ZENOBE SHETLAND BACKUP BESS

At GREMISTA

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
30 Jun 2026
Status
Accepted to connect
Planning consent
Granted 21 Feb 2024
Scottish Government (S36), reference ECU00004881 · Source: REPD
Customer
Not stated
Site name
ZENOBE SHETLAND BACKUP BESS
Address
INSPECTION HOUSE, PORT BUSINESS PARK, SHETLAND, SHETLAND ISLANDS, ZE1 0TW
Grid reference
Easting 446329, northing 1142677
Licence area
North of Scotland (SHEPD)
Grid supply point
GREMISTA
Bulk supply point
Not stated
Primary substation
GREMISTA
Connection voltage
33 kV
Technology group
Storage
Energy source 1
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 99.68 MW registered
Registered capacity
99.68 MW
Change to maximum export capacity
70 MW
Change to maximum import capacity
80.737 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
20 Jun 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
August 2023 edition

What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?

Change history

Tracked since the August 2023 edition, across 40 editions.

Changes to the details QueueWatch tracks, newest first.

  • December 2025 edition
    Customer not stated (name not shown in the November 2025 edition)
  • November 2025 edition
    Target energisation date stated as 30 Jun 2026 (not stated in the October 2025 edition)
  • September 2023 edition
    Customer stated, name not shown (not stated in the August 2023 edition)

Also at GREMISTA

GSP view

23 other sites at this grid supply point in the November 2026 edition, 20 of them at GREMISTA, the same primary substation. In all, the sites here total 292 MW: 81 MW connected, 211 MW accepted to connect.

  • GARTH FARMHOUSEName not shown, Wind, GREMISTA primaryAccepted74.9 MW
  • SHETLAND WIND FARMWind, GREMISTA primaryAccepted22.4 MW
  • SULLOM VOEFORTUM O & M UK LTD, Other or not stated, GREMISTA primaryConnected17.1 MW
  • LERWICK PS G24SSE GENERATION LTD, Wind, GREMISTA primaryConnected8.075 MW
  • HILL OF WETHERSTALOCOGEN CONSULTING LTD, Other or not stated, GREMISTA primaryAccepted5.2 MW
  • GARTH WIND FARMGARTH WIND LTD, Wind, GREMISTA primaryConnected4.275 MW
  • LERWICK P S (G5)SSE GENERATION LTD, Wind, GREMISTA primaryConnected4.275 MW
  • LERWICK PS (G11)SSE GENERATION LTD, Other or not stated, GREMISTA primaryConnected4.275 MW

See all 23

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.