Land At Priesthawes Farm
UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Dec 2031
- Status
- Accepted to connect
- Customