What changed in the DNOs’ registers
Changes to sites found in both editions of each pair, by DNO, newest first: 1,171 changes across 57 pairs of editions.
When a connection date moves, so does what a project is worth. Read our study: Sell now, or wait for your Gate 2 offer?
UK Power Networks
UKPN’s pageOctober 2026 edition to November 2026 edition
101 changes
1,025 sites matched. 14 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- ((ANM) Stow RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
- (ANM) 68-70 Reach RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 31 Oct 2031 (36 months later)
- (ANM) Abbotsley RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 31 Oct 2031 (36 months later)
- (ANM) Ashwell RoadEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Mar 2026 (15 months later)
- (ANM) Beerhouse FarmEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- (ANM) Bracon AshEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- (ANM) Bunwell RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- (ANM) Bushmead RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
- (ANM) ChelmsfordEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
- (ANM) Childerley HallEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 31 Oct 2031 (36 months later)
- (ANM) Crays Hall FarmEastern Power Networks (EPN)Target energisation date moved from 30 Jun 2025 to 10 Dec 2025 (5 months later)
- (ANM) Crows LaneEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
- (ANM) East Tilbury QuarryEastern Power Networks (EPN)Target energisation date moved from 30 Oct 2030 to 11 Jan 2032 (14 months later)
- (ANM) Fallow Solar FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
- (ANM) Green EndEastern Power Networks (EPN)Target energisation date stated as 31 Oct 2034 (not stated in the October 2026 edition)
- (ANM) Kestrel Solar FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
- (ANM) Kingsey Solar FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Dec 2025 (12 months later)
- (ANM) Land At Cressing FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Mar 2026 (15 months later)
- (ANM) Land At Warmans FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
- (ANM) Land East Of Drayton LaneEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- (ANM) Land North Of Bassmead ManorEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
- (ANM) Land Off Twinwood RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
- (ANM) Land On The South East Side Of Wilsons RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 31 Oct 2031 (36 months later)
- (ANM) Land South Of A47Eastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- (ANM) Marshes Burnham-On-CrouchEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
- (ANM) North West Of Kimblewick RoadEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Dec 2025 (12 months later)
- (ANM) Parkgate FarmEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 31 Mar 2026 (15 months later)
- (ANM) Rowley Hill RoadEastern Power Networks (EPN)Target energisation date moved from 12 Jan 2024 to 31 Oct 2026 (34 months later)
- (ANM) South Woodham FerrersEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
- (ANM) SS17 9LL The ManorwayEastern Power Networks (EPN)Target energisation date moved from 30 Nov 2024 to 30 Nov 2025 (12 months later)
- (ANM) Vicarage LaneEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
- (ANM) Water Hall FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
- (ANM) Weirs Drove 2Eastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 31 Oct 2031 (36 months later)
- (ANM)Foxholes FarmEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
- Bank Farm SolarSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2025 to 31 Dec 2028 (47 months later)
- Bentley EstateSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
- Berden Hall Farm PVEastern Power Networks (EPN)Target energisation date moved from 20 Jun 2025 to 31 Mar 2027 (21 months later)
- Bockingfold FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 24 Apr 2025 to 11 Jul 2025 (3 months later)
- Bolney SolarSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
- Boreham StreetSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2029 to 31 Dec 2031 (35 months later)
- Brogborough Solar FarmEastern Power Networks (EPN)Target energisation date stated as 23 Nov 2026 (not stated in the October 2026 edition)
- Broomfield Solar FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 18 Oct 2027 to 28 Oct 2027 (10 days later)
- Broomfield Solar FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
- Cards RoadEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
- Chalgrave ManorEastern Power Networks (EPN)Target energisation date moved from 31 Mar 2025 to 31 Oct 2028 (43 months later)
- Common Barn Wind Farm Phase 2Eastern Power Networks (EPN)Target energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
- Coombe FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2029 to 31 Oct 2027 (15 months earlier)
- Dereham RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- Discovery ParkSouth Eastern Power Networks (SPN)Target energisation date stated as 4 Jan 2026 (not stated in the October 2026 edition)
- Envirtotech 3South Eastern Power Networks (SPN)Target energisation date moved from 31 Oct 2026 to 28 Oct 2027 (12 months later)
- Fambridge FarmEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
- FDG F-02 Land At Chittering DroveEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 30 Sep 2025 (9 months later)
- Gabriel Spring RoadSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2025 to 31 Oct 2027 (33 months later)
- Gatwick Airport Electric ForecourtSouth Eastern Power Networks (SPN)Target energisation date not stated (30 Sep 2024 in the October 2026 edition)
- Great Wheatley Solar FarmEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
- Guildford STWSouth Eastern Power Networks (SPN)Target energisation date moved from 30 Apr 2025 to 10 Jul 2025 (2 months later)
- Hale Farm, HulcottEastern Power Networks (EPN)Target energisation date moved from 30 May 2025 to 31 Oct 2028 (41 months later)
- Halewick LaneSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2024 to 18 Dec 2026 (24 months later)
- Highfield FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Sep 2026 (21 months later)
- Horton Wood Solar FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Oct 2025 to 20 Jun 2026 (8 months later)
- Ironsbottom Solar FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
- Isle Of GrainSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2024 to 31 Dec 2025 (12 months later)
- Kentish Farm 1Eastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 31 Oct 2030 (70 months later)
- Kentish Farm 2Eastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 31 Oct 2030 (70 months later)
- Kingsey Solar FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 30 Apr 2026 (16 months later)
- Kingsnorth Power StationSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2024 to 31 Oct 2026 (22 months later)
- Knowl Green FarmEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 31 Jul 2026 (19 months later)
- Land At Harp FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 30 Apr 2025 to 31 Oct 2027 (30 months later)
- Land At Priesthawes FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
- Land At Redcoats FarmEastern Power Networks (EPN)Target energisation date moved from 28 Apr 2028 to 31 Oct 2029 (18 months later)
- Land Near Hadham RdEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2028 to 31 Oct 2029 (10 months later)
- Land To The North Of Sewage WorksSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2024 to 31 Oct 2026 (22 months later)
- Little Flanchford FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
- Lower Dunton RoadEastern Power Networks (EPN)Target energisation date not stated (30 Oct 2024 in the October 2026 edition)
- Maggotts EndEastern Power Networks (EPN)Target energisation date moved from 12 Jan 2024 to 31 Oct 2029 (70 months later)
- Marden GenerationSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Mar 2025 to 9 Jan 2027 (21 months later)
- Mathurst Farm SolarSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Mar 2029 to 31 Dec 2031 (33 months later)
- Merton CollegeSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Mar 2025 to 31 Oct 2027 (31 months later)
- Northfleet East GridSouth Eastern Power Networks (SPN)Target energisation date moved from 30 Jun 2025 to 31 Oct 2025 (4 months later)
- Offham QuarrySouth Eastern Power Networks (SPN)Export capacity stated as 9.5 MW (not stated in the October 2026 edition)
- Offham QuarrySouth Eastern Power Networks (SPN)Target energisation date not stated (30 Apr 2025 in the October 2026 edition)
- Olives FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2027 (36 months earlier)
- Ouse Valley SolarSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
- Ph 2 Cu-Mining DagenhamEastern Power Networks (EPN)Target energisation date moved from 31 Dec 2024 to 3 Mar 2026 (14 months later)
- Quakers HouseEastern Power Networks (EPN)Target energisation date moved from 15 Nov 2025 to 31 Oct 2028 (36 months later)
- Rayleigh SiteEastern Power Networks (EPN)Target energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
- Richborough Energy ParkSouth Eastern Power Networks (SPN)Target energisation date moved from 30 Jun 2025 to 3 Jan 2026 (6 months later)
- Rowley LaneEastern Power Networks (EPN)Target energisation date not stated (31 Oct 2033 in the October 2026 edition)
- School LaneSouth Eastern Power Networks (SPN)Target energisation date moved from 30 Jan 2025 to 10 Jan 2026 (11 months later)
- Shearwater Solar FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2029 to 31 Dec 2031 (35 months later)
- Slyfield FarmSouth Eastern Power Networks (SPN)Target energisation date moved from 1 Jan 2025 to 31 Jan 2029 (49 months later)
- Southfleet Hook GreenSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Dec 2027 to 15 Oct 2027 (3 months earlier)
- Tring RoadEastern Power Networks (EPN)Target energisation date moved from 31 Oct 2024 to 31 Oct 2028 (48 months later)
- Vigo Lane Solar ParkSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Jan 2029 to 31 Dec 2031 (35 months later)
- Wealden WorksSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Oct 2025 to 31 Oct 2026 (12 months later)
- West Thaxted Solar FarmEastern Power Networks (EPN)Target energisation date moved from 12 Jan 2024 to 1 Dec 2025 (23 months later)
- Wharf RoadEastern Power Networks (EPN)Target energisation date moved from 13 Mar 2025 to 30 Mar 2026 (13 months later)
- Wickham HallEastern Power Networks (EPN)Target energisation date moved from 12 Jan 2024 to 1 Dec 2025 (23 months later)
- Wickham HallEastern Power Networks (EPN)Target energisation date moved from 6 Jun 2025 to 6 Jun 2026 (12 months later)
- Wineham LaneSouth Eastern Power Networks (SPN)Target energisation date moved from 31 Oct 2026 to 31 Oct 2027 (12 months later)
- Woburn RoadEastern Power Networks (EPN)Target energisation date not stated (22 Dec 2025 in the October 2026 edition)
14 sites without a match in the other edition
In the November 2026 edition only (3)
In the October 2026 edition only (11)
September 2026 edition to October 2026 edition
14 changes
1,033 sites matched. 11 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Enterprise PowerSouth Eastern Power Networks (SPN)Capacity changed from 5 MW to 5.07 MW+0.07 MW
- Enterprise PowerSouth Eastern Power Networks (SPN)Export capacity changed from 5 MW to 5.07 MW
- Francis WoodSouth Eastern Power Networks (SPN)Capacity changed from 4.4 MW to 7 MW+2.6 MW
- Francis WoodSouth Eastern Power Networks (SPN)Export capacity changed from 4.4 MW to 7 MW
- Lower Dunton RoadEastern Power Networks (EPN)Customer changed from Conrad Energy Limited to Conrad (Lower Dunton) Limited
- Olives FarmSouth Eastern Power Networks (SPN)Capacity changed from 75 MW to 49.9 MW−25.1 MW
- Olives FarmSouth Eastern Power Networks (SPN)Export capacity changed from 75 MW to 49.9 MW
- PV Solar (Carlton Farm)Eastern Power Networks (EPN)Capacity changed from 5.5 MW to 5 MW−0.5 MW
- PV Solar (Carlton Farm)Eastern Power Networks (EPN)Export capacity changed from 5.5 MW to 5 MW
- Tilbury Docks Ph2Eastern Power Networks (EPN)Capacity changed from 20 MW to 40 MW+20 MW
- Tilbury Docks Ph2Eastern Power Networks (EPN)Customer changed from ESB International to Thameside Energy Recovery Facility Limited 2021
- Tilbury Docks Ph2Eastern Power Networks (EPN)Export capacity changed from 20 MW to 40 MW
- Westgate PowerSouth Eastern Power Networks (SPN)Capacity changed from 5.34 MW to 5.33 MW−0.01 MW
- Westgate PowerSouth Eastern Power Networks (SPN)Export capacity changed from 5.34 MW to 5.33 MW
11 sites without a match in the other edition
In the October 2026 edition only (3)
In the September 2026 edition only (8)
National Grid Electricity Distribution
NGED’s pageTracking NGED’s register since its August 2026 edition. Changes will show from its next edition.
Scottish and Southern Electricity Networks
SSEN’s pageOctober 2026 edition to November 2026 edition
37 changes
1,290 sites matched. 19 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 30MW PV & 30MW BESSSouthern England (SEPD)Export capacity changed from 31.579 MW to 60 MW
- 99.9MW BESS CHRISTCHURCH ROAD STORAGESouthern England (SEPD)Export capacity changed from 99.9 MW to 105.158 MW
- ALLT DOMHAIN WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 64.8 MW to 0.1 MW
- ARNISH COMMUNITY WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 38.92 MW to 0.41 MW
- BALGONIE FARM 50MW BATTERYNorth of Scotland (SHEPD)Export capacity changed from 50 MW to 52.68 MW
- BEINN NAN LOCHAN WINDNorth of Scotland (SHEPD)Export capacity changed from 0.539 MW to 35 MW
- BINSTEAD FARMSouthern England (SEPD)Export capacity changed from 4.9 MW to 12.174 MW
- BUNLOINN WIND FARM AND BESSNorth of Scotland (SHEPD)Export capacity changed from 5.5 MW to 71.6 MW
- CASTLECRAIG FARMSNorth of Scotland (SHEPD)Export capacity changed from 15 MW to 0.15 MW
- CHARLESTON SOLAR 20MW PVNorth of Scotland (SHEPD)Export capacity changed from 0.25 MW to 20 MW
- CLACHAIG WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 52.8 MW to 0.204 MW
- CROMLET HILL WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 1.2 MW to 60 MW
- CRUCIS PARK ESTATE LLPSouthern England (SEPD)Export capacity changed from 11 MW to 12.6 MW
- DENHEAD SOLAR MACDUFF GSPNorth of Scotland (SHEPD)Export capacity changed from 20 MW to 0.1 MW
- DOWN AMPNEY AIRFIELD QUARRYSouthern England (SEPD)Export capacity changed from 0.499 MW to 2.45 MW
- DRUMFORSKIE PVNorth of Scotland (SHEPD)Export capacity changed from 0.05 MW to 2 MW
- EDAY TIDAL DEVELOPMENTSNorth of Scotland (SHEPD)Export capacity changed from 4.8 MW to 0.1 MW
- ETON COLLEGE PVSouthern England (SEPD)Export capacity changed from 3.96 MW to 0.05 MW
- EYNSHAM ESTATE - PV & BESSSouthern England (SEPD)Export capacity changed from 52.526 MW to 100 MW
- FACCOMBE ESTATESouthern England (SEPD)Export capacity changed from 2.425 MW to 0.53 MW
- GARBHAIG HYDRONorth of Scotland (SHEPD)Export capacity changed from 0.04 MW to 1 MW
- HAMPRESTON SOLAR FARMSouthern England (SEPD)Export capacity changed from 40 MW to 0.421 MW
- HILLHEAD OF GASK PV AND BESSNorth of Scotland (SHEPD)Export capacity changed from 14.2 MW to 5.8 MW
- INVERTER CHANGESouthern England (SEPD)Export capacity changed from 3.64 MW to 0 MW
- LUGGIES KNOWENorth of Scotland (SHEPD)Export capacity changed from 0.2 MW to 4.2 MW
- MORENISHNorth of Scotland (SHEPD)Export capacity changed from 49.4 MW to 52 MW
- MOUNT BLAIRY SOLAR FARM BROWNSIDE FARMNorth of Scotland (SHEPD)Export capacity changed from 35.2 MW to 0.8 MW
- NORTH HOO FIELD LTDNorth of Scotland (SHEPD)Export capacity changed from 2.3 MW to 0.15 MW
- PEATTIE FARM PVNorth of Scotland (SHEPD)Export capacity changed from 0.8 MW to 49.7 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 85.5 MW to 73.684 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 1.155 MW to 1.797 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 8.112 MW to 0 MW
- STRATH TIRRY WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 35 MW to 0.317 MW
- TRINITY FARMSouthern England (SEPD)Export capacity changed from 100.1 MW to 84.211 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 1.9 MW to 2.4 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 0 MW to 4.949 MW
- WESTFIELD SOLAR & STORAGENorth of Scotland (SHEPD)Export capacity changed from 52.631 MW to 50 MW
19 sites without a match in the other edition
In the November 2026 edition only (8)
In the October 2026 edition only (11)
September 2026 edition to October 2026 edition
33 changes
1,291 sites matched. 20 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 100MW BESSSouthern England (SEPD)Export capacity changed from 100 MW to 105.263 MW
- 5.88MW BESSSouthern England (SEPD)Export capacity changed from 5.88 MW to 4.99 MW
- 6MVA IMPORT LOAD & 577KW PVSouthern England (SEPD)Target energisation date moved from 5 Jul 2027 to 20 Aug 2027 (1 month later)
- ARNISH COMMUNITY WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0.41 MW to 38.92 MW
- BEINN NAN LOCHAN WINDNorth of Scotland (SHEPD)Export capacity changed from 35 MW to 0.539 MW
- BINSTEAD FARMSouthern England (SEPD)Export capacity changed from 12.174 MW to 4.9 MW
- BISHOPS SUTTONSouthern England (SEPD)Export capacity changed from 0.105 MW to 5.4 MW
- BRANSBURY MANOR FARMSouthern England (SEPD)Export capacity changed from 5.263 MW to 10 MW
- BUNLOINN WIND FARM AND BESSNorth of Scotland (SHEPD)Export capacity changed from 71.6 MW to 5.5 MW
- CHARLESTON SOLAR 20MW PVNorth of Scotland (SHEPD)Export capacity changed from 20 MW to 0.25 MW
- CRUCIS PARK ESTATE LLPSouthern England (SEPD)Export capacity changed from 12.6 MW to 11 MW
- DOWN AMPNEY AIRFIELD QUARRYSouthern England (SEPD)Export capacity changed from 2.45 MW to 0.499 MW
- EDAY TIDAL DEVELOPMENTSNorth of Scotland (SHEPD)Export capacity changed from 0.1 MW to 4.8 MW
- INVERCANNIE WATERWORKS PVNorth of Scotland (SHEPD)Export capacity changed from 0 MW to 1.88 MW
- INVERTER CHANGESouthern England (SEPD)Export capacity changed from 0 MW to 3.64 MW
- KINNELLS MILL PVNorth of Scotland (SHEPD)Export capacity changed from 0.05 MW to 9.9 MW
- LITTLE BARRAS FARM PV & BESSNorth of Scotland (SHEPD)Export capacity changed from 74 MW to 0.42 MW
- MOUNT BLAIRY SOLAR FARM BROWNSIDE FARMNorth of Scotland (SHEPD)Export capacity changed from 0.8 MW to 35.2 MW
- PEATTIE FARM PVNorth of Scotland (SHEPD)Export capacity changed from 49.7 MW to 0.8 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 1.4 MW to 1.9 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 0 MW to 1.574 MW
- SPRING FARMSouthern England (SEPD)Export capacity changed from 0.105 MW to 13.2 MW
- STAGECOACHSouthern England (SEPD)Export capacity changed from 3.7 MW to 2.2 MW
- STRATH TIRRY WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0.317 MW to 35 MW
- SWECO UK LTDSouthern England (SEPD)Export capacity changed from 105.6 MW to 104.211 MW
- TERTIARY STUDYSouthern England (SEPD)Export capacity changed from 57 MW to 60 MW
- TRINITY FARMSouthern England (SEPD)Export capacity changed from 84.211 MW to 100.1 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 2.4 MW to 1.9 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 4.949 MW to 0 MW
- WARDHILL FARM BESSNorth of Scotland (SHEPD)Export capacity changed from 49.9 MW to 50 MW
- WELLBECK HEALTH CENTRESouthern England (SEPD)Export capacity changed from 0.7 MW to 1 MW
- WELLS FOREST FARM 25MWNorth of Scotland (SHEPD)Export capacity changed from 50.16 MW to 26.5 MW
- WESTFIELD SOLAR & STORAGENorth of Scotland (SHEPD)Export capacity changed from 50 MW to 52.631 MW
20 sites without a match in the other edition
In the October 2026 edition only (10)
In the September 2026 edition only (10)
August 2026 edition to September 2026 edition
43 changes
1,293 sites matched. 20 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 30MW PV & 30MW BESSSouthern England (SEPD)Export capacity changed from 60 MW to 31.579 MW
- 9.9MW 33KV POC REQUESTEDSouthern England (SEPD)Export capacity changed from 10.421 MW to 9.9 MW
- 99.9MW BESS CHRISTCHURCH ROAD STORAGESouthern England (SEPD)Export capacity changed from 105.158 MW to 99.9 MW
- 99.9MW BESS TITCHFIELD LANESouthern England (SEPD)Export capacity changed from 105.263 MW to 100 MW
- ALLT DOMHAIN WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0.1 MW to 64.8 MW
- ALLT NA MOINE HYDRO - IMPORT ADDCAPNorth of Scotland (SHEPD)Export capacity changed from 3.093 MW to 4.99 MW
- BALGONIE FARM 50MW BATTERYNorth of Scotland (SHEPD)Export capacity changed from 52.68 MW to 50 MW
- BANKHEAD PV & WINDNorth of Scotland (SHEPD)Export capacity changed from 2.8 MW to 3.5 MW
- BEINN NAN LOCHAN WINDNorth of Scotland (SHEPD)Export capacity changed from 0.539 MW to 35 MW
- BRANSBURY MANOR FARMSouthern England (SEPD)Export capacity changed from 10 MW to 5.263 MW
- BUCKLAND RIPERS 20MW PV & BESSSouthern England (SEPD)Export capacity changed from 45 MW to 0.526 MW
- CHARLESTON SOLAR 20MW PVNorth of Scotland (SHEPD)Export capacity changed from 0.25 MW to 20 MW
- CHRATHAICH WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0.632 MW to 62.4 MW
- CLACHAIG WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0.204 MW to 52.8 MW
- CROMLET HILL WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 60 MW to 1.2 MW
- CRUCIS PARK ESTATE LLPSouthern England (SEPD)Export capacity changed from 11 MW to 12.6 MW
- DENHEAD SOLAR MACDUFF GSPNorth of Scotland (SHEPD)Export capacity changed from 0.1 MW to 20 MW
- DOWN AMPNEY AIRFIELD QUARRYSouthern England (SEPD)Export capacity changed from 0.499 MW to 2.45 MW
- DRUIDS LODGE ESTATESouthern England (SEPD)Export capacity changed from 0.316 MW to 61.56 MW
- DRUMFORSKIE PVNorth of Scotland (SHEPD)Export capacity changed from 2 MW to 0.05 MW
- EDAY TIDAL DEVELOPMENTSNorth of Scotland (SHEPD)Export capacity changed from 4.8 MW to 0.1 MW
- ETON COLLEGE PVSouthern England (SEPD)Export capacity changed from 0.05 MW to 3.96 MW
- FACCOMBE ESTATESouthern England (SEPD)Export capacity changed from 0.53 MW to 2.425 MW
- GARBHAIG HYDRONorth of Scotland (SHEPD)Export capacity changed from 1 MW to 0.04 MW
- HAMPRESTON SOLAR FARMSouthern England (SEPD)Export capacity changed from 0.421 MW to 40 MW
- INVERCANNIE WATERWORKS PVNorth of Scotland (SHEPD)Export capacity changed from 1.88 MW to 0 MW
- KINLOSS BARRACKS PVNorth of Scotland (SHEPD)Export capacity changed from 2.64 MW to 0 MW
- LITTLE BARRAS FARM PV & BESSNorth of Scotland (SHEPD)Export capacity changed from 0.42 MW to 74 MW
- MELVICH WIND ENERGY HUBNorth of Scotland (SHEPD)Export capacity changed from 86.4 MW to 45.474 MW
- MORENISHNorth of Scotland (SHEPD)Export capacity changed from 52 MW to 49.4 MW
- NORTH HOO FIELD LTDNorth of Scotland (SHEPD)Export capacity changed from 0.15 MW to 2.3 MW
- PURTON SOLAR FARMSouthern England (SEPD)Export capacity changed from 0 MW to 3.2 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 0.105 MW to 20 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 73.684 MW to 85.5 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 1.789 MW to 11.8 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 1.9 MW to 1.4 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 0 MW to 8.112 MW
- STONEYHILL FARM 49.9MWNorth of Scotland (SHEPD)Export capacity changed from 99.95 MW to 52.53 MW
- STRATH TIRRY WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 35 MW to 0.317 MW
- SWECO UK LTDSouthern England (SEPD)Export capacity changed from 104.211 MW to 105.6 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 1.9 MW to 2.4 MW
- WELLBECK HEALTH CENTRESouthern England (SEPD)Export capacity changed from 1 MW to 0.7 MW
- WESTFIELD SOLAR & STORAGENorth of Scotland (SHEPD)Export capacity changed from 52.631 MW to 50 MW
20 sites without a match in the other edition
In the September 2026 edition only (8)
In the August 2026 edition only (12)
July 2026 edition to August 2026 edition
33 changes
1,299 sites matched. 14 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 99.9MW BESS TITCHFIELD LANESouthern England (SEPD)Export capacity changed from 100 MW to 105.263 MW
- ARBORFIELD PVSouthern England (SEPD)Capacity changed from 10.45 MW to 13.999 MW+3.549 MW
- ARBORFIELD PVSouthern England (SEPD)Export capacity changed from 10.45 MW to 13.999 MW
- ARNISH COMMUNITY WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 38.92 MW to 0.41 MW
- BANKHEAD PV & WINDNorth of Scotland (SHEPD)Export capacity changed from 3.5 MW to 2.8 MW
- BEINN NAN LOCHAN WINDNorth of Scotland (SHEPD)Export capacity changed from 35 MW to 0.539 MW
- BINSTEAD FARMSouthern England (SEPD)Export capacity changed from 4.9 MW to 12.174 MW
- BUNLOINN WIND FARM AND BESSNorth of Scotland (SHEPD)Export capacity changed from 5.5 MW to 71.6 MW
- CRACKA LONGI WINDNorth of Scotland (SHEPD)Export capacity changed from 8.421 MW to 8.4 MW
- CROMLET HILL WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 1.2 MW to 60 MW
- CRUCIS PARK ESTATE LLPSouthern England (SEPD)Export capacity changed from 12.6 MW to 11 MW
- DRUMFORSKIE PVNorth of Scotland (SHEPD)Export capacity changed from 0.05 MW to 2 MW
- ETON COLLEGE PVSouthern England (SEPD)Export capacity changed from 3.96 MW to 0.05 MW
- GLENKILN FARMNorth of Scotland (SHEPD)Export capacity changed from 4 MW to 0.1 MW
- HAMPRESTON SOLAR FARMSouthern England (SEPD)Export capacity changed from 40 MW to 0.421 MW
- INVERCANNIE WATERWORKS PVNorth of Scotland (SHEPD)Export capacity changed from 0 MW to 1.88 MW
- INVERTER CHANGESouthern England (SEPD)Export capacity changed from 3.64 MW to 0 MW
- LITTLE BARRAS FARM PV & BESSNorth of Scotland (SHEPD)Export capacity changed from 74 MW to 0.42 MW
- MOUNT BLAIRY SOLAR FARM BROWNSIDE FARMNorth of Scotland (SHEPD)Export capacity changed from 35.2 MW to 0.8 MW
- NORTH HOO FIELD LTDNorth of Scotland (SHEPD)Export capacity changed from 2.3 MW to 0.15 MW
- PEATTIE FARM PVNorth of Scotland (SHEPD)Export capacity changed from 0.8 MW to 49.7 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 1.4 MW to 1.9 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 8.112 MW to 0 MW
- SPRING FARMSouthern England (SEPD)Export capacity changed from 13.2 MW to 0.105 MW
- STAGECOACHSouthern England (SEPD)Export capacity changed from 2.2 MW to 3.7 MW
- STONEYHILL FARM 49.9MWNorth of Scotland (SHEPD)Export capacity changed from 52.53 MW to 99.95 MW
- STRATH TIRRY WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0.317 MW to 35 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 2.4 MW to 1.9 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 0 MW to 4.949 MW
- WERRAR FARMSouthern England (SEPD)Export capacity changed from 45 MW to 9.474 MW
- WESTFIELD SOLAR & STORAGENorth of Scotland (SHEPD)Export capacity changed from 50 MW to 52.631 MW
- WITH CCMNorth of Scotland (SHEPD)Export capacity changed from 0.5 MW to 36.72 MW
- WITH CCM - DGENNorth of Scotland (SHEPD)Export capacity changed from 52.6 MW to 25 MW
14 sites without a match in the other edition
In the August 2026 edition only (6)
In the July 2026 edition only (8)
June 2026 edition to July 2026 edition
38 changes
1,300 sites matched. 22 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 100MW BESSSouthern England (SEPD)Export capacity changed from 105.263 MW to 100 MW
- 30MW PV & 30MW BESSSouthern England (SEPD)Export capacity changed from 31.579 MW to 60 MW
- 4.8MW TIDALNorth of Scotland (SHEPD)Flexible connection stated as “yes” (not stated in the June 2026 edition)
- 56.8MW - LOCH NAN CUILLE WINDNorth of Scotland (SHEPD)Export capacity changed from 56.8 MW to 0.321 MW
- 9.9MW 33KV POC REQUESTEDSouthern England (SEPD)Export capacity changed from 9.9 MW to 10.421 MW
- 99.9MW BESS CHRISTCHURCH ROAD STORAGESouthern England (SEPD)Export capacity changed from 99.9 MW to 105.158 MW
- 99.9MW BESS TITCHFIELD LANESouthern England (SEPD)Export capacity changed from 105.263 MW to 100 MW
- ALLT DOMHAIN WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 64.8 MW to 0.1 MW
- BAKER BARRACKS - PVSouthern England (SEPD)Flexible connection stated as “yes” (not stated in the June 2026 edition)
- BANKHEAD PV & WINDNorth of Scotland (SHEPD)Export capacity changed from 2.8 MW to 3.5 MW
- BEINN NAN LOCHAN WINDNorth of Scotland (SHEPD)Export capacity changed from 0.539 MW to 35 MW
- BINSTEAD FARMSouthern England (SEPD)Export capacity changed from 12.174 MW to 4.9 MW
- BISHOPS SUTTONSouthern England (SEPD)Export capacity changed from 5.4 MW to 0.105 MW
- BLOUNTS COURT FARMSouthern England (SEPD)Flexible connection stated as “yes” (not stated in the June 2026 edition)
- BRANSBURY MANOR FARMSouthern England (SEPD)Export capacity changed from 5.263 MW to 10 MW
- CAIRNBROGIE WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0 MW to 4.1 MW
- CHRATHAICH WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 62.4 MW to 0.632 MW
- CRUCIS PARK ESTATE LLPSouthern England (SEPD)Export capacity changed from 11 MW to 12.6 MW
- DENHEAD SOLAR MACDUFF GSPNorth of Scotland (SHEPD)Export capacity changed from 20 MW to 0.1 MW
- INVERCANNIE WATERWORKS PVNorth of Scotland (SHEPD)Export capacity changed from 1.88 MW to 0 MW
- KINLOSS BARRACKS PVNorth of Scotland (SHEPD)Export capacity changed from 0 MW to 2.64 MW
- KINNELLS MILL PVNorth of Scotland (SHEPD)Export capacity changed from 9.9 MW to 0.05 MW
- LOCHEND WINDNorth of Scotland (SHEPD)Flexible connection stated as “yes” (not stated in the June 2026 edition)
- MELVICH WIND ENERGY HUBNorth of Scotland (SHEPD)Export capacity changed from 45.474 MW to 86.4 MW
- MORENISHNorth of Scotland (SHEPD)Export capacity changed from 49.4 MW to 52 MW
- PEATTIE FARM PVNorth of Scotland (SHEPD)Export capacity changed from 49.7 MW to 0.8 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 20 MW to 0.105 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 30 MW to 0.105 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 1.797 MW to 1.155 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 0 MW to 8.112 MW
- SOUTHWOOD FARMSouthern England (SEPD)Export capacity changed from 0.105 MW to 30 MW
- STONEYHILL FARM 49.9MWNorth of Scotland (SHEPD)Export capacity changed from 99.95 MW to 52.53 MW
- TAPPIES FARM PV (CUST REF KINTORE SOLAR FARM)North of Scotland (SHEPD)Export capacity changed from 0.315 MW to 22 MW
- TRINITY FARMSouthern England (SEPD)Export capacity changed from 100.1 MW to 84.211 MW
- WELLBECK HEALTH CENTRESouthern England (SEPD)Export capacity changed from 0.7 MW to 1 MW
- WERRAR FARMSouthern England (SEPD)Export capacity changed from 9.474 MW to 45 MW
- WITH CCM - DGENNorth of Scotland (SHEPD)Export capacity changed from 25 MW to 52.6 MW
- WORK FARM, WORK FARMNorth of Scotland (SHEPD)Flexible connection stated as “yes” (not stated in the June 2026 edition)
22 sites without a match in the other edition
In the July 2026 edition only (7)
In the June 2026 edition only (15)
May 2026 edition to June 2026 edition
37 changes
1,306 sites matched. 27 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 100MW BESSSouthern England (SEPD)Export capacity changed from 100 MW to 105.263 MW
- 30MW PV & 30MW BESSSouthern England (SEPD)Export capacity changed from 60 MW to 31.579 MW
- 9.9MW 33KV POC REQUESTEDSouthern England (SEPD)Export capacity changed from 10.421 MW to 9.9 MW
- 950KW EXPORTSouthern England (SEPD)Export capacity changed from 1.338 MW to 1.8 MW
- 99.9MW BESS CHRISTCHURCH ROAD STORAGESouthern England (SEPD)Export capacity changed from 105.158 MW to 99.9 MW
- ALLT NA MOINE HYDRO - IMPORT ADDCAPNorth of Scotland (SHEPD)Export capacity changed from 4.99 MW to 3.093 MW
- BALGONIE FARM 50MW BATTERYNorth of Scotland (SHEPD)Export capacity changed from 50 MW to 52.68 MW
- BEINN NAN LOCHAN WINDNorth of Scotland (SHEPD)Export capacity changed from 35 MW to 0.539 MW
- BINSTEAD FARMSouthern England (SEPD)Export capacity changed from 4.9 MW to 12.174 MW
- BISHOPS SUTTONSouthern England (SEPD)Export capacity changed from 0.105 MW to 5.4 MW
- BRANSBURY MANOR FARMSouthern England (SEPD)Export capacity changed from 10 MW to 5.263 MW
- BUCKLAND RIPERS 20MW PV & BESSSouthern England (SEPD)Export capacity changed from 0.526 MW to 45 MW
- BUNLOINN WIND FARM AND BESSNorth of Scotland (SHEPD)Export capacity changed from 71.6 MW to 5.5 MW
- CASTLECRAIG FARMSNorth of Scotland (SHEPD)Export capacity changed from 0.15 MW to 15 MW
- CHRATHAICH WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0.632 MW to 62.4 MW
- CRUCIS PARK ESTATE LLPSouthern England (SEPD)Export capacity changed from 12.6 MW to 11 MW
- DOWN AMPNEY AIRFIELD QUARRYSouthern England (SEPD)Export capacity changed from 2.45 MW to 0.499 MW
- DRUIDS LODGE ESTATESouthern England (SEPD)Export capacity changed from 61.56 MW to 0.316 MW
- EDAY TIDAL DEVELOPMENTSNorth of Scotland (SHEPD)Export capacity changed from 0.1 MW to 4.8 MW
- FIRST ABERDEEN BESSNorth of Scotland (SHEPD)Export capacity changed from 2 MW to 2.105 MW
- GLENKILN FARMNorth of Scotland (SHEPD)Export capacity changed from 0.1 MW to 4 MW
- INVERCANNIE WATERWORKS PVNorth of Scotland (SHEPD)Export capacity changed from 0 MW to 1.88 MW
- INVERTER CHANGESouthern England (SEPD)Export capacity changed from 0 MW to 3.64 MW
- LITTLE BARRAS FARM PV & BESSNorth of Scotland (SHEPD)Export capacity changed from 0.42 MW to 74 MW
- NORTH HOO FIELD LTDNorth of Scotland (SHEPD)Export capacity changed from 0.15 MW to 2.3 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 0.105 MW to 20 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 85.5 MW to 73.684 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 1.155 MW to 1.797 MW
- Site not namedSouthern England (SEPD)Target energisation date moved from 12 Jan 2027 to 1 Dec 2027 (11 months later)
- SPRING FARMSouthern England (SEPD)Export capacity changed from 0.105 MW to 13.2 MW
- STONEYHILL FARM 49.9MWNorth of Scotland (SHEPD)Export capacity changed from 52.53 MW to 99.95 MW
- TRINITY FARMSouthern England (SEPD)Export capacity changed from 84.211 MW to 100.1 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 1.9 MW to 2.4 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 4.949 MW to 0 MW
- WARDHILL FARM BESSNorth of Scotland (SHEPD)Export capacity changed from 50 MW to 49.9 MW
- WELLBECK HEALTH CENTRESouthern England (SEPD)Export capacity changed from 1 MW to 0.7 MW
- WITH CCM - DGENNorth of Scotland (SHEPD)Export capacity changed from 52.6 MW to 25 MW
27 sites without a match in the other edition
In the June 2026 edition only (9)
In the May 2026 edition only (18)
April 2026 edition to May 2026 edition
46 changes
1,312 sites matched. 21 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 100MW BESSSouthern England (SEPD)Export capacity changed from 105.263 MW to 100 MW
- 30MW PV & 30MW BESSSouthern England (SEPD)Export capacity changed from 31.579 MW to 60 MW
- 950KW EXPORTSouthern England (SEPD)Export capacity changed from 1.8 MW to 1.338 MW
- 99.9MW BESS TITCHFIELD LANESouthern England (SEPD)Export capacity changed from 100 MW to 105.263 MW
- BANKHEAD PV & WINDNorth of Scotland (SHEPD)Export capacity changed from 3.5 MW to 2.8 MW
- BINSTEAD FARMSouthern England (SEPD)Customer not stated (name not shown in the April 2026 edition)
- BINSTEAD FARMSouthern England (SEPD)Export capacity changed from 12.174 MW to 4.9 MW
- BISHOPS SUTTONSouthern England (SEPD)Export capacity changed from 5.4 MW to 0.105 MW
- BUNLOINN WIND FARM AND BESSNorth of Scotland (SHEPD)Export capacity changed from 5.5 MW to 71.6 MW
- CAIRNBORROW II WINDFARMNorth of Scotland (SHEPD)Export capacity changed from 96.9 MW to 49.364 MW
- CAIRNBROGIE WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 4.1 MW to 0 MW
- CHRATHAICH WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 62.4 MW to 0.632 MW
- CRACKA LONGI WINDNorth of Scotland (SHEPD)Export capacity changed from 8.4 MW to 8.421 MW
- CRAIGNATHRO FARM PVNorth of Scotland (SHEPD)Export capacity changed from 5.6 MW to 0.05 MW
- CROMLET HILL WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 60 MW to 1.2 MW
- CRUCIS PARK ESTATE LLPSouthern England (SEPD)Export capacity changed from 11 MW to 12.6 MW
- DENHEAD SOLAR MACDUFF GSPNorth of Scotland (SHEPD)Export capacity changed from 0.1 MW to 20 MW
- EDAY TIDAL DEVELOPMENTSNorth of Scotland (SHEPD)Export capacity changed from 4.8 MW to 0.1 MW
- ESCART ESTATENorth of Scotland (SHEPD)Export capacity changed from 0.1 MW to 26 MW
- EYNSHAM ESTATE - PV & BESSSouthern England (SEPD)Export capacity changed from 100 MW to 52.526 MW
- FIRST ABERDEEN BESSNorth of Scotland (SHEPD)Export capacity changed from 2.105 MW to 2 MW
- GARBET WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 46.2 MW to 0.25 MW
- GARBHAIG HYDRONorth of Scotland (SHEPD)Export capacity changed from 0.04 MW to 1 MW
- HAMPRESTON SOLAR FARMSouthern England (SEPD)Export capacity changed from 0.421 MW to 40 MW
- INVERCANNIE WATERWORKS PVNorth of Scotland (SHEPD)Export capacity changed from 1.88 MW to 0 MW
- INVERTER CHANGESouthern England (SEPD)Export capacity changed from 3.64 MW to 0 MW
- KINNELLS MILL PVNorth of Scotland (SHEPD)Export capacity changed from 0.05 MW to 9.9 MW
- MELVICH WIND ENERGY HUBNorth of Scotland (SHEPD)Export capacity changed from 86.4 MW to 45.474 MW
- MORENISHNorth of Scotland (SHEPD)Export capacity changed from 52 MW to 49.4 MW
- NORTH HOO FIELD LTDNorth of Scotland (SHEPD)Export capacity changed from 2.3 MW to 0.15 MW
- PEATTIE FARM PVNorth of Scotland (SHEPD)Export capacity changed from 0.8 MW to 49.7 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 20 MW to 0.105 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 1.797 MW to 1.155 MW
- STAGECOACHSouthern England (SEPD)Export capacity changed from 3.7 MW to 2.2 MW
- STONEYHILL FARM 49.9MWNorth of Scotland (SHEPD)Export capacity changed from 99.95 MW to 52.53 MW
- TAPPIES FARM PV (CUST REF KINTORE SOLAR FARM)North of Scotland (SHEPD)Export capacity changed from 22 MW to 0.315 MW
- TRINITY FARMSouthern England (SEPD)Export capacity changed from 100.1 MW to 84.211 MW
- TUMMEL BRIDGE POWER STATIONNorth of Scotland (SHEPD)Export capacity changed from 6.46 MW to 0 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 2.4 MW to 1.9 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 0 MW to 4.949 MW
- WARDHILL FARM BESSNorth of Scotland (SHEPD)Export capacity changed from 49.9 MW to 50 MW
- WELLBECK HEALTH CENTRESouthern England (SEPD)Export capacity changed from 0.7 MW to 1 MW
- WELLS FOREST FARM 25MWNorth of Scotland (SHEPD)Export capacity changed from 26.5 MW to 50.16 MW
- WERRAR FARMSouthern England (SEPD)Export capacity changed from 45 MW to 9.474 MW
- WESTFIELD SOLAR & STORAGENorth of Scotland (SHEPD)Export capacity changed from 52.631 MW to 50 MW
- WITH CCM - DGENNorth of Scotland (SHEPD)Export capacity changed from 25 MW to 52.6 MW
21 sites without a match in the other edition
In the May 2026 edition only (12)
In the April 2026 edition only (9)
March 2026 edition to April 2026 edition
43 changes
1,316 sites matched. 51 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 100MW BESSSouthern England (SEPD)Export capacity changed from 100 MW to 105.263 MW
- 30MW PV & 30MW BESSSouthern England (SEPD)Export capacity changed from 60 MW to 31.579 MW
- 9.9MW 33KV POC REQUESTEDSouthern England (SEPD)Export capacity changed from 9.9 MW to 10.421 MW
- 99.9MW BESS CHRISTCHURCH ROAD STORAGESouthern England (SEPD)Export capacity changed from 99.9 MW to 105.158 MW
- BISHOPS SUTTONSouthern England (SEPD)Export capacity changed from 0.105 MW to 5.4 MW
- CAIRNBORROW II WINDFARMNorth of Scotland (SHEPD)Export capacity changed from 49.364 MW to 96.9 MW
- CAIRNBROGIE WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0 MW to 4.1 MW
- CHARLESTON SOLAR 20MW PVNorth of Scotland (SHEPD)Export capacity changed from 20 MW to 0.25 MW
- CHRATHAICH WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0.632 MW to 62.4 MW
- CRAIGNATHRO FARM PVNorth of Scotland (SHEPD)Export capacity changed from 0.05 MW to 5.6 MW
- CROMLET HILL WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 1.2 MW to 60 MW
- DENHEAD SOLAR MACDUFF GSPNorth of Scotland (SHEPD)Export capacity changed from 20 MW to 0.1 MW
- EDAY TIDAL DEVELOPMENTSNorth of Scotland (SHEPD)Export capacity changed from 0.1 MW to 4.8 MW
- ETON COLLEGE PVSouthern England (SEPD)Export capacity changed from 0.05 MW to 3.96 MW
- EYNSHAM ESTATE - PV & BESSSouthern England (SEPD)Export capacity changed from 52.526 MW to 100 MW
- FACCOMBE ESTATESouthern England (SEPD)Export capacity changed from 2.425 MW to 0.53 MW
- FIRST ABERDEEN BESSNorth of Scotland (SHEPD)Export capacity changed from 2 MW to 2.105 MW
- GARBHAIG HYDRONorth of Scotland (SHEPD)Export capacity changed from 1 MW to 0.04 MW
- GOLTICLAY WIND FARM NC ONLY REQUOTENorth of Scotland (SHEPD)Export capacity changed from 58 MW to 0.2 MW
- HAMPRESTON SOLAR FARMSouthern England (SEPD)Export capacity changed from 40 MW to 0.421 MW
- LERWICK POWER STATIONNorth of Scotland (SHEPD)Export capacity changed from 17.514 MW to 0 MW
- LITTLE BARRAS FARM PV & BESSNorth of Scotland (SHEPD)Export capacity changed from 74 MW to 0.42 MW
- MONTREATHMONTNorth of Scotland (SHEPD)Export capacity changed from 73.7 MW to 34.375 MW
- MORENISHNorth of Scotland (SHEPD)Export capacity changed from 49.4 MW to 52 MW
- NORTH HOO FIELD LTDNorth of Scotland (SHEPD)Export capacity changed from 0.15 MW to 2.3 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 73.684 MW to 85.5 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 1.9 MW to 1.4 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 12.105 MW to 50.6 MW
- Site not namedNorth of Scotland (SHEPD)Export capacity changed from 0.2 MW to 4.2 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 9.3 MW to 11.25 MW
- SOUTHWOOD FARMSouthern England (SEPD)Export capacity changed from 30 MW to 0.105 MW
- STONEYHILL FARM 49.9MWNorth of Scotland (SHEPD)Export capacity changed from 52.53 MW to 99.95 MW
- TAPPIES FARM PV (CUST REF KINTORE SOLAR FARM)North of Scotland (SHEPD)Export capacity changed from 0.315 MW to 22 MW
- TRINITY FARMSouthern England (SEPD)Export capacity changed from 84.211 MW to 100.1 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 1.9 MW to 2.4 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 4.949 MW to 0 MW
- WARDHILL FARM BESSNorth of Scotland (SHEPD)Export capacity changed from 50 MW to 49.9 MW
- WELLBECK HEALTH CENTRESouthern England (SEPD)Export capacity changed from 1 MW to 0.7 MW
- WERRAR FARMSouthern England (SEPD)Export capacity changed from 9.474 MW to 45 MW
- WESTFIELD SOLAR & STORAGENorth of Scotland (SHEPD)Export capacity changed from 50 MW to 52.631 MW
- WESTON LANE (G)Southern England (SEPD)Export capacity changed from 450 MW to 200 MW
- WITH CCMNorth of Scotland (SHEPD)Export capacity changed from 36.72 MW to 0.5 MW
- WITH CCM - DGENNorth of Scotland (SHEPD)Export capacity changed from 52.6 MW to 25 MW
51 sites without a match in the other edition
In the April 2026 edition only (5)
In the March 2026 edition only (46)
February 2026 edition to March 2026 edition
No changes found.
1,332 sites matched. 54 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
54 sites without a match in the other edition
In the March 2026 edition only (30)
In the February 2026 edition only (24)
January 2026 edition to February 2026 edition
61 changes
1,345 sites matched. 59 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 100MW BESSSouthern England (SEPD)Export capacity changed from 99.9 MW to 100 MW
- 30MW PV & 30MW BESSSouthern England (SEPD)Export capacity changed from 30 MW to 60 MW
- 49.9MW BESSSouthern England (SEPD)Target energisation date stated as 25 May 2027 (not stated in the January 2026 edition)
- 56.8MW - LOCH NAN CUILLE WINDNorth of Scotland (SHEPD)Export capacity changed from 56 MW to 56.8 MW
- 950KW EXPORTSouthern England (SEPD)Export capacity changed from 0.95 MW to 1.8 MW
- 99.9MW BESS TITCHFIELD LANESouthern England (SEPD)Export capacity changed from 99.9 MW to 100 MW
- ALLT NA MOINE HYDRO - IMPORT ADDCAPNorth of Scotland (SHEPD)Export capacity changed from 0 MW to 4.99 MW
- ARNISH COMMUNITY WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 35 MW to 38.92 MW
- BANKHEAD PV & WINDNorth of Scotland (SHEPD)Export capacity changed from 2.8 MW to 3.5 MW
- BISHOPS SUTTONSouthern England (SEPD)Export capacity changed from 4.75 MW to 0.105 MW
- BRANSBURY MANOR FARMSouthern England (SEPD)Export capacity changed from 5 MW to 10 MW
- BUNLOINN WIND FARM AND BESSNorth of Scotland (SHEPD)Export capacity changed from 71.6 MW to 5.5 MW
- CAIRNBORROW II WINDFARMNorth of Scotland (SHEPD)Export capacity changed from 46.9 MW to 49.364 MW
- CAIRNBROGIE WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 4.1 MW to 0 MW
- CASTLECRAIG FARMSNorth of Scotland (SHEPD)Export capacity changed from 15 MW to 0.15 MW
- CHRATHAICH WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 62.4 MW to 0.632 MW
- CLACHAIG GLEN WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 0 MW to 49.9 MW
- CRAIGNATHRO FARM PVNorth of Scotland (SHEPD)Export capacity changed from 5 MW to 0.05 MW
- CROMLET HILL WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 60 MW to 1.2 MW
- CRUCIS PARK ESTATE LLPSouthern England (SEPD)Export capacity changed from 0 MW to 11 MW
- DOWN AMPNEY AIRFIELD QUARRYSouthern England (SEPD)Export capacity changed from 0.9 MW to 2.45 MW
- DRUIDS LODGE ESTATESouthern England (SEPD)Export capacity changed from 60 MW to 61.56 MW
- EDAY TIDAL DEVELOPMENTSNorth of Scotland (SHEPD)Export capacity changed from 4.8 MW to 0.1 MW
- EDINTORE 2 WIND FARM (CAIRDS WOOD) - WINDNorth of Scotland (SHEPD)Export capacity changed from 16.8 MW to 0.5 MW
- ESCART ESTATENorth of Scotland (SHEPD)Export capacity changed from 26 MW to 0.1 MW
- ETON COLLEGE PVSouthern England (SEPD)Export capacity changed from 3.96 MW to 0.05 MW
- EYNSHAM ESTATE - PV & BESSSouthern England (SEPD)Export capacity changed from 49.9 MW to 52.526 MW
- FACCOMBE ESTATESouthern England (SEPD)Export capacity changed from 0.669 MW to 2.425 MW
- GLASSA HYDRONorth of Scotland (SHEPD)Export capacity changed from 9.9 MW to 0.05 MW
- GLENKILN FARMNorth of Scotland (SHEPD)Export capacity changed from 4 MW to 0.1 MW
- GOLTICLAY EXTENSIONNorth of Scotland (SHEPD)Export capacity changed from 55 MW to 0.1 MW
- HESTA HEAD WINDNorth of Scotland (SHEPD)Export capacity changed from 20.4 MW to 0.636 MW
- HILL OF STONEYFIELD WINDNorth of Scotland (SHEPD)Export capacity changed from 15 MW to 0.2 MW
- INVERTER CHANGESouthern England (SEPD)Export capacity changed from 0 MW to 3.64 MW
- KINLOSS BARRACKS PVNorth of Scotland (SHEPD)Export capacity changed from 2.08 MW to 0 MW
- KINNELLS MILL PVNorth of Scotland (SHEPD)Export capacity changed from 9.9 MW to 0.05 MW
- LITTLE BARRAS FARM PV & BESSNorth of Scotland (SHEPD)Export capacity changed from 50 MW to 74 MW
- MELVICH WIND ENERGY HUBNorth of Scotland (SHEPD)Export capacity changed from 43.2 MW to 86.4 MW
- MILL STREETSouthern England (SEPD)Export capacity changed from 13.2 MW to 0.211 MW
- MONTREATHMONTNorth of Scotland (SHEPD)Export capacity changed from 34.375 MW to 73.7 MW
- NORTH HOO FIELD LTDNorth of Scotland (SHEPD)Export capacity changed from 2.3 MW to 0.15 MW
- PEATTIE FARM PVNorth of Scotland (SHEPD)Export capacity changed from 49.7 MW to 0.8 MW
- PURTON SOLAR FARMSouthern England (SEPD)Export capacity changed from 3.2 MW to 0 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 70 MW to 73.684 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 11.8 MW to 1.789 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 0.949 MW to 1.9 MW
- SLOY POWER STATIONNorth of Scotland (SHEPD)Export capacity changed from 160 MW to 72.5 MW
- SPRING FARMSouthern England (SEPD)Export capacity changed from 12 MW to 0.105 MW
- STAGECOACHSouthern England (SEPD)Export capacity changed from 0.999 MW to 3.7 MW
- STONEYHILL FARM 49.9MWNorth of Scotland (SHEPD)Export capacity changed from 49.9 MW to 52.53 MW
- STRATH TIRRY WIND FARMNorth of Scotland (SHEPD)Export capacity changed from 34.8 MW to 0.317 MW
- TAPPIES FARM PV (CUST REF KINTORE SOLAR FARM)North of Scotland (SHEPD)Export capacity changed from 22 MW to 0.315 MW
- TRINITY FARMSouthern England (SEPD)Export capacity changed from 99.9 MW to 84.211 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 0 MW to 1.9 MW
- UNIPART GROUP OF COMPANIESSouthern England (SEPD)Export capacity changed from 0 MW to 4.949 MW
- WELLBECK HEALTH CENTRESouthern England (SEPD)Export capacity changed from 0.999 MW to 1 MW
- WELLS FOREST FARM 25MWNorth of Scotland (SHEPD)Export capacity changed from 25 MW to 26.5 MW
- WERRAR FARMSouthern England (SEPD)Export capacity changed from 35 MW to 9.474 MW
- WICKS FARMSouthern England (SEPD)Export capacity changed from 3.901 MW to 2.901 MW
- WITH CCMNorth of Scotland (SHEPD)Export capacity changed from 35 MW to 36.72 MW
- WITH CCM - DGENNorth of Scotland (SHEPD)Export capacity changed from 25 MW to 52.6 MW
59 sites without a match in the other edition
In the February 2026 edition only (11)
In the January 2026 edition only (48)
December 2025 edition to January 2026 edition
No changes found.
1,388 sites matched. 10 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
10 sites without a match in the other edition
In the January 2026 edition only (5)
In the December 2025 edition only (5)
November 2025 edition to December 2025 edition
14 changes
1,377 sites matched. 29 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 199.9MWSouthern England (SEPD)Customer not stated (name not shown in the November 2025 edition)
- 49.9MW BESSNorth of Scotland (SHEPD)Customer not stated (name not shown in the November 2025 edition)
- 49.9MW BESSSouthern England (SEPD)Target energisation date not stated (25 May 2027 in the November 2025 edition)
- 66MW WINDNorth of Scotland (SHEPD)Customer not stated (name not shown in the November 2025 edition)
- 75MW WIND, PV AND BESSNorth of Scotland (SHEPD)Customer not stated (name not shown in the November 2025 edition)
- BLACKHILL FARM BESSNorth of Scotland (SHEPD)Customer not stated (name not shown in the November 2025 edition)
- CAIRNBULG ESTATE BESSNorth of Scotland (SHEPD)Customer not stated (name not shown in the November 2025 edition)
- CRAIGO AND GLENSKINNO FARM SOLARNorth of Scotland (SHEPD)Customer not stated (name not shown in the November 2025 edition)
- CRAIGSHAW DRIVE EV & BESSNorth of Scotland (SHEPD)Customer not stated (name not shown in the November 2025 edition)
- GRUDIE BRIDGE 49.4MW BESSNorth of Scotland (SHEPD)Customer not stated (name not shown in the November 2025 edition)
- LAND SITUATED NORTH WESTSouthern England (SEPD)Customer not stated (name not shown in the November 2025 edition)
- Site not namedSouthern England (SEPD)Customer not stated (name not shown in the November 2025 edition)
- STORMONT PARK - PHASE 2North of Scotland (SHEPD)Customer not stated (name not shown in the November 2025 edition)
- ZENOBE SHETLAND BACKUP BESSNorth of Scotland (SHEPD)Customer not stated (name not shown in the November 2025 edition)
29 sites without a match in the other edition
In the December 2025 edition only (16)
In the November 2025 edition only (13)
October 2025 edition to November 2025 edition
2 changes
1,382 sites matched. 22 sites couldn’t be matched between the two editions, because their details changed or they appear in only one. SSEN’s November 2025 edition gives a target energisation date for 657 sites that its October 2025 edition left blank.
- 1.499MW EXPORTSouthern England (SEPD)Target energisation date moved from 23 Sep 2024 to 23 Jan 2027 (28 months later)
- BINDWELL LANE - PVSouthern England (SEPD)Target energisation date moved from 6 Dec 2024 to 7 Oct 2026 (22 months later)
22 sites without a match in the other edition
In the November 2025 edition only (8)
In the October 2025 edition only (14)
September 2025 edition to October 2025 edition
7 changes
1,362 sites matched. 55 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- CHALCROFT FARMSouthern England (SEPD)Technology changed from Hydro and marine to Solar
- CONRAD (MELKSHAM) LIMITEDSouthern England (SEPD)Customer changed from CONRAD (MELKSHAM GSP) LIMITED to CONRAD (MELKSHAM) LIMITED
- CRUACH MORNorth of Scotland (SHEPD)Technology changed from Hydro and marine to Wind
- JBM SOLAR PROJECTS 18 LTDSouthern England (SEPD)Customer changed from AMBERSIDE ENERGY LTD to JBM SOLAR PROJECTS 18 LTD
- JBM SOLAR PROJECTS 18 LTDSouthern England (SEPD)Status changed from “accepted to connect” to “connected”Connected
- N COE INVOICE CAMSTER 2 WIND FARMNorth of Scotland (SHEPD)Target energisation date moved from 3 Oct 2025 to 25 Nov 2025 (2 months later)
- TANGY WINDFARMNorth of Scotland (SHEPD)Technology changed from Hydro and marine to Wind
55 sites without a match in the other edition
In the October 2025 edition only (34)
In the September 2025 edition only (21)
August 2025 edition to September 2025 edition
2 changes
1,369 sites matched. 49 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- CHARLESTON SOLAR 20MW PVNorth of Scotland (SHEPD)Customer changed from SONNEDIX WESTON LTD to TNEI SERVICES
- CONRAD (MELKSHAM GSP) LIMITEDSouthern England (SEPD)Customer changed from CONRAD (MELKSHAM) LIMITED to CONRAD (MELKSHAM GSP) LIMITED
49 sites without a match in the other edition
In the September 2025 edition only (14)
In the August 2025 edition only (35)
July 2025 edition to August 2025 edition
No changes found.
1,390 sites matched. 45 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
45 sites without a match in the other edition
In the August 2025 edition only (14)
In the July 2025 edition only (31)
June 2025 edition to July 2025 edition
27 changes
1,397 sites matched. 48 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 0MW - DIESEL (SHORT TERM PARALLEL)Southern England (SEPD)Technology stated as Gas and other fossil (not stated in the June 2025 edition)
- 1.322MW CHPSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the June 2025 edition)
- 26.5MW - STEAMSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the June 2025 edition)
- 35MW PV & CHP (ADD CAP)Southern England (SEPD)Technology stated as Bioenergy and waste (not stated in the June 2025 edition)
- 9.9MWNorth of Scotland (SHEPD)Customer not stated (name not shown in the June 2025 edition)
- 99.9MW BESS TITCHFIELD LANESouthern England (SEPD)Customer not stated (name not shown in the June 2025 edition)
- AFFINITY WATER LIMITEDSouthern England (SEPD)Technology stated as Gas and other fossil (not stated in the June 2025 edition)
- AGRIVERT LIMITEDSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the June 2025 edition)
- AH BUNKERS HILL SOLAR A - SOLAR AND BATTERYSouthern England (SEPD)Status changed from “accepted to connect” to “connected”Connected
- BOTLEY ENERGY RESERVE LIMITEDSouthern England (SEPD)Export capacity changed from 0 MW to 49.9 MW
- FARLEIGH WALLOP AD PLANTSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the June 2025 edition)
- FRIMLEY HEALTH NHS FOUNDATION TRUSTSouthern England (SEPD)Technology stated as Gas and other fossil (not stated in the June 2025 edition)
- GLENKILN FARMNorth of Scotland (SHEPD)Customer not stated (name not shown in the June 2025 edition)
- GORING POWER IMPORTSouthern England (SEPD)Capacity changed from 7.12 MW to 6.764 MW−0.356 MW
- GORING POWER IMPORTSouthern England (SEPD)Export capacity changed from 0 MW to 6.764 MW
- HERRIARD AD PLANTSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the June 2025 edition)
- JPMORGAN CHASE BANK - NATIONAL ASSOCIATIONSouthern England (SEPD)Technology stated as Gas and other fossil (not stated in the June 2025 edition)
- LOUDWATERSouthern England (SEPD)Export capacity changed from 0 MW to 40 MW
- PARK GROUNDSSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the June 2025 edition)
- READY - 29.4MW CHP & STP DIESEL (SEE NOTES)Southern England (SEPD)Technology stated as Bioenergy and waste (not stated in the June 2025 edition)
- REDCENTRIC SOLUTIONSSouthern England (SEPD)Technology stated as Gas and other fossil (not stated in the June 2025 edition)
- ROWNHAMS IMPORTSouthern England (SEPD)Technology stated as Gas and other fossil (not stated in the June 2025 edition)
- SEVERN TRENT GREEN POWER LIMITEDSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the June 2025 edition)
- Site not namedSouthern England (SEPD)Customer not stated (name not shown in the June 2025 edition)
- Site not namedSouthern England (SEPD)Technology stated as Gas and other fossil (not stated in the June 2025 edition)
- TILLINGHAM POWERSouthern England (SEPD)Technology stated as Gas and other fossil (not stated in the June 2025 edition)
- UNIT 2Southern England (SEPD)Technology stated as Gas and other fossil (not stated in the June 2025 edition)
48 sites without a match in the other edition
In the July 2025 edition only (24)
In the June 2025 edition only (24)
May 2025 edition to June 2025 edition
2 changes
1,398 sites matched. 46 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- DENHEAD SOLAR MACDUFF GSPNorth of Scotland (SHEPD)Flexible connection not stated (“no” in the May 2025 edition)
- DENHEAD SOLAR MACDUFF GSPNorth of Scotland (SHEPD)Technology changed from Bioenergy and waste to Solar
46 sites without a match in the other edition
In the June 2025 edition only (23)
In the May 2025 edition only (23)
April 2025 edition to May 2025 edition
4 changes
1,410 sites matched. 59 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- BOTLEY ENERGY RESERVE LIMITEDSouthern England (SEPD)Export capacity changed from 49.9 MW to 0 MW
- GORING POWER IMPORTSouthern England (SEPD)Capacity changed from 6.764 MW to 7.12 MW+0.356 MW
- GORING POWER IMPORTSouthern England (SEPD)Export capacity changed from 6.764 MW to 0 MW
- LOUDWATERSouthern England (SEPD)Export capacity changed from 40 MW to 0 MW
59 sites without a match in the other edition
In the May 2025 edition only (11)
In the April 2025 edition only (48)
March 2025 edition to April 2025 edition
63 changes
1,439 sites matched. 34 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 950KW EXPORTSouthern England (SEPD)Technology changed from Other to Solar
- ALLINGTON LANESouthern England (SEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- BASIS1ZZSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- BIFFA WASTE SERVICES LIMITEDSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- BISHOPS WALTHAMSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- BNRG IOW LTDSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- BOYNDIE WINDFARMNorth of Scotland (SHEPD)Technology stated as Wind (not stated in the March 2025 edition)
- BRADLEY WIND ENERGY 2 LIMITEDNorth of Scotland (SHEPD)Technology stated as Wind (not stated in the March 2025 edition)
- BURGAR HILLNorth of Scotland (SHEPD)Technology stated as Wind (not stated in the March 2025 edition)
- BURRADALE HILL 2North of Scotland (SHEPD)Technology stated as Wind (not stated in the March 2025 edition)
- CALCUTT SOLAR PVSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- CIRENCESTER PVSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- COMMUNITY ENERGY SERVICES LTDNorth of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- CONRAD (YEOVIL) LIMITEDSouthern England (SEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- DALCHONZIE POWER STATIONNorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the March 2025 edition)
- DROVE LANE SOLARSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- EAST FARMSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- EVELEY FARM 2Southern England (SEPD)Customer changed from PADERO SOLAER LIMITED to PS-GANDER-DOWN SOLAR FARM LTD
- EVELEY FARM 2Southern England (SEPD)Status changed from “accepted to connect” to “connected”Connected
- FAREHAMSouthern England (SEPD)Technology stated as Storage (not stated in the March 2025 edition)
- FINLARIG POWER STATIONNorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the March 2025 edition)
- FORMER ANDOVER AIRFIELDSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- HIILLHEAD OF AUQUIRENorth of Scotland (SHEPD)Technology stated as Wind (not stated in the March 2025 edition)
- IMP EXP SUPPLYSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- INFINISSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- INFINIS LIMITEDSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- KIRKWALL PS G4North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- KIRKWALL PS G6North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- KIRKWALL PS G8North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- KIRKWALL PS G9North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- LAIRIG A MHUIC LLPNorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the March 2025 edition)
- LEDNOCK POWER STATIONNorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the March 2025 edition)
- LOCH CARNON G1North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- LOCH CARNON G2North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- LOCH CARNON G3North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- LOCH CARNON G4North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- LOCH CARNON G5North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- LOVEDEAN LIMITEDSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- MALDIE HYDRO SCHEMENorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the March 2025 edition)
- N COE INVOICE CAMSTER 2 WIND FARMNorth of Scotland (SHEPD)Target energisation date stated as 3 Oct 2025 (not stated in the March 2025 edition)
- NEWLANDS FARMSouthern England (SEPD)Technology stated as Storage (not stated in the March 2025 edition)
- Site not namedSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- Site not namedSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- Site not namedSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- Site not namedSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- Site not namedSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- Site not namedSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- SOUTHERN WATER SERVICES LIMITEDSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- ST LAND ADJSouthern England (SEPD)Technology stated as Storage (not stated in the March 2025 edition)
- STELLAR POWER LTDSouthern England (SEPD)Technology stated as Solar (not stated in the March 2025 edition)
- STORNOWAY PS G1North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- STORNOWAY PS G1North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- STORNOWAY PS G3North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- STORNOWAY PS G5North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- STORNOWAY PS G6North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- STORNOWAY PS G8North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- STORNOWAY PS G9North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- STORNOWAY PS G9North of Scotland (SHEPD)Technology stated as Gas and other fossil (not stated in the March 2025 edition)
- TARBOTHILLNorth of Scotland (SHEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- VEOLIA ES (UK) LIMITEDSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- VIRIDIS ENERGY (NORGEN) LIMITEDNorth of Scotland (SHEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- WAPSEYS WOOD IIISouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
- WESSEX WATER SERVICES LIMITEDSouthern England (SEPD)Technology stated as Bioenergy and waste (not stated in the March 2025 edition)
34 sites without a match in the other edition
In the April 2025 edition only (19)
In the March 2025 edition only (15)
February 2025 edition to March 2025 edition
No changes found.
