QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

The distribution connection queue

Every site of 1 MW and over in the six distribution network operators' Embedded Capacity Registers, connected and accepted to connect. Each DNO publishes its register once a month; QueueWatch keeps every edition and reports what changed from one to the next.

6,649sites of 1 MW and over
156.7 GWcapacity
43.6 GWconnected (3,905 sites)
113.1 GWaccepted to connect (2,744 sites)

The DNOs publish on their own timetables, so these totals add editions of different months: UKPN October 2026, NGED August 2026, SSEN September 2026, SPEN September 2026, Northern Powergrid September 2026, ENWL September 2026.

By DNO

DNORegister and editionSitesCapacityConnected sitesConnectedAccepted sitesAccepted to connect
UK Power NetworksEmbedded Capacity Register 2 – 1MW and above, October 2026 edition1,04123.3 GW6919.8 GW35013.5 GW
National Grid Electricity DistributionEmbedded Capacity Register, August 2026 edition2,04242.3 GW1,23910.7 GW80331.6 GW
Scottish and Southern Electricity NetworksEmbedded Capacity Register, September 2026 edition1,30132 GW7067.7 GW59524.3 GW
SP Energy NetworksEmbedded Capacity Register >1MW, September 2026 edition77317.1 GW4836.3 GW29010.8 GW
Northern PowergridEmbedded Capacity Register 1MW and Over, September 2026 edition93130.1 GW4855.9 GW44624.2 GW
Electricity North WestEmbedded Capacity Register 2 – 1MW and above, September 2026 edition56111.9 GW3013.2 GW2608.7 GW
All six6,649156.7 GW3,90543.6 GW2,744113.1 GW

A site counts once, at its registered capacity: connected, or accepted to connect. Sites under 1 MW are left out, including the 50 kW to 1 MW sites National Grid Electricity Distribution publishes in the same file.

By technology

TechnologySitesCapacityConnectedAccepted to connect
Solar2,72059.6 GW11.6 GW48 GW
Storage99053 GW5.1 GW47.9 GW
Wind93119.9 GW10 GW9.9 GW
Gas and other fossil98811.4 GW9.7 GW1.7 GW
Bioenergy and waste6356 GW4.5 GW1.5 GW
Other or not stated2635.8 GW1.8 GW4 GW
Hydro and marine1221 GW0.8 GW0.2 GW

Each site is grouped by its first energy source, as the register names it.

By status

StatusSitesCapacity
Connected3,90543.6 GW
Accepted to connect2,744113.1 GW
All sites6,649156.7 GW

Each status as its DNO's register gives it.

Busiest grid supply points

The most capacity connected and accepted to connect, each in its DNO's latest edition.

  • WalpoleUKPN, 99 sites. 1.3 GW connected, 2 GW accepted to connect3.3 GW
  • HARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUPENWL, 127 sites. 0.8 GW connected, 2 GW accepted to connect2.8 GW
  • Ferrybridge BNorthern Powergrid, 57 sites. 0.3 GW connected, 2.1 GW accepted to connect2.4 GW
  • Bicker Fen 132Kv S StnNGED, 46 sites. 0.3 GW connected, 2.1 GW accepted to connect2.4 GW
  • KeadbyNorthern Powergrid, 66 sites. 0.6 GW connected, 1.8 GW accepted to connect2.4 GW
  • BramfordUKPN, 109 sites. 1 GW connected, 1.3 GW accepted to connect2.3 GW
  • NorwichUKPN, 76 sites. 1.1 GW connected, 1.1 GW accepted to connect2.2 GW
  • Ratcliffe On Soar 132Kv S StnNGED, 60 sites. 0.2 GW connected, 2 GW accepted to connect2.2 GW
  • COWLEY GSPSSEN, 71 sites. 0.4 GW connected, 1.6 GW accepted to connect2 GW
  • NortonNorthern Powergrid, 67 sites. 0.4 GW connected, 1.6 GW accepted to connect2 GW
  • MELKSHAM GSPSSEN, 96 sites. 0.5 GW connected, 1.5 GW accepted to connect2 GW
  • Grendon 132Kv S StnNGED, 81 sites. 0.4 GW connected, 1.6 GW accepted to connect2 GW

Largest customers

The most capacity connected and accepted to connect across the six registers, under one name however each register writes it. Names withheld in a register are left out. Each with two or more sites links to its page.

Accepted to connect, by target energisation year

Each DNO's sites accepted to connect, by the year of the target energisation date its register gives them, in its own latest edition. The DNOs do not set these dates the same way, so they are never added together. Northern Powergrid publishes no target energisation dates.

UKPN, October 2026 edition

Target yearSitesCapacity
2024220.6 GW
2025361.2 GW
2026100.3 GW
202760.4 GW
2028401.3 GW
202960.4 GW
2030190.6 GW
2031211 GW
2032150.5 GW
203330.2 GW
2034260.8 GW
203660.2 GW
203770.5 GW
Not stated1335.5 GW
Accepted to connect35013.5 GW

NGED, August 2026 edition

Target yearSitesCapacity
2021149.9 MW
20261934.6 GW
202750722.9 GW
2028281 GW
2029160.6 GW
203070.2 GW
203120.1 GW
203240.2 GW
203350.5 GW
203430.1 GW
203670.2 GW
2037201.1 GW
203810.1 GW
2039153.1 MW
Not stated818 MW
Accepted to connect80331.6 GW

SSEN, September 2026 edition

Target yearSitesCapacity
2025421.2 GW
20261073.1 GW
2027872.5 GW
2028571.7 GW
2029291.1 GW
2030371.8 GW
2031322.1 GW
2032331.8 GW
2033382 GW
2034130.5 GW
2035100.5 GW
2036251.4 GW
2037593 GW
2038161.5 GW
Not stated100.1 GW
Accepted to connect59524.3 GW

SPEN, September 2026 edition

Target yearSitesCapacity
2021115 MW
2022338.9 MW
202370.1 GW
202440.3 GW
202540.3 GW
2026150.6 GW
2027421.7 GW
2028562.7 GW
2029160.4 GW
2030180.8 GW
2031210.9 GW
2032130.7 GW
203370.3 GW
2034130 MW
203520.1 GW
203630.2 GW
203790.2 GW
Not stated681.5 GW
Accepted to connect29010.8 GW

ENWL, September 2026 edition

Target yearSitesCapacity
202520.1 GW
202617 MW
202740.1 GW
Not stated2538.5 GW
Accepted to connect2608.7 GW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose