Distribution / NGED / Grid supply point

Bushbury D 132Kv

Grid supply point in West Midlands

NGED Embedded Capacity Register, August 2026 edition

23sites of 1 MW and over
564 MWcapacity
106 MWconnected (10 sites)
458 MWaccepted to connect (13 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar13292 MW11 MW281 MW
Storage4177 MW–177 MW
Gas and other fossil357.3 MW57.3 MW–
Bioenergy and waste134 MW34 MW–
Wind24 MW4 MW–

Storage capacity in MWh: not published by NGED.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the August 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Stafford 132 25Kv S Stn136 MW–
Stafford 132 25Kv S Stn1–49.5 MW
Bushbury C 132Kv S Stn540.6 MW4.9 MW
Bushbury C 132Kv S Stn24.1 MW9 MW
Bushbury C 132Kv S Stn36 MW–
Wednesfield 132Kv S Stn119.3 MW–
Not stated10–395 MW

Search and filter all 23 sites at Bushbury D 132Kv

What changed recently

Changes to sites here found in both editions of each pair, newest first.

Tracking NGED’s register since its August 2026 edition. Changes will show from its next edition.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.