1,444 sites matched. 34 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
34 sites without a match in the other edition
In the March 2025 edition only (10)
In the February 2025 edition only (24)
January 2025 edition to February 2025 edition
14 changes
1,451 sites matched. 32 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 100MW BESSSouthern England (SEPD)Export capacity changed from 100 MW to 99.9 MW
- ALLT FION POWERHOUSENorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the January 2025 edition)
- ALT-NA LAIRIGE POWER STATIONNorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the January 2025 edition)
- BALDOVIE ROADNorth of Scotland (SHEPD)Technology changed from Other to Wind
- BEN GLAS POWER LIMITEDNorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the January 2025 edition)
- BENZIESNorth of Scotland (SHEPD)Technology stated as Wind (not stated in the January 2025 edition)
- DARROCH POWER LIMITEDNorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the January 2025 edition)
- LOCH TURRET WTW-EXPNorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the January 2025 edition)
- LUSSA POWER STATIONNorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the January 2025 edition)
- MACALLAN 1.75MW PVNorth of Scotland (SHEPD)Target energisation date not stated (27 Jan 2025 in the January 2025 edition)
- MUCCOMER POWER STATIONNorth of Scotland (SHEPD)Technology stated as Hydro and marine (not stated in the January 2025 edition)
- NFPA LTDSouthern England (SEPD)Customer changed from NFPA LTD (APRIL 2DATA NOT AVAILABLE13) to NFPA LTD
- NIGG SEA OUTFALLNorth of Scotland (SHEPD)Technology stated as Solar (not stated in the January 2025 edition)
- PITHEAVLISNorth of Scotland (SHEPD)Technology stated as Storage (not stated in the January 2025 edition)
32 sites without a match in the other edition
In the February 2025 edition only (17)
In the January 2025 edition only (15)
December 2024 edition to January 2025 edition
3 changes
1,446 sites matched. 26 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 28MW PVSouthern England (SEPD)Capacity changed from 28.125 MW to 19 MW−9.125 MW
- 28MW PVSouthern England (SEPD)Export capacity changed from 28 MW to 19 MW
- MACALLAN 1.75MW PVNorth of Scotland (SHEPD)Target energisation date stated as 27 Jan 2025 (not stated in the December 2024 edition)
26 sites without a match in the other edition
In the January 2025 edition only (20)
In the December 2024 edition only (6)
November 2024 edition to December 2024 edition
2 changes
1,427 sites matched. 85 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 43.975MW - PV & BATTERYSouthern England (SEPD)Capacity changed from 43.975 MW to 63.975 MW+20 MW
- 43.975MW - PV & BATTERYSouthern England (SEPD)Export capacity changed from 43.975 MW to 44 MW
85 sites without a match in the other edition
In the December 2024 edition only (25)
In the November 2024 edition only (60)
October 2024 edition to November 2024 edition
No changes found.
1,481 sites matched. 9 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
9 sites without a match in the other edition
In the November 2024 edition only (6)
In the October 2024 edition only (3)
September 2024 edition to October 2024 edition
No changes found.
1,471 sites matched. 15 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
15 sites without a match in the other edition
In the October 2024 edition only (13)
In the September 2024 edition only (2)
August 2024 edition to September 2024 edition
1 change
1,460 sites matched. 28 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 1.499MW EXPORTSouthern England (SEPD)Target energisation date stated as 23 Sep 2024 (not stated in the August 2024 edition)
28 sites without a match in the other edition
In the September 2024 edition only (13)
In the August 2024 edition only (15)
July 2024 edition to August 2024 edition
No changes found.
1,448 sites matched. 46 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
46 sites without a match in the other edition
In the August 2024 edition only (27)
In the July 2024 edition only (19)
June 2024 edition to July 2024 edition
No changes found.
1,448 sites matched. 30 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
30 sites without a match in the other edition
In the July 2024 edition only (19)
In the June 2024 edition only (11)
May 2024 edition to June 2024 edition
1 change
1,431 sites matched. 39 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- OVERSCRAIG 30MW BESSNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the May 2024 edition)
39 sites without a match in the other edition
In the June 2024 edition only (28)
In the May 2024 edition only (11)
April 2024 edition to May 2024 edition
2 changes
1,417 sites matched. 32 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- QUOTE TO REDUCE IMPORT TO 100MW EXD149Southern England (SEPD)Capacity changed from 150 MW to 120 MW−30 MW
- QUOTE TO REDUCE IMPORT TO 100MW EXD149Southern England (SEPD)Technology changed from Storage to Other
32 sites without a match in the other edition
In the May 2024 edition only (25)
In the April 2024 edition only (7)
March 2024 edition to April 2024 edition
5 changes
1,399 sites matched. 41 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- CALZIEVEG BESS 50MWNorth of Scotland (SHEPD)Capacity changed from 34.978 MW to 51.75 MW+16.772 MW
- CALZIEVEG BESS 50MWNorth of Scotland (SHEPD)Export capacity changed from 20 MW to 50 MW
- CALZIEVEG BESS 50MWNorth of Scotland (SHEPD)Technology changed from Solar to Storage
- Site not namedSouthern England (SEPD)Capacity changed from 2.7 MW to 1.575 MW−1.125 MW
- Site not namedSouthern England (SEPD)Export capacity changed from 2.565 MW to 1.415 MW
41 sites without a match in the other edition
In the April 2024 edition only (25)
In the March 2024 edition only (16)
February 2024 edition to March 2024 edition
1 change
1,398 sites matched. 49 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- 50MW WIND, PV & BATTERYNorth of Scotland (SHEPD)Customer changed from REG HOLDINGS LTD to ALLT AN TUIR RENEWABLE ENERGY PARK
49 sites without a match in the other edition
In the March 2024 edition only (17)
In the February 2024 edition only (32)
January 2024 edition to February 2024 edition
6 changes
1,404 sites matched. 54 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- (PC) 1MW PV/BESS (ADD CAP)Southern England (SEPD)Target energisation date moved from 9 Jan 2024 to 28 Mar 2024 (3 months later)
- 49.9MW BESS SITE IN DUNDEENorth of Scotland (SHEPD)Customer not stated (name not shown in the January 2024 edition)
- 49.9MW BESS SITE IN DUNDEENorth of Scotland (SHEPD)Export capacity changed from 50 MW to 49.9 MW
- CIRENCESTER SOLAR PARK - PVSouthern England (SEPD)Capacity changed from 50 MW to 49 MW−1 MW
- CIRENCESTER SOLAR PARK - PVSouthern England (SEPD)Export capacity changed from 50 MW to 49 MW
- THE WATERS BESSNorth of Scotland (SHEPD)Customer changed from Name not shown to ANESCO LTD
54 sites without a match in the other edition
In the February 2024 edition only (26)
In the January 2024 edition only (28)
December 2023 edition to January 2024 edition
No changes found.
1,399 sites matched. 35 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
35 sites without a match in the other edition
In the January 2024 edition only (33)
In the December 2023 edition only (2)
November 2023 edition to December 2023 edition
16 changes
1,295 sites matched. 134 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- (AM) WICKES FARMSouthern England (SEPD)Capacity changed from 3 MW to 1.38 MW−1.62 MW
- (AM) WICKES FARMSouthern England (SEPD)Export capacity changed from 1.73 MW to 0.999 MW
- (AM) WICKES FARMSouthern England (SEPD)Technology not stated (Solar in the November 2023 edition)
- (PC) 1MW PV/BESS (ADD CAP)Southern England (SEPD)Target energisation date stated as 9 Jan 2024 (not stated in the November 2023 edition)
- 25MW PVNorth of Scotland (SHEPD)Target energisation date stated as 2 Feb 2026 (not stated in the November 2023 edition)
- 99.56MW PV/BESSNorth of Scotland (SHEPD)Capacity changed from 25 MW to 99.56 MW+74.56 MW
- 99.56MW PV/BESSNorth of Scotland (SHEPD)Export capacity changed from 25 MW to 49.8 MW
- DE LA RUE INTERNATIONAL LTD ET ALSouthern England (SEPD)Capacity changed from 3.362 MW to 6 MW+2.638 MW
- DE LA RUE INTERNATIONAL LTD ET ALSouthern England (SEPD)Customer changed from NICK BOOTH LIMITED to DE LA RUE INTERNATIONAL LTD ET AL
- DE LA RUE INTERNATIONAL LTD ET ALSouthern England (SEPD)Export capacity changed from 1.2 MW to 5.7 MW
- DE LA RUE INTERNATIONAL LTD ET ALSouthern England (SEPD)Status changed from “accepted to connect” to “connected”Connected
- GERRAD CROSS BATTERY STORAGESouthern England (SEPD)Flexible connection not stated (“no” in the November 2023 edition)
- LAND ON THE WEST SIDE OF BLANDFORD ROAD - BATTERYSouthern England (SEPD)Target energisation date stated as 6 Oct 2023 (not stated in the November 2023 edition)
- WHEATLEY GAS GENERATIONSouthern England (SEPD)Customer changed from SAVILLS (UK) LTD to WHEATLEY POWER EXPORT
- WHEATLEY GAS GENERATIONSouthern England (SEPD)Export capacity changed from 7.12 MW to 6.764 MW
- WHEATLEY GAS GENERATIONSouthern England (SEPD)Status changed from “accepted to connect” to “connected”Connected
134 sites without a match in the other edition
In the December 2023 edition only (106)
In the November 2023 edition only (28)
October 2023 edition to November 2023 edition
101 changes
1,256 sites matched. 254 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- ABERDEEN CITY COUNCILNorth of Scotland (SHEPD)Capacity changed from 3 MW to 2.85 MW−0.15 MW
- ABHAINN RATH & ALLT NA LAIRIGE HYDRONorth of Scotland (SHEPD)Capacity changed from 4.999 MW to 4.749 MW−0.25 MW
- ALLINGTON LANESouthern England (SEPD)Technology not stated (Gas and other fossil in the October 2023 edition)
- ALLT NA MOINE HYDRO LIMITEDNorth of Scotland (SHEPD)Capacity changed from 1.99 MW to 1.891 MW−0.099 MW
- ALLT SHALLAIN HYDRONorth of Scotland (SHEPD)Capacity changed from 1.053 MW to 1 MW−0.053 MW
- ATTADALE HYDRO GENERATING STATIONNorth of Scotland (SHEPD)Capacity changed from 3.684 MW to 3.5 MW−0.184 MW
- BAKERS FARMSouthern England (SEPD)Capacity changed from 10.526 MW to 9.5 MW−1.026 MW
- BAKERS FARMSouthern England (SEPD)Customer changed from SIDLESHAM to SIDLESHAM RENEWABLES LIMITED
- BARR RIVER HYDRONorth of Scotland (SHEPD)Capacity changed from 0.012 MW to 1.045 MW+1.033 MW
- BARRAN CALTUM WINDNorth of Scotland (SHEPD)Capacity changed from 1.2 MW to 1.14 MW−0.06 MW
- BATLEY'S POWER STATIONSouthern England (SEPD)Flexible connection not stated (“no” in the October 2023 edition)
- BATLEY'S POWER STATIONSouthern England (SEPD)Technology not stated (Bioenergy and waste in the October 2023 edition)
- BERRY COURT PVSouthern England (SEPD)Capacity changed from 4.211 MW to 3.8 MW−0.411 MW
- BISHOPS WALTHAMSouthern England (SEPD)Capacity stated as 11.4 MW (not stated in the October 2023 edition)
- BOURNE PARK PV GENERATIONSouthern England (SEPD)Capacity changed from 7.895 MW to 4.75 MW−3.145 MW
- BOWDEN LANE SOLAR PARK LIMITEDSouthern England (SEPD)Capacity changed from 4.13 MW to 3.924 MW−0.206 MW
- BRADLEY WIND ENERGY 2 LIMITEDNorth of Scotland (SHEPD)Capacity stated as 4.465 MW (not stated in the October 2023 edition)
- BROOK FARM PVSouthern England (SEPD)Capacity changed from 8.421 MW to 6.84 MW−1.581 MW
- BROOK FARM PVSouthern England (SEPD)Capacity stated as 3.8 MW (not stated in the October 2023 edition)
- BROTHERTON WIND GENERATING STATIONNorth of Scotland (SHEPD)Capacity changed from 4.842 MW to 4.6 MW−0.242 MW
- BURGAR HILLNorth of Scotland (SHEPD)Technology not stated (Wind in the October 2023 edition)
- CALCUTT SOLAR PVSouthern England (SEPD)Capacity stated as 12.35 MW (not stated in the October 2023 edition)
- CALCUTT SOLAR PVSouthern England (SEPD)Flexible connection stated as “no” (not stated in the October 2023 edition)
- CALCUTT SOLAR PVSouthern England (SEPD)Technology not stated (Solar in the October 2023 edition)
- CIRENCESTER PVSouthern England (SEPD)Capacity stated as 9.5 MW (not stated in the October 2023 edition)
- CIRENCESTER PVSouthern England (SEPD)Flexible connection stated as “no” (not stated in the October 2023 edition)
- CIRENCESTER PVSouthern England (SEPD)Technology not stated (Solar in the October 2023 edition)
- COWDOWN RENEWABLES LTDSouthern England (SEPD)Capacity changed from 47.368 MW to 30.4 MW−16.968 MW
- CRUCIS PARK PV FARMSouthern England (SEPD)Capacity stated as 14.25 MW (not stated in the October 2023 edition)
- DRAGON HALL FARM PVNorth of Scotland (SHEPD)Capacity changed from 5 MW to 4.75 MW−0.25 MW
- DRAGON HALL FARM PVNorth of Scotland (SHEPD)Customer changed from ECOSSE SOLAR PARKS LIMITED to COOP PPA SITES
- EAST FARMSouthern England (SEPD)Capacity changed from 12.5 MW to 11.875 MW−0.625 MW
- EAST FARMSouthern England (SEPD)Technology not stated (Solar in the October 2023 edition)
- FAIRLEE FARM PV GENERATIONSouthern England (SEPD)Capacity stated as 6.546 MW (not stated in the October 2023 edition)
- FAREHAMSouthern England (SEPD)Capacity stated as 38 MW (not stated in the October 2023 edition)
- FAREHAMSouthern England (SEPD)Customer stated as FAREHAM (not stated in the October 2023 edition)
- FAREHAMSouthern England (SEPD)Flexible connection not stated (“no” in the October 2023 edition)
- FIVE OAKS SOLAR FARM LIMITEDSouthern England (SEPD)Capacity changed from 5.263 MW to 3.905 MW−1.358 MW
- FLIT FARM PVSouthern England (SEPD)Capacity changed from 21.053 MW to 9.5 MW−11.553 MW
- FLIT FARM PVSouthern England (SEPD)Customer changed from FLIT SOLAR PARK LIMITED to GREENCOAT SOLAR ASSETS II LIMITED
- FORMER ANDOVER AIRFIELDSouthern England (SEPD)Capacity stated as 3.563 MW (not stated in the October 2023 edition)
- FRIMLEY HEALTH NHS FOUNDATION TRUSTSouthern England (SEPD)Capacity stated as 1.9 MW (not stated in the October 2023 edition)
- GLEN AFRIC HYDRONorth of Scotland (SHEPD)Capacity changed from 3.895 MW to 3.7 MW−0.195 MW
- GREENBANK CRESCENTNorth of Scotland (SHEPD)Capacity changed from 16 MW to 15.2 MW−0.8 MW
- HALE SOLARSouthern England (SEPD)Capacity changed from 5.242 MW to 4.731 MW−0.511 MW
- HENBURY PVSouthern England (SEPD)Customer changed from LIGHTSOURCE SPV 50 LIMITED to LIGHTSOURCE SPV 5DATA NOT AVAILABLE LIMITED
- HUNGERFORD FARM PVSouthern England (SEPD)Capacity stated as 4.75 MW (not stated in the October 2023 edition)
- HUNGERFORD FARM PVSouthern England (SEPD)Capacity changed from 1.2 MW to 1.14 MW−0.06 MW
- LAINS FARM PVSouthern England (SEPD)Capacity changed from 3.684 MW to 3.325 MW−0.359 MW
- LAKESIDE ENERGY FROM WASTE LIMITEDSouthern England (SEPD)Customer changed from NFPA (APRIL 2020) to NFPA (APRIL 2DATA NOT AVAILABLE2DATA NOT AVAILABLE)
- LOCH ETIVE HYDRONorth of Scotland (SHEPD)Capacity changed from 2.105 MW to 6.46 MW+4.355 MW
- MANOR COURT FARM PVSouthern England (SEPD)Capacity changed from 4.632 MW to 4.18 MW−0.452 MW
- MARSH FARM B PVSouthern England (SEPD)Capacity stated as 11.4 MW (not stated in the October 2023 edition)
- NETLEY PVSouthern England (SEPD)Capacity changed from 4.625 MW to 4.394 MW−0.231 MW
- NETLEY PVSouthern England (SEPD)Customer changed from ETHICAL POWER to EPG NETLEY SOLAR NORTH LIMITED
- NEWLANDS FARMSouthern England (SEPD)Capacity changed from 37.895 MW to 16.673 MW−21.222 MW
- NEWLANDS FARMSouthern England (SEPD)Capacity changed from 21.05 MW to 19.998 MW−1.052 MW
- NEWLANDS FARMSouthern England (SEPD)Customer changed from SUNSAVE 10 (FAREHAM) LTD to SUNSAVE 1DATA NOT AVAILABLE (FAREHAM) LTD
- NEWLANDS FARMSouthern England (SEPD)Customer stated, name not shown (not stated in the October 2023 edition)
- NEWLANDS FARMSouthern England (SEPD)Export capacity changed from 34.2 MW to 16.673 MW
- NEWLANDS FARMSouthern England (SEPD)Technology not stated (Other in the October 2023 edition)
- NFPA LTD (APRIL 2DATA NOT AVAILABLE13)Southern England (SEPD)Customer changed from NFPA LTD (APRIL 2013) to NFPA LTD (APRIL 2DATA NOT AVAILABLE13)
- NORRINGTON PV GENERATIONSouthern England (SEPD)Capacity stated as 9.5 MW (not stated in the October 2023 edition)
- NORTH CRANNA FARMNorth of Scotland (SHEPD)Capacity changed from 6 MW to 5.7 MW−0.3 MW
- OAKFIELD FARM PVSouthern England (SEPD)Capacity changed from 4.484 MW to 4.047 MW−0.437 MW
- PARK GROUNDSSouthern England (SEPD)Capacity changed from 6 MW to 5.7 MW−0.3 MW
- PEAKGEN HAVANTSouthern England (SEPD)Customer not stated (PEAKGEN HAVANT in the October 2023 edition)
- PEAKGEN HAVANTSouthern England (SEPD)Flexible connection not stated (“yes” in the October 2023 edition)
- PEAKGEN HAVANTSouthern England (SEPD)Technology changed from Gas and other fossil to Other
- PURLIEUS BATTERY STORAGESouthern England (SEPD)Capacity changed from 110.737 MW to 94.991 MW−15.746 MW
- PV GENERATIONSouthern England (SEPD)Capacity changed from 7.579 MW to 6.84 MW−0.739 MW
- PV GENERATIONSouthern England (SEPD)Capacity changed from 13.474 MW to 12.16 MW−1.314 MW
- PV GENERATIONSouthern England (SEPD)Capacity changed from 11.789 MW to 10.64 MW−1.149 MW
- REDBRIDGE FARMSouthern England (SEPD)Capacity changed from 5.263 MW to 3.344 MW−1.919 MW
- ROWLES FARM PVSouthern England (SEPD)Capacity changed from 10.526 MW to 9.5 MW−1.026 MW
- ROWNHAMS IMPORTSouthern England (SEPD)Capacity changed from 21.19 MW to 20.131 MW−1.059 MW
- Site not namedSouthern England (SEPD)Capacity stated as 7.268 MW (not stated in the October 2023 edition)
- Site not namedNorth of Scotland (SHEPD)Capacity changed from 2.2 MW to 2.09 MW−0.11 MW
- Site not namedSouthern England (SEPD)Capacity changed from 7.95 MW to 7.553 MW−0.397 MW
- Site not namedSouthern England (SEPD)Capacity changed from 2.118 MW to 2.012 MW−0.106 MW
- SOLAR FARMSouthern England (SEPD)Customer changed from TUSC LTD to COOP PPA SITES
- SOUTH SOLAR FARMSouthern England (SEPD)Capacity changed from 40 MW to 38 MW−2 MW
- ST LAND ADJSouthern England (SEPD)Capacity changed from 10 MW to 9.5 MW−0.5 MW
- STANTON WATERS PVSouthern England (SEPD)Capacity changed from 4.211 MW to 3.8 MW−0.411 MW
- STUD FARMSouthern England (SEPD)Capacity changed from 8 MW to 7.6 MW−0.4 MW
- SUTTON BRIDGE PVSouthern England (SEPD)Capacity stated as 5.273 MW (not stated in the October 2023 edition)
- THORFINN A WIND ENERGY PROJECTNorth of Scotland (SHEPD)Customer changed from ORKNEY WIND TURBINE NM1500 to ORKNEY WIND TURBINE NM15DATA NOT AVAILABLEDATA NOT AVAILABLE
- THREE MAIDS HILL PVSouthern England (SEPD)Capacity changed from 25 MW to 23.75 MW−1.25 MW
- TILLINGHAM POWERSouthern England (SEPD)Capacity changed from 16.842 MW to 15.2 MW−1.642 MW
- UK POWER RESERVE WESTERN ROADSouthern England (SEPD)Capacity changed from 20 MW to 19 MW−1 MW
- UNIT 2Southern England (SEPD)Capacity changed from 4.211 MW to 3.849 MW−0.362 MW
- UNIT 2Southern England (SEPD)Export capacity changed from 3.8 MW to 3.849 MW
- UNIT A1 MARSTON TRADING ESTATESouthern England (SEPD)Capacity changed from 2.535 MW to 2.408 MW−0.127 MW
- UPPER GEISLITTLE / WEYDALENorth of Scotland (SHEPD)Customer changed from GVO WIND NO.40 LTD to GVO WIND NO.4DATA NOT AVAILABLE LTD
- WARREN FARM PVSouthern England (SEPD)Capacity changed from 5.262 MW to 4.749 MW−0.513 MW
- WATHERGAR 2 WIND FARMNorth of Scotland (SHEPD)Capacity changed from 23.684 MW to 22.5 MW−1.184 MW
- WELTON OF CREUCHIES WIND FARM S2North of Scotland (SHEPD)Capacity changed from 9.2 MW to 8.74 MW−0.46 MW
- WEST GOURDIE BESSNorth of Scotland (SHEPD)Capacity changed from 49.9 MW to 47.405 MW−2.495 MW
- WEST PITNACREE FARM, ALYTHNorth of Scotland (SHEPD)Capacity changed from 99.56 MW to 25 MW−74.56 MW
- WEST PITNACREE FARM, ALYTHNorth of Scotland (SHEPD)Export capacity changed from 49.8 MW to 25 MW
- WOODTOWN SOLAR LIMITEDSouthern England (SEPD)Capacity changed from 4.011 MW to 3.62 MW−0.391 MW
254 sites without a match in the other edition
In the November 2023 edition only (67)
In the October 2023 edition only (187)
September 2023 edition to October 2023 edition
No changes found.
1,441 sites matched. 4 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
4 sites without a match in the other edition
In the October 2023 edition only (2)
In the September 2023 edition only (2)
August 2023 edition to September 2023 edition
22 changes
1,354 sites matched. 108 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- *40MW - PVSouthern England (SEPD)Technology changed from Solar to Bioenergy and waste
- 49.9MW BESSNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- 50MW BESSNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- 50MW BESSNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- 66MW WINDNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- 99.56MW PV/BESSNorth of Scotland (SHEPD)Capacity changed from 25 MW to 99.56 MW+74.56 MW
- 99.56MW PV/BESSNorth of Scotland (SHEPD)Export capacity changed from 25 MW to 49.8 MW
- ABERDEEN BESS, NIGGNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- ALTENS 10MW PV + ELECTOLYSERNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- ALTENS 10MW PV + ELECTOLYSERNorth of Scotland (SHEPD)Technology changed from Solar to Bioenergy and waste
- AUTH - 49.9MW PVSouthern England (SEPD)Technology changed from Solar to Bioenergy and waste
- AUTH SP TR RECEIVEDSouthern England (SEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- AUTH SP TR RECEIVEDSouthern England (SEPD)Technology changed from Solar to Bioenergy and waste
- CAIRNBULG ESTATE BESSNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- CRAIGSHAW DRIVE EV & BESSNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- JS AUT 99.9MW BESSSouthern England (SEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- NEWTON OF PARK BESS 2North of Scotland (SHEPD)Customer changed from OPDE UK LIMITED to Name not shown
- SENT TO QCSouthern England (SEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- SENT TO QCSouthern England (SEPD)Technology changed from Other to Bioenergy and waste
- SPITTAL BESSNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the August 2023 edition)
- YZ-NTH FIELD COMPOUND - PV/EV/BATTERY (REQUOTE)Southern England (SEPD)Technology changed from Solar to Bioenergy and waste
- ZENOBE SHETLAND BACKUP BESSNorth of Scotland (SHEPD)Customer stated, name not shown (not stated in the August 2023 edition)
108 sites without a match in the other edition
In the September 2023 edition only (89)
In the August 2023 edition only (19)
SP Energy Networks
SPEN’s pageAugust 2026 edition to September 2026 edition
35 changes
773 sites matched. 2 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- AGS Calderside Farm SolarCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- AGS Calderside Farm SolarCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Ardoch Farm BESS (Kilwinning BESS)Central and Southern Scotland (SPD)Target energisation date moved from 30 Aug 2027 to 30 Jul 2027 (1 month earlier)
- Benthead Farm Solar and BESSCentral and Southern Scotland (SPD)Capacity changed from 70.4 MW to 113.43 MW+43.03 MW
- Benthead Farm Solar and BESSCentral and Southern Scotland (SPD)Target energisation date moved from 18 Sep 2026 to 1 Oct 2026 (13 days later)
- Burnbank Coatbridge BESSCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
- Dalmarnock Road BESS (Former Sanmex Site)Central and Southern Scotland (SPD)Target energisation date moved from 1 Sep 2026 to 11 Sep 2026 (10 days later)
- Dewshill Wind FarmCentral and Southern Scotland (SPD)Target energisation date moved from 3 Aug 2027 to 3 Sep 2027 (1 month later)
- Doveryard (Oldhall ERF)Central and Southern Scotland (SPD)Target energisation date moved from 29 Aug 2026 to 4 Sep 2026 (6 days later)
- Drumfad Battery Storage SystemCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2027 to 30 Oct 2027 (1 day earlier)
- Elderslie EstateCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Elderslie EstateCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Energy Park FifeCentral and Southern Scotland (SPD)Target energisation date moved from 30 Oct 2028 to 30 Oct 2029 (12 months later)
- Greenside FarmCentral and Southern Scotland (SPD)Target energisation date moved from 20 Nov 2027 to 28 Mar 2028 (4 months later)
- Holmston Farm (Previously Broomfield Lodge)Central and Southern Scotland (SPD)Target energisation date moved from 26 Aug 2026 to 21 Sep 2026 (1 month later)
- Inverkeithing Solar FarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Mar 2031 (not stated in the August 2026 edition)
- Kirknewton Solar & BESSCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Capacity changed from 2.25 MW to 2.175 MW−0.075 MW
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 2.25 MW to 2.175 MW
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the August 2026 edition)
- Lochfauld Solar ParkCentral and Southern Scotland (SPD)Target energisation date moved from 30 Aug 2026 to 9 Oct 2026 (1 month later)
- South Clyde Energy CentreCentral and Southern Scotland (SPD)Target energisation date moved from 13 Aug 2026 to 20 Sep 2026 (1 month later)
- Steven's Croft BiomassCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Strathaven West 69.8MWCentral and Southern Scotland (SPD)Target energisation date moved from 1 Jul 2029 to 31 Oct 2030 (16 months later)
- Thermo Fisher Inchinnan Solar GeneratorCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2029 to 31 Aug 2029 (2 months earlier)
- Thermo Fisher Inchinnan Solar Generator Alternative FeedCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2029 to 31 Aug 2029 (2 months earlier)
- Touch Energy ParkCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Westfield SolarCentral and Southern Scotland (SPD)Target energisation date moved from 28 Jan 2028 to 28 Apr 2028 (3 months later)
- Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
- Woodlands Farm WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the August 2026 edition)
2 sites without a match in the other edition
In the August 2026 edition only (2)
July 2026 edition to August 2026 edition
56 changes
768 sites matched. 8 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Andershaw WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Andershaw WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
- Andershaw WindfarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
- Andershaw WindfarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the July 2026 edition)
- Ardoch Farm BESS (Kilwinning BESS)Central and Southern Scotland (SPD)Target energisation date moved from 30 Apr 2027 to 30 Aug 2027 (4 months later)
- Benthead Farm Solar and BESSCentral and Southern Scotland (SPD)Target energisation date moved from 13 Aug 2026 to 18 Sep 2026 (1 month later)
- Bentley MotorsMerseyside, Cheshire and North Wales (SPM)Customer changed from Bentley Motors to QuiNotas ENoergy UK
- Bentley MotorsMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
- Doveryard (Oldhall ERF)Central and Southern Scotland (SPD)Target energisation date moved from 27 Jul 2026 to 29 Aug 2026 (1 month later)
- Getrag(Ford)Merseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
- Gladsmuir Wind FarmCentral and Southern Scotland (SPD)Capacity changed from 43.4 MW to 31 MW−12.4 MW
- Gladsmuir Wind FarmCentral and Southern Scotland (SPD)Export capacity changed from 41.5 MW to 31 MW
- Glenniston Solar and BESSCentral and Southern Scotland (SPD)Target energisation date moved from 3 Aug 2027 to 19 Jul 2028 (12 months later)
- Glenrothes BESSCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jun 2027 to 30 Sep 2027 (3 months later)
- Greengairs East WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36 MW to 24 MW−12 MW
- Greengairs East WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 36 MW to 24 MW
- Heights Wind FarmCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jun 2028 to 30 Aug 2028 (2 months later)
- Holmston Farm (Previously Broomfield Lodge)Central and Southern Scotland (SPD)Target energisation date moved from 24 Aug 2026 to 26 Aug 2026 (2 days later)
- Howpark WindfarmCentral and Southern Scotland (SPD)Capacity changed from 18.8 MW to 16 MW−2.8 MW
- Howpark WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 18.8 MW to 16 MW
- JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Capacity changed from 15.4 MW to 17.11 MW+1.71 MW
- JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 0.999 MW to 4.95 MW
- JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
- KronospanMerseyside, Cheshire and North Wales (SPM)Customer changed from River Island to Kronospan Limited
- KronospanMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 47.4 MW to 28 MW
- KronospanMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “yes” to “no”
- KronospanMerseyside, Cheshire and North Wales (SPM)Status changed from “accepted to connect” to “connected”Connected
- KronospanMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Capacity changed from 2.175 MW to 2.25 MW+0.075 MW
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 2.175 MW to 2.25 MW
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the July 2026 edition)
- Lochfauld Solar ParkCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jul 2026 to 30 Aug 2026 (1 month later)
- Longhill Burn WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36 MW to 50 MW+14 MW
- Longhill Burn WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 36 MW to 50 MW
- McQuittiston FarmCentral and Southern Scotland (SPD)Target energisation date moved from 29 Oct 2027 to 10 Dec 2027 (1 month later)
- Mill Rig WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Mill Rig WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (15 Jul 2026 in the July 2026 edition)
- Moor FarmMerseyside, Cheshire and North Wales (SPM)Customer changed from SPF Moorfarm Ltd to G59 Projects
- Nether FarmCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jun 2027 to 30 Sep 2027 (3 months later)
- Nutberry Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Nutberry Wind FarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Nutberry Wind FarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the July 2026 edition)
- Rogerton Cottage (Rogerton Avenue BESS)Central and Southern Scotland (SPD)Target energisation date moved from 1 Jul 2027 to 16 Aug 2027 (1 month later)
- Sorbie WindfarmCentral and Southern Scotland (SPD)Capacity changed from 7.5 MW to 12 MW+4.5 MW
- Sorbie WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 7.5 MW to 12.6 MW
- South Clyde Energy CentreCentral and Southern Scotland (SPD)Target energisation date moved from 14 Jul 2026 to 13 Aug 2026 (1 month later)
- St Marys Isle Solar FarmCentral and Southern Scotland (SPD)Target energisation date moved from 27 Jan 2030 to 27 Jun 2030 (5 months later)
- ToyotaMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “no” to “yes”
- ToyotaMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
- ToyotaMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
- Westfield SolarCentral and Southern Scotland (SPD)Target energisation date moved from 28 Apr 2028 to 28 Jan 2028 (3 months earlier)
- Wull Muir Wind FarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
- Wull Muir Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
8 sites without a match in the other edition
In the August 2026 edition only (7)
In the July 2026 edition only (1)
June 2026 edition to July 2026 edition
51 changes
766 sites matched. 18 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Aberangell FarmMerseyside, Cheshire and North Wales (SPM)Technology changed from Wind to Solar
- Airies WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36.7 MW to 39.9 MW+3.2 MW
- Andershaw WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
- Andershaw WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Andershaw WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Andershaw WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the June 2026 edition)
- Ardgowan EstateCentral and Southern Scotland (SPD)Capacity changed from 49.86 MW to 23.75 MW−26.11 MW
- Ardgowan EstateCentral and Southern Scotland (SPD)Export capacity changed from 49.9 MW to 20 MW
- Arran ViewCentral and Southern Scotland (SPD)Capacity changed from 40 MW to 50 MW+10 MW
- Arran ViewCentral and Southern Scotland (SPD)Export capacity changed from 20 MW to 49.9 MW
- Bentley MotorsMerseyside, Cheshire and North Wales (SPM)Capacity changed from 8 MW to 14.1 MW+6.1 MW
- Diageo SolarCentral and Southern Scotland (SPD)Capacity changed from 4.1 MW to 3.395 MW−0.705 MW
- Garviland Wind FarmCentral and Southern Scotland (SPD)Capacity changed from 24 MW to 13.5 MW−10.5 MW
- Garviland Wind FarmCentral and Southern Scotland (SPD)Export capacity changed from 21.3 MW to 12.5 MW
- Getrag(Ford)Merseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
- Greengairs East WindfarmCentral and Southern Scotland (SPD)Capacity changed from 24 MW to 36 MW+12 MW
- Greengairs East WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 24 MW to 36 MW
- IcelandMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “no” to “yes”
- IcelandMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
- IcelandMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
- JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
- KronospanMerseyside, Cheshire and North Wales (SPM)Capacity changed from 47.4 MW to 28 MW−19.4 MW
- KronospanMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Capacity changed from 2.25 MW to 2.175 MW−0.075 MW
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 2.25 MW to 2.175 MW
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the June 2026 edition)
- Longhill Burn WindfarmCentral and Southern Scotland (SPD)Capacity changed from 50 MW to 36 MW−14 MW
- Longhill Burn WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 50 MW to 36 MW
- Nutberry Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
- Nutberry Wind FarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
- Nutberry Wind FarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the June 2026 edition)
- Rolls RoyceMerseyside, Cheshire and North Wales (SPM)Capacity changed from 17.015 MW to 7.1 MW−9.915 MW
- Rolls RoyceMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 17.015 MW to 7.1 MW
- Shin Etsu CHPCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Shin Etsu CHPCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Shin Etsu CHPCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Shin Etsu CHPCentral and Southern Scotland (SPD)Target energisation date not stated (31 Dec 2025 in the June 2026 edition)
- Sorbie WindfarmCentral and Southern Scotland (SPD)Capacity changed from 12 MW to 7.5 MW−4.5 MW
- Sorbie WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 12.6 MW to 7.5 MW
- Stanwardine Grange PV & BESSMerseyside, Cheshire and North Wales (SPM)Technology changed from Storage to Solar
- Touch Energy ParkCentral and Southern Scotland (SPD)Capacity changed from 71.4 MW to 54 MW−17.4 MW
- ToyotaMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “yes” to “no”
- ToyotaMerseyside, Cheshire and North Wales (SPM)Status changed from “accepted to connect” to “connected”Connected
- ToyotaMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
- Williams Farm Solar (Phase 2)Merseyside, Cheshire and North Wales (SPM)Capacity changed from 16.27 MW to 10 MW−6.27 MW
- Williams Farm Solar (Phase 2)Merseyside, Cheshire and North Wales (SPM)Customer changed from Renewabuild to Solar Ventures
- Williams Farm Solar (Phase 2)Merseyside, Cheshire and North Wales (SPM)Technology changed from Storage to Solar
- Wull Muir Wind FarmCentral and Southern Scotland (SPD)Target energisation date not stated (1 Oct 2029 in the June 2026 edition)
18 sites without a match in the other edition
In the July 2026 edition only (3)
In the June 2026 edition only (15)
May 2026 edition to June 2026 edition
51 changes
764 sites matched. 19 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Aberangell FarmMerseyside, Cheshire and North Wales (SPM)Technology changed from Storage to Wind
- Ash RoadMerseyside, Cheshire and North Wales (SPM)Capacity changed from 5 MW to 4.9 MW−0.1 MW
- Ash RoadMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 5 MW to 4.9 MW
- Bankend Rig Extension WindfarmCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2028 to 1 Oct 2028 (1 month earlier)
- Bwlch Y CibauMerseyside, Cheshire and North Wales (SPM)Capacity changed from 5 MW to 4.9 MW−0.1 MW
- Bwlch Y CibauMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 5 MW to 4.9 MW
- BYK AdditivesMerseyside, Cheshire and North Wales (SPM)Customer stated as BYK Additives Limited (not stated in the May 2026 edition)
- Caergeiliog Solar FarmMerseyside, Cheshire and North Wales (SPM)Capacity changed from 49.2 MW to 28.5 MW−20.7 MW
- Caergeiliog Solar FarmMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 49.2 MW to 28.5 MW
- Dalmarnock Road BESS (Former Sanmex Site)Central and Southern Scotland (SPD)Target energisation date moved from 11 Aug 2026 to 1 Sep 2026 (1 month later)
- Drumcross BESS (Muirhall)Central and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Drumcross BESS (Muirhall)Central and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Drumcross BESS (Muirhall)Central and Southern Scotland (SPD)Target energisation date not stated (28 May 2026 in the May 2026 edition)
- Flatterton FarmCentral and Southern Scotland (SPD)Capacity changed from 53.2 MW to 58.8 MW+5.6 MW
- Flatterton FarmCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jun 2027 to 28 Jun 2028 (12 months later)
- Getrag(Ford)Merseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
- Gowy Landfill 3Merseyside, Cheshire and North Wales (SPM)Target energisation date not stated (1 Dec 2030 in the May 2026 edition)
- IcelandMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “yes” to “no”
- IcelandMerseyside, Cheshire and North Wales (SPM)Status changed from “accepted to connect” to “connected”Connected
- IcelandMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
- Iddenshall GrangeMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “yes” to “no”
- Iddenshall GrangeMerseyside, Cheshire and North Wales (SPM)Status changed from “accepted to connect” to “connected”Connected
- JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
- KronospanMerseyside, Cheshire and North Wales (SPM)Customer changed from Kronospan Limited to River Island
- KronospanMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “no” to “yes”
- KronospanMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
- Longhill Burn WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36 MW to 50 MW+14 MW
- Longhill Burn WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 36 MW to 50 MW
- Mill Rig WindfarmCentral and Southern Scotland (SPD)Target energisation date moved from 22 Jun 2026 to 15 Jul 2026 (1 month later)
- Monashee WindfarmCentral and Southern Scotland (SPD)Target energisation date moved from 1 Feb 2029 to 28 Feb 2029 (1 month later)
- Pen-Y-GroesMerseyside, Cheshire and North Wales (SPM)Capacity changed from 39.96 MW to 15.96 MW−24 MW
- Pen-Y-GroesMerseyside, Cheshire and North Wales (SPM)Technology stated as Wind (not stated in the May 2026 edition)
- Rogerton Cottage (Rogerton Avenue BESS)Central and Southern Scotland (SPD)Target energisation date moved from 30 Apr 2027 to 1 Jul 2027 (2 months later)
- Rolls RoyceMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 8 MW to 17.015 MW
- Rolls RoyceMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “yes” to “no”
- Rolls RoyceMerseyside, Cheshire and North Wales (SPM)Status changed from “accepted to connect” to “connected”Connected
- Sheriff Faulds FarmCentral and Southern Scotland (SPD)Capacity changed from 49.4 MW to 58.8 MW+9.4 MW
- Sheriff Faulds FarmCentral and Southern Scotland (SPD)Target energisation date moved from 28 Jun 2027 to 20 Aug 2027 (2 months later)
- South Clyde Energy CentreCentral and Southern Scotland (SPD)Target energisation date moved from 1 Jun 2026 to 14 Jul 2026 (1 month later)
- Southrigg 2Central and Southern Scotland (SPD)Target energisation date moved from 30 Mar 2027 to 30 Mar 2028 (12 months later)
- Stanwardine Grange PV & BESSMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Storage
- ToyotaMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “no” to “yes”
- ToyotaMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
- ToyotaMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
- Ty Du UchafMerseyside, Cheshire and North Wales (SPM)Capacity changed from 6 MW to 4.7 MW−1.3 MW
- Ty Du UchafMerseyside, Cheshire and North Wales (SPM)Export capacity changed from 6 MW to 4.7 MW
- Tyler HillCentral and Southern Scotland (SPD)Target energisation date moved from 30 Jul 2027 to 30 Mar 2028 (8 months later)
- Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Woodlands Farm WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
- Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
- Woodlands Farm WindfarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the May 2026 edition)
19 sites without a match in the other edition
In the June 2026 edition only (17)
In the May 2026 edition only (2)
April 2026 edition to May 2026 edition
128 changes
766 sites matched. Every April site and every May site had a match in the other edition.
- Aber ParkMerseyside, Cheshire and North Wales (SPM)Customer stated as Conrad Energy (Developments) Ltd (not stated in the April 2026 edition)
- Abercorn Street GasCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- AGS Bonnyton SolarCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- AGS Calderside Farm SolarCentral and Southern Scotland (SPD)Customer stated as Advanced Grid Solutions Ltd (not stated in the April 2026 edition)
- Aikengall WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Airies WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Almondell BESS (Broxburn BESS)Central and Southern Scotland (SPD)Customer stated as Ethical Power Connections Ltd (not stated in the April 2026 edition)
- Almondell BESS (Broxburn BESS)Central and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Almondell BESS (Broxburn BESS)Central and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2025 (not stated in the April 2026 edition)
- Andershaw WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Andershaw WindfarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
- Andershaw WindfarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the April 2026 edition)
- Ardgowan EstateCentral and Southern Scotland (SPD)Capacity changed from 23.75 MW to 49.86 MW+26.11 MW
- Ardgowan EstateCentral and Southern Scotland (SPD)Export capacity changed from 20 MW to 49.9 MW
- Arran ViewCentral and Southern Scotland (SPD)Capacity changed from 50 MW to 40 MW−10 MW
- Arran ViewCentral and Southern Scotland (SPD)Export capacity changed from 49.9 MW to 20 MW
- Assel Valley WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Auchencarroch LandfillCentral and Southern Scotland (SPD)Customer stated as Auchencarroch Energy Ltd (not stated in the April 2026 edition)
- Auchrobert WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Balmore WTWCentral and Southern Scotland (SPD)Customer changed from SP Distribution plc to FES Support Services
- Balmore WTW ExtensionCentral and Southern Scotland (SPD)Customer stated as Scottish Water Horizons Limited (not stated in the April 2026 edition)
- Bentley MotorsMerseyside, Cheshire and North Wales (SPM)Target energisation date stated as 1 Sep 2023 (not stated in the April 2026 edition)
- Blackburn Wind FarmCentral and Southern Scotland (SPD)Customer stated as Wind Estate (UK) Ltd. (not stated in the April 2026 edition)
- Bowbeat Wind Energy HubCentral and Southern Scotland (SPD)Customer stated as Belltown Power UK Limited (not stated in the April 2026 edition)
- Bridgewater PaperMerseyside, Cheshire and North Wales (SPM)Target energisation date stated as 30 Sep 2023 (not stated in the April 2026 edition)
- Bruach / Croich HydroCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2015 (not stated in the April 2026 edition)
- Bryn Plentyn FarmMerseyside, Cheshire and North Wales (SPM)Customer stated as Cr & Gm Woollam & Son (not stated in the April 2026 edition)
- Buildwas Rd 1 (Longacres)Merseyside, Cheshire and North Wales (SPM)Target energisation date stated as 17 Nov 2023 (not stated in the April 2026 edition)
- Camilla Energy Park Battery StorageCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Camilty WindfarmCentral and Southern Scotland (SPD)Target energisation date moved from 30 Mar 2027 to 30 Sep 2027 (6 months later)
- Castlehill Road Multi G98Central and Southern Scotland (SPD)Target energisation date moved from 31 Dec 2025 to 31 Dec 2027 (24 months later)
- Cathkin BESSCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Cefn EstateMerseyside, Cheshire and North Wales (SPM)Customer stated as Anesco Ltd (not stated in the April 2026 edition)
- Clwyd CloseMerseyside, Cheshire and North Wales (SPM)Customer stated as Dee Tech Services Ltd (not stated in the April 2026 edition)
- Colton Farm (Dunfermline Solar PV & BESS)Central and Southern Scotland (SPD)Target energisation date stated as 31 Dec 2023 (not stated in the April 2026 edition)
- Craigannet Wind TurbineCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Craigdow Hill Farm Wind and BESSCentral and Southern Scotland (SPD)Customer stated as AEUK Wind Project I Ltd (not stated in the April 2026 edition)
- Crookedstone Farm PVCentral and Southern Scotland (SPD)Customer stated as Enviromena Project Management UK Limited (not stated in the April 2026 edition)
- Dalmarnock Road BESS (Former Sanmex Site)Central and Southern Scotland (SPD)Target energisation date moved from 11 May 2026 to 11 Aug 2026 (3 months later)
- Ditton RoadMerseyside, Cheshire and North Wales (SPM)Customer changed from Horizon Power & Energy Ltd to Halton Borough Council
- Dock Yard PowerMerseyside, Cheshire and North Wales (SPM)Customer stated as Urban Reserve (Assettco) Ltd (not stated in the April 2026 edition)
- Doveryard (Oldhall ERF)Central and Southern Scotland (SPD)Target energisation date moved from 27 May 2026 to 27 Jul 2026 (2 months later)
- Drumcross BESS (Muirhall)Central and Southern Scotland (SPD)Target energisation date moved from 8 May 2026 to 28 May 2026 (1 month later)
- DSM-FirmenichCentral and Southern Scotland (SPD)Customer stated as The Farm Energy Partnership (not stated in the April 2026 edition)
- Dun Law Windfarm RepoweringCentral and Southern Scotland (SPD)Customer stated as Belltown Power UK Ltd (not stated in the April 2026 edition)
- Duniface Farm BESS (Leven BESS)Central and Southern Scotland (SPD)Customer stated as Forsa Energy Gas Holdings Ltd (not stated in the April 2026 edition)
- Dunwan Dam Wind FarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Dunwan Dam Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Easter Drumclair (formerly Greenhills WF)Central and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Edinburgh Airport SolarCentral and Southern Scotland (SPD)Target energisation date not stated (31 Dec 2025 in the April 2026 edition)
- Erkeksi Power Station (Milton Farm)Central and Southern Scotland (SPD)Customer stated as Renewco Power Ltd (not stated in the April 2026 edition)
- Factory RoadMerseyside, Cheshire and North Wales (SPM)Customer stated as Coveris Winsford Limited (not stated in the April 2026 edition)
- Fechan Generation Facility (Minsca extension)Central and Southern Scotland (SPD)Customer stated as Renewco Power Ltd (not stated in the April 2026 edition)
- Ferrymuir Energy StorageCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Flint C, Aber Park, Aber Road, Flint, FlMerseyside, Cheshire and North Wales (SPM)Customer stated as Conrad Energy (Developments) Ltd (not stated in the April 2026 edition)
- G59 Colwydr Cyf, Gwynedd LL55 4UUMerseyside, Cheshire and North Wales (SPM)Customer stated as Ellergreen Hydro Ltd (not stated in the April 2026 edition)
- Gilmerton 50MW BESSCentral and Southern Scotland (SPD)Customer stated as Trina Solar (not stated in the April 2026 edition)
- Glenchamber WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- GlenfarmCentral and Southern Scotland (SPD)Flexible connection changed from “no” to “yes”
- GlenfarmCentral and Southern Scotland (SPD)In a connection queue changed from “no” to “yes”
- Gowy Landfill 3Merseyside, Cheshire and North Wales (SPM)Target energisation date stated as 1 Dec 2030 (not stated in the April 2026 edition)
- Great Bear DistributionMerseyside, Cheshire and North Wales (SPM)Customer stated as Urban Reserve (Assettco) Ltd (not stated in the April 2026 edition)
- Greengairs East WindfarmCentral and Southern Scotland (SPD)Capacity changed from 36 MW to 24 MW−12 MW
- Greengairs East WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 36 MW to 24 MW
- Greengairs East WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Greenside FarmCentral and Southern Scotland (SPD)Target energisation date moved from 30 May 2027 to 20 Nov 2027 (6 months later)
