Mondelez uk confectionary production limited

Mondelez uk confectionery production limited at Bishops Wood 132Kv S Stn

NGED Embedded Capacity Register, August 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
4 Oct 2022
Status
Connected
Customer
Mondelez uk confectionery production limited
Site name
Mondelez uk confectionary production limited
Address
Export -Cadbury, Marlbrook, Leominster, Herefordshire, HR6 0PQ
Grid reference
Easting 351266, northing 253928
Licence area
West Midlands
Grid supply point
Bishops Wood 132Kv S Stn
Bulk supply point
Hereford 66Kv S Stn
Primary substation
Bodenham 66 11Kv S Stn
Connection voltage
11 kV
Technology group
Gas and other fossil
Energy source 1
Fossil - Gas, Steam turbine (thermal power plant): 2 MW registered
Registered capacity
2 MW
Maximum export capacity
0.01 MW
Maximum import capacity
3.054 MW
Flexible connection
Not published by NGED
In a connection queue
Not published by NGED
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by NGED
Transmission reinforcement reference
Not published by NGED
Export MPAN
1470001552150
Import MPAN
1424382200000
Last updated
6 Aug 2026
Tracked since
August 2026 edition

Change history

Tracked since the August 2026 edition, the only one QueueWatch holds so far.

Changes to its status, capacity, technology or customer, newest first.

Changes will show from the next edition.

Also at Bishops Wood 132Kv S Stn

GSP view

61 other sites at this grid supply point in the August 2026 edition, 2 of them at Bodenham 66 11Kv S Stn, the same primary substation. In all, the sites here total 1.2 GW: 0.3 GW connected, 0.9 GW accepted to connect.

See all 61

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose