UK Power Networks

Embedded Capacity Register 2 – 1MW and above, October 2026 edition

1,041sites of 1 MW and over
23.3 GWcapacity
9.8 GWconnected (691 sites)
13.5 GWaccepted to connect (350 sites)

Capacity by edition month

Total capacity of sites of 1 MW and over, month by month. Months not covered by UKPN's own files use Northern Powergrid's copy of all six registers.

0 GW12.5 GW25 GW37.5 GW50 GWFeb 2024February 2024: 9.2 GW connected, 20.6 GW accepted to connect (National ECR Archive, a secondary source)March 2024: 9.1 GW connected, 21.3 GW accepted to connect (National ECR Archive, a secondary source)April 2024: 9.1 GW connected, 24 GW accepted to connect (National ECR Archive, a secondary source)May 2024: 9.2 GW connected, 24.7 GW accepted to connect (National ECR Archive, a secondary source)June 2024: 9.2 GW connected, 25.2 GW accepted to connect (National ECR Archive, a secondary source)July 2024: no edition heldAugust 2024: 9.3 GW connected, 25.2 GW accepted to connect (National ECR Archive, a secondary source)September 2024: 9.3 GW connected, 25.8 GW accepted to connect (National ECR Archive, a secondary source)October 2024: no edition heldNovember 2024: no edition heldDecember 2024: no edition heldJan 2025January 2025: 9.2 GW connected, 26.3 GW accepted to connect (National ECR Archive, a secondary source)February 2025: 9.3 GW connected, 26.7 GW accepted to connect (National ECR Archive, a secondary source)March 2025: 9.2 GW connected, 26.7 GW accepted to connect (National ECR Archive, a secondary source)April 2025: 9.5 GW connected, 26.4 GW accepted to connect (National ECR Archive, a secondary source)May 2025: 9.5 GW connected, 26.3 GW accepted to connect (National ECR Archive, a secondary source)June 2025: no edition heldJuly 2025: no edition heldAugust 2025: no edition heldSeptember 2025: no edition heldOctober 2025: no edition heldNovember 2025: 9.7 GW connected, 26.1 GW accepted to connect (National ECR Archive, a secondary source)December 2025: no edition heldJan 2026January 2026: 9.7 GW connected, 26 GW accepted to connect (National ECR Archive, a secondary source)February 2026: no edition heldMarch 2026: no edition heldApril 2026: no edition heldMay 2026: no edition heldJune 2026: no edition heldJuly 2026: no edition heldAugust 2026: no edition heldSeptember 2026: 9.8 GW connected, 13.5 GW accepted to connect (UKPN's own edition)October 2026: 9.8 GW connected, 13.5 GW accepted to connect (UKPN's own edition)

ConnectedAccepted to connectUKPN's own editionNational ECR Archive, a secondary sourceNo edition held

The figures, month by month
Edition monthSourceSitesConnectedAccepted to connectTotal
October 2026UKPN's own edition1,0419.8 GW13.5 GW23.3 GW
September 2026UKPN's own edition1,0419.8 GW13.5 GW23.3 GW
August 2026No edition held––––
July 2026No edition held––––
June 2026No edition held––––
May 2026No edition held––––
April 2026No edition held––––
March 2026No edition held––––
February 2026No edition held––––
January 2026National ECR Archive, a secondary source1,2449.7 GW26 GW35.7 GW
December 2025No edition held––––
November 2025National ECR Archive, a secondary source1,2599.7 GW26.1 GW35.8 GW
October 2025No edition held––––
September 2025No edition held––––
August 2025No edition held––––
July 2025No edition held––––
June 2025No edition held––––
May 2025National ECR Archive, a secondary source1,2669.5 GW26.3 GW35.8 GW
April 2025National ECR Archive, a secondary source1,2639.5 GW26.4 GW35.9 GW
March 2025National ECR Archive, a secondary source1,2709.2 GW26.7 GW35.9 GW
February 2025National ECR Archive, a secondary source1,2729.3 GW26.7 GW36 GW
January 2025National ECR Archive, a secondary source1,2649.2 GW26.3 GW35.5 GW
December 2024No edition held––––
November 2024No edition held––––
October 2024No edition held––––
September 2024National ECR Archive, a secondary source1,2889.3 GW25.8 GW35.1 GW
August 2024National ECR Archive, a secondary source1,2819.3 GW25.2 GW34.5 GW
July 2024No edition held––––
June 2024National ECR Archive, a secondary source1,2739.2 GW25.2 GW34.4 GW
May 2024National ECR Archive, a secondary source1,2759.2 GW24.7 GW33.9 GW
April 2024National ECR Archive, a secondary source1,2739.1 GW24 GW33.1 GW
March 2024National ECR Archive, a secondary source1,1919.1 GW21.3 GW30.4 GW
February 2024National ECR Archive, a secondary source1,1909.2 GW20.6 GW29.8 GW

What changed between editions

Changes to sites found in both of two consecutive monthly editions.

September 2026 edition to October 2026 edition 0 changes

1,021 sites matched. 40 sites couldn't be matched between the two editions, because their details changed or they appear in only one.

No changes found.

Grid supply points in the October 2026 edition

Each grid supply point the edition names, the largest first, with the capacity of its sites connected and accepted to connect.

Walpole991.3 GW2 GW
Bramford1091 GW1.3 GW
Norwich761.1 GW1.1 GW
Bolney460.6 GW0.8 GW
Rayleigh480.5 GW0.9 GW
Sundon700.5 GW0.6 GW
Burwell390.4 GW0.7 GW
Eaton Socon42276 MW677 MW
Pelham39234 MW629 MW
Ninfield33277 MW569 MW

Sites in the October 2026 edition

1,041 sites, 23.3 GW: 9.8 GW connected, 13.5 GW accepted to connect

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Shoreham Power StationVPI Power LimitedSouth Eastern Power Networks (SPN)Gas and other fossilConnected460Bolney
Gt Yarmouth Power StationE.ON UK PLCEastern Power Networks (EPN)Gas and other fossilConnected420Norwich
Kings Lynn Power StationRWE KL LimitedEastern Power Networks (EPN)Gas and other fossilConnected350Walpole
Peterborough Power StationCentrica PB LimitedEastern Power Networks (EPN)Gas and other fossilConnected337.5Walpole
Sheringham Shoal Offshore WindfarmNational Grid Electricity Transmission PLCEastern Power Networks (EPN)WindConnected322Norwich
Thanet WindfarmNational Grid Electricity Transmission PLCSouth Eastern Power Networks (SPN)WindConnected315Richborough/Sellindge 132kV
Southfleet Hook GreenEcoDev (South) LimitedSouth Eastern Power Networks (SPN)StorageAccepted to connect300Littlebrook 132kV (SPN)
Land At Hookers FarmAncleggan LimitedSouth Eastern Power Networks (SPN)StorageAccepted to connect263Bolney
Eastlands FarmMAS 001 LimitedSouth Eastern Power Networks (SPN)StorageAccepted to connect240Ninfield
(ANM - N/A) Raymonds FarmBSR Applications LimitedEastern Power Networks (EPN)StorageAccepted to connect239.99Rayleigh

QueueWatch holds 2 UKPN editions, from September 2026 to October 2026.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.

Flexible connection

The network operator can reduce how much power the site exports or imports when the local network is busy, usually in return for connecting sooner or more cheaply.

Yes: the register says it has one. No: the register says it doesn't. Not stated: the register leaves it blank.