- Guala Closures GartcoshCentral and Southern Scotland (SPD)Target energisation date stated as 31 Dec 2027 (not stated in the April 2026 edition)
- Gwytherin Wind FarmMerseyside, Cheshire and North Wales (SPM)Customer stated as Alerion Uk Ltd (not stated in the April 2026 edition)
- Harehill Extn WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Holmston Farm (Previously Broomfield Lodge)Central and Southern Scotland (SPD)Target energisation date moved from 4 Aug 2026 to 24 Aug 2026 (1 month later)
- Hooton Bio PowerMerseyside, Cheshire and North Wales (SPM)Customer stated as North Lanarkshire Bio Power Limited (not stated in the April 2026 edition)
- Howpark WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Customer stated as Jaguar Land Rover Ltd (not stated in the April 2026 edition)
- Kirk Hill WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Capacity changed from 2.175 MW to 2.25 MW+0.075 MW
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 2.175 MW to 2.25 MW
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Status changed from “connected” to “accepted to connect”
- Lesmahagow WindfarmCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2028 (not stated in the April 2026 edition)
- Linwood WWTWCentral and Southern Scotland (SPD)Target energisation date not stated (31 Dec 2025 in the April 2026 edition)
- Lochfergus FarmCentral and Southern Scotland (SPD)Capacity changed from 87.8 MW to 99.278 MW+11.478 MW
- Longhill Burn WindfarmCentral and Southern Scotland (SPD)Capacity changed from 50 MW to 36 MW−14 MW
- Longhill Burn WindfarmCentral and Southern Scotland (SPD)Export capacity changed from 50 MW to 36 MW
- Longhill Burn WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Macfarlan Smith CHPCentral and Southern Scotland (SPD)Capacity changed from 2.478 MW to 2.028 MW−0.45 MW
- Macfarlan Smith CHPCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Macfarlan Smith CHPCentral and Southern Scotland (SPD)Target energisation date not stated (31 Dec 2025 in the April 2026 edition)
- Marshall North Wind TurbineCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2029 (not stated in the April 2026 edition)
- MATERNITY HOSPITALMerseyside, Cheshire and North Wales (SPM)Customer stated as Equans Services Ltd (not stated in the April 2026 edition)
- Meadowhead WWTWCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Meadowhead WWTWCentral and Southern Scotland (SPD)Target energisation date not stated (31 Dec 2025 in the April 2026 edition)
- Monashee WindfarmCentral and Southern Scotland (SPD)Target energisation date moved from 1 Feb 2028 to 1 Feb 2029 (12 months later)
- Moss Farm (Southport)Merseyside, Cheshire and North Wales (SPM)Customer stated as Taiyo Power & Storage Ltd (not stated in the April 2026 edition)
- Nairn Road AlphaCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Nairn Road BravoCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Nairn Road Gas (Drumcross Gas)Central and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- NORTH SEAFORTHMerseyside, Cheshire and North Wales (SPM)Customer stated as E.On Uk Heat Limited (not stated in the April 2026 edition)
- Nutberry Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Nutberry Wind FarmCentral and Southern Scotland (SPD)Status changed from “accepted to connect” to “connected”Connected
- Nutberry Wind FarmCentral and Southern Scotland (SPD)Target energisation date not stated (31 Oct 2028 in the April 2026 edition)
- Old Greenock Road (Erskine BESS)Central and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Pearie Law WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Pen-Y-GroesMerseyside, Cheshire and North Wales (SPM)Customer stated as Arc-Tech Mu Ltd (not stated in the April 2026 edition)
- Penmanshiel WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Pines Burn Windfarm (Fernilees Windfarm)Central and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Pitkevey Energy StorageCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Quixwood WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Rhosgoch SocketMerseyside, Cheshire and North Wales (SPM)Target energisation date stated as 17 Nov 2023 (not stated in the April 2026 edition)
- Rigmuir FarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Ross PrioryCentral and Southern Scotland (SPD)Target energisation date moved from 31 Dec 2025 to 31 Dec 2027 (24 months later)
- Shepards House (Moor House)Central and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Shilton Lane BESSCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Solar PV 13 Ash Road South, Wrexham, LL1Merseyside, Cheshire and North Wales (SPM)Customer stated as Aniron Ltd (not stated in the April 2026 edition)
- Solwaybank WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Sorbie WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- St James Energy Centre CHPCentral and Southern Scotland (SPD)Target energisation date not stated (31 Dec 2025 in the April 2026 edition)
- St Marys Isle Solar FarmCentral and Southern Scotland (SPD)Target energisation date moved from 27 Feb 2030 to 27 Jan 2030 (1 month earlier)
- Strathaven West 69.8MWCentral and Southern Scotland (SPD)Target energisation date moved from 31 Oct 2030 to 1 Jul 2029 (16 months earlier)
- Tormywheel Wind extensionCentral and Southern Scotland (SPD)Export capacity changed from 9.5 MW to 9.4 MW
- Torrance Farm Windfarm ExtensionCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Tyler HillCentral and Southern Scotland (SPD)Target energisation date moved from 30 Aug 2027 to 30 Jul 2027 (1 month earlier)
- West Benhar Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Westfield ERFCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Westfield SolarCentral and Southern Scotland (SPD)Target energisation date moved from 28 Aug 2027 to 28 Apr 2028 (8 months later)
- Woodlands Farm WindfarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Wull Muir Wind FarmCentral and Southern Scotland (SPD)Flexible connection changed from “yes” to “no”
- Wull Muir Wind FarmCentral and Southern Scotland (SPD)In a connection queue changed from “yes” to “no”
- Wykey FarmMerseyside, Cheshire and North Wales (SPM)Customer stated as W H Gittins & Sons (not stated in the April 2026 edition)
March 2026 edition to April 2026 edition
16 changes
765 sites matched. 3 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Aberangell FarmMerseyside, Cheshire and North Wales (SPM)Technology changed from Wind to Storage
- Getrag(Ford)Merseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
- IcelandMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “no” to “yes”
- IcelandMerseyside, Cheshire and North Wales (SPM)Status changed from “connected” to “accepted to connect”
- IcelandMerseyside, Cheshire and North Wales (SPM)Technology changed from Gas and other fossil to Solar
- JAGUAR LANDROVERMerseyside, Cheshire and North Wales (SPM)Technology changed from Solar to Gas and other fossil
- KronospanMerseyside, Cheshire and North Wales (SPM)Customer changed from River Island to Kronospan Limited
- KronospanMerseyside, Cheshire and North Wales (SPM)In a connection queue changed from “yes” to “no”
- KronospanMerseyside, Cheshire and North Wales (SPM)Status changed from “accepted to connect” to “connected”Connected
- Moor FarmMerseyside, Cheshire and North Wales (SPM)Customer changed from G59 Projects to SPF Moorfarm Ltd
- Rutherglen ParkCentral and Southern Scotland (SPD)Target energisation date moved from 1 Jan 2027 to 1 Oct 2027 (9 months later)
- South Clyde Energy CentreCentral and Southern Scotland (SPD)Target energisation date moved from 24 May 2026 to 1 Jun 2026 (8 days later)
- Thermo Fisher Inchinnan Solar GeneratorCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2029 (not stated in the March 2026 edition)
- Thermo Fisher Inchinnan Solar Generator Alternative FeedCentral and Southern Scotland (SPD)Target energisation date stated as 31 Oct 2029 (not stated in the March 2026 edition)
- Tyler HillCentral and Southern Scotland (SPD)Target energisation date moved from 30 May 2027 to 30 Aug 2027 (3 months later)
- Wemyss Estate PVCentral and Southern Scotland (SPD)Target energisation date moved from 1 Oct 2023 to 1 Jun 2027 (44 months later)
3 sites without a match in the other edition
In the April 2026 edition only (1)
In the March 2026 edition only (2)
Northern Powergrid
Northern Powergrid’s pageOctober 2026 edition to November 2026 edition
No changes found.
933 sites matched. 5 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
5 sites without a match in the other edition
In the November 2026 edition only (4)
In the October 2026 edition only (1)
September 2026 edition to October 2026 edition
6 changes
929 sites matched. 7 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Knapton HybridNorth East (Northern Powergrid)Export capacity changed from 114 MW to 41.5 MW
- Knapton HybridNorth East (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
- Station Road CHPNorth East (Northern Powergrid)Capacity changed from 3.8 MW to 4.7 MW+0.9 MW
- Station Road CHPNorth East (Northern Powergrid)Customer changed from Jan Bezemer And Sons Ltd to Station Road CHP
- Station Road CHPNorth East (Northern Powergrid)Export capacity changed from 3.8 MW to 4.7 MW
- Station Road CHPNorth East (Northern Powergrid)Status changed from “connected” to “accepted to connect”
7 sites without a match in the other edition
In the October 2026 edition only (5)
In the September 2026 edition only (2)
August 2026 edition to September 2026 edition
1 change
928 sites matched. 12 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Western School PVYorkshire (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
12 sites without a match in the other edition
In the September 2026 edition only (3)
In the August 2026 edition only (9)
July 2026 edition to August 2026 edition
7 changes
887 sites matched. 99 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Bradford Royal InfirmaryYorkshire (Northern Powergrid)Capacity changed from 5.094 MW to 5.214 MW+0.12 MW
- Bradford Royal InfirmaryYorkshire (Northern Powergrid)Export capacity changed from 0 MW to 0.778 MW
- Castle Hill HospitalYorkshire (Northern Powergrid)Export capacity changed from 1.521 MW to 4 MW
- Land south of Skeeby SubstationNorth East (Northern Powergrid)Export capacity changed from 73.23 MW to 39.33 MW
- Land south of Skeeby SubstationNorth East (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
- Pennywell Industrial Estate PVNorth East (Northern Powergrid)Export capacity changed from 2.09 MW to 0.99 MW
- Pennywell Industrial Estate PVNorth East (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
99 sites without a match in the other edition
In the August 2026 edition only (50)
In the July 2026 edition only (49)
June 2026 edition to July 2026 edition
3 changes
935 sites matched. 11 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Ashcourt Forster Street WindYorkshire (Northern Powergrid)Export capacity changed from 1 MW to 0.25 MW
- Ashcourt Forster Street WindYorkshire (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
- York Road PVYorkshire (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
11 sites without a match in the other edition
In the July 2026 edition only (1)
In the June 2026 edition only (10)
May 2026 edition to June 2026 edition
26 changes
941 sites matched. 6 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Bawtry Solar FarmYorkshire (Northern Powergrid)Capacity changed from 51 MW to 40 MW−11 MW
- Bawtry Solar FarmYorkshire (Northern Powergrid)Export capacity changed from 51 MW to 40 MW
- Bochum Parkway Combined TechYorkshire (Northern Powergrid)Technology changed from Solar to Storage
- California Hybrid Solar & BESSNorth East (Northern Powergrid)Flexible connection changed from “no” to “yes”
- Carr Edge Farm BESSNorth East (Northern Powergrid)Technology changed from Storage to Solar
- Grange Road Multitech (38307)Yorkshire (Northern Powergrid)Capacity changed from 68.7 MW to 59.9 MW−8.8 MW
- Grange Road Multitech (38307)Yorkshire (Northern Powergrid)Export capacity changed from 68.7 MW to 59.9 MW
- Grange Road Multitech (38307)Yorkshire (Northern Powergrid)Technology changed from Gas and other fossil to Solar
- IDNO Routh40Yorkshire (Northern Powergrid)Capacity changed from 40 MW to 80 MW+40 MW
- IDNO Routh40Yorkshire (Northern Powergrid)Export capacity changed from 40 MW to 80 MW
- IDNO Routh40Yorkshire (Northern Powergrid)Flexible connection changed from “no” to “yes”
- Land south of Skeeby SubstationNorth East (Northern Powergrid)Capacity changed from 39.33 MW to 73.23 MW+33.9 MW
- Land south of Skeeby SubstationNorth East (Northern Powergrid)Export capacity changed from 39.33 MW to 73.23 MW
- Low Bohemia FarmNorth East (Northern Powergrid)Capacity changed from 49.999 MW to 59.9 MW+9.901 MW
- Low Bohemia FarmNorth East (Northern Powergrid)Export capacity changed from 49.999 MW to 59.9 MW
- Low Bohemia FarmNorth East (Northern Powergrid)Flexible connection changed from “no” to “yes”
- Old Malton Solar PV and BESSNorth East (Northern Powergrid)Capacity changed from 49.9 MW to 61.9 MW+12 MW
- Old Malton Solar PV and BESSNorth East (Northern Powergrid)Export capacity changed from 49.9 MW to 61.9 MW
- Parkcliff Farm BESSYorkshire (Northern Powergrid)Capacity changed from 49.99 MW to 88.59 MW+38.6 MW
- Parkcliff Farm BESSYorkshire (Northern Powergrid)Export capacity changed from 49.99 MW to 88.59 MW
- Rawcliffe GasYorkshire (Northern Powergrid)Technology changed from Gas and other fossil to Solar
- South West of Station LaneNorth East (Northern Powergrid)Capacity changed from 6 MW to 16 MW+10 MW
- South West of Station LaneNorth East (Northern Powergrid)Export capacity changed from 6 MW to 16 MW
- Warren Lane PhotovoltaicYorkshire (Northern Powergrid)Capacity changed from 38 MW to 80 MW+42 MW
- Warren Lane PhotovoltaicYorkshire (Northern Powergrid)Export capacity changed from 38 MW to 80 MW
- Warren Lane PhotovoltaicYorkshire (Northern Powergrid)Technology changed from Solar to Storage
6 sites without a match in the other edition
In the June 2026 edition only (4)
In the May 2026 edition only (2)
April 2026 edition to May 2026 edition
2 changes
942 sites matched. 2 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Otley Road CHPYorkshire (Northern Powergrid)Export capacity changed from 1.25 MW to 3.308 MW
- Otley Road CHPYorkshire (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
2 sites without a match in the other edition
In the May 2026 edition only (1)
In the April 2026 edition only (1)
March 2026 edition to April 2026 edition
5 changes
940 sites matched. 13 sites couldn’t be matched between the two editions, because their details changed or they appear in only one.
- Grimsby SolarYorkshire (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
- John Charles Stadium PVYorkshire (Northern Powergrid)Export capacity changed from 1.4 MW to 0.625 MW
- John Charles Stadium PVYorkshire (Northern Powergrid)Status changed from “accepted to connect” to “connected”Connected
- Station Sawmills BESSNorth East (Northern Powergrid)Capacity changed from 3.5 MW to 2.845 MW−0.655 MW
- Station Sawmills BESSNorth East (Northern Powergrid)Technology changed from Storage to Solar
13 sites without a match in the other edition
In the April 2026 edition only (3)
In the March 2026 edition only (10)
Electricity North West
ENWL’s pageSeptember 2026 edition to October 2026 edition
No changes found.
561 sites matched. Every September site and every October site had a match in the other edition.
May 2026 edition to September 2026 edition
3 changes
559 sites matched. 7 sites couldn’t be matched between the two editions, because their details changed or they appear in only one. QueueWatch holds no edition between these two (4 months apart). ENWL’s May 2026 edition: its rows were last updated on 22 June 2026.
- BARROW FLOATING SOLARNorth West England (ENWL)Capacity changed from 0 MW to 11 MW+11 MW
- SOWERBY LODGE FARMNorth West England (ENWL)Capacity stated as 38 MW (not stated in the May 2026 edition)
- WHITWORTHNorth West England (ENWL)Capacity stated as 5 MW (not stated in the May 2026 edition)
7 sites without a match in the other edition
In the September 2026 edition only (2)
In the May 2026 edition only (5)
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?