Blackburn Wind Farm
Wind Estate (UK) Ltd. at Eccles
SPEN Embedded Capacity Register >1MW, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 30 Nov 2030
- Status
- Accepted to connect
- Customer
- Wind Estate (UK) Ltd.
- Site name
- Blackburn Wind Farm
- Address
- Blackburn Farm, Causeway Bank, Chirnside, Berwickshire, TD11 3LF
- Grid reference
- Easting 377585, northing 666538
- Licence area
- Central and Southern Scotland (SPD)
- Grid supply point
- Eccles
- Bulk supply point
- Not stated
- Primary substation
- Not stated
- Connection voltage
- 33 kV
- Technology group
- Wind
- Energy source 1
- Wind, Onshore wind turbines: 16.8 MW registered
- Registered capacity
- 16.8 MW
- Change to maximum export capacity
- 16.8 MW
- Change to maximum import capacity
- 0.1 MW
- Flexible connection
- Yes
- In a connection queue
- Yes
- Date accepted
- 19 Feb 2025
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SPEN
- Transmission reinforcement reference
- Not stated
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 25 Jun 2025
- Tracked since
- March 2026 edition
Change history
Tracked since the March 2026 edition, across 7 editions.
Changes to the details QueueWatch tracks, newest first.
- May 2026 editionCustomer stated as Wind Estate (UK) Ltd. (not stated in the April 2026 edition)
Also at Eccles
GSP view3 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 105 MW: 29 MW connected, 76 MW accepted to connect.
- Coldstream Solar PV Plant (Elwartlaw Farm)Conrad Energy (Developments) II Limited, SolarAccepted40.56 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?