QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / Sites / Customer

LOW CARBON UK SOLAR INVESTMENT COMPANY LIMITED

Customer named in the DNOs' registers

In UKPN's October 2026, NGED's August 2026, SSEN's September 2026 and SPEN's September 2026 editions

The registers spell this customer’s name more than one way: “LOW CARBON UK SOLAR INVESTMENT COMPANY LIMITED” (8 sites), “Low Carbon UK Solar Investment Company Limited” (4 sites), “Low Carbon UK Solar Investment Company Ltd” (1 site) and “Low carbon uk solar investment company l” (1 site).

14sites of 1 MW and over
426 MWcapacity
–connected (0 sites)
426 MWaccepted to connect (14 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
UKPNOctober 2026 edition487 MW–87 MW
NGEDAugust 2026 edition130 MW–30 MW
SSENSeptember 2026 edition8243 MW–243 MW
SPENSeptember 2026 edition166 MW–66 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar12379 MW–379 MW
Storage247 MW–47 MW

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs' latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
Badgers Energy CentreSPENCheshire ESolarAccepted to connect66
HASELEY SOLAR FARM - SOLAR PVSSENCOWLEY GSPSolarAccepted to connect50
SOLAR PV AND BATTERY 50MW IMPORT 50MW EXPORTSSENMELKSHAM GSPSolarAccepted to connect50
PART HAVELEYS SOLAR PARKSSENEAST CLAYDON GSPSolarAccepted to connect45.5
KIMPTON WOOD SOLAR FARMSSENBRAMLEY (THAT-AMES)SolarAccepted to connect42.7
Green Lane Solar FarmUKPNNorthfleet EastSolarAccepted to connect40
Inkersall road solar farmNGEDChesterfield 132Kv S StnStorageAccepted to connect30
HARLESFORD SOLAR FARMSSENCOWLEY GSPSolarAccepted to connect20
Napoleon Solar FarmUKPNNorthfleet EastSolarAccepted to connect20
Shearwater Solar FarmUKPNNinfieldStorageAccepted to connect17

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
COWLEY GSPSSEN2–70 MW
Cheshire ESPEN1–66 MW
Northfleet EastUKPN2–60 MW
MELKSHAM GSPSSEN1–50 MW
EAST CLAYDON GSPSSEN1–45.5 MW
BRAMLEY (THAT-AMES)SSEN1–42.7 MW
Chesterfield 132Kv S StnNGED1–30 MW
MANNINGTON GSPSSEN2–19.8 MW
NinfieldUKPN1–17 MW
FAWLEY GSPSSEN1–15 MW

What changed recently

Changes to its sites found in both of two consecutive monthly editions of their DNO's register, the latest first.

UKPN, September 2026 edition to October 2026 edition, for this customer's sites: 4 sites matched. Every September site and every October site had a match in the other edition.

NGED: QueueWatch holds one edition of its register so far, the August 2026 edition, so there is nothing to compare yet.

SSEN, August 2026 edition to September 2026 edition, for this customer's sites: 8 sites matched. Every August site and every September site had a match in the other edition.

SPEN, August 2026 edition to September 2026 edition, for this customer's sites: 1 site matched. Every August site and every September site had a match in the other edition.

No change to the status, capacity, technology or customer of its sites in the editions QueueWatch holds.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose