd
Address
Mercedes A M G High Performance P Export, Morgan Drive, Brixworth, Northampton, Northamptonshire, NN6 9GZ
Grid reference
Easting 475341, northing 271374
Licence area
East Midlands
Grid supply point
Grendon 132Kv S Stn
Bulk supply point
Northampton West 33Kv S Stn
Primary substation
Chapel Brampton 33 11Kv S Stn
Connection voltage
11 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 2.876 MW registered
Energy source 2
Stored Energy (all stored energy irrespective of the original energy source), Storage - Thermal: 1.5 MW registered
Registered capacity
4.376 MW
Maximum export capacity
3.876 MW
Maximum import capacity
12.92 MW
Flexible connection
Not published by NGED
In a connection queue
Not published by NGED
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by NGED
Transmission reinforcement reference
Not published by NGED
Export MPAN
1170000968736/1170000968745
Import MPAN
1100050836492/1100051092479
Last updated
6 Aug 2026
Tracked since
August 2026 edition

Change history

Tracked since the August 2026 edition, the only one QueueWatch holds so far.

Changes to its status, capacity, technology or customer, newest first.

Changes will show from the next edition.

Also at Grendon 132Kv S Stn

GSP view

80 other sites at this grid supply point in the August 2026 edition, 1 of them at Chapel Brampton 33 11Kv S Stn, the same primary substation. In all, the sites here total 2 GW: 0.4 GW connected, 1.6 GW accepted to connect.

See all 80

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose