QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / Sites / Customer

ECODEV GROUP LTD

Customer named in the DNOs' registers

In NGED's August 2026, SSEN's September 2026, SPEN's September 2026 and ENWL's September 2026 editions

The registers spell this customer’s name more than one way: “ECODEV GROUP LTD” (3 sites), “EcoDev Group Ltd” (1 site) and “Ecodev group ltd” (1 site).

5sites of 1 MW and over
224 MWcapacity
–connected (0 sites)
224 MWaccepted to connect (5 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
NGEDAugust 2026 edition14 MW–4 MW
SSENSeptember 2026 edition2150 MW–150 MW
SPENSeptember 2026 edition150 MW–50 MW
ENWLSeptember 2026 edition120 MW–20 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar2150 MW–150 MW
Storage374 MW–74 MW

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs' latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
KEITHICK ESTATE SOLAR, AND BATTERY STORAGE PLANTSSENCOUPAR ANGUSSolarAccepted to connect112.5
Bankside BESSSPENBainsfordStorageAccepted to connect50
37.5MW GEN PV & BATT / 16MW EXPORTSSENCOUPAR ANGUSSolarAccepted to connect37.5
VAUSE FARMENWLPENWORTHAM WEST GSP / STANAH GSP GROUPStorageAccepted to connect20
Ecodev group ltdNGEDCoventry 132Kv S StnStorageAccepted to connect4

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
COUPAR ANGUSSSEN2–150 MW
BainsfordSPEN1–50 MW
PENWORTHAM WEST GSP / STANAH GSP GROUPENWL1–20 MW
Coventry 132Kv S StnNGED1–4 MW

What changed recently

Changes to its sites found in both of two consecutive monthly editions of their DNO's register, the latest first.

NGED: QueueWatch holds one edition of its register so far, the August 2026 edition, so there is nothing to compare yet.

SSEN, August 2026 edition to September 2026 edition, for this customer's sites: 2 sites matched. Every August site and every September site had a match in the other edition.

SPEN, August 2026 edition to September 2026 edition, for this customer's sites: 1 site matched. Every August site and every September site had a match in the other edition.

ENWL, May 2026 edition to September 2026 edition, for this customer's sites: 1 site matched. Every May site and every September site had a match in the other edition.

No change to the status, capacity, technology or customer of its sites in the editions QueueWatch holds.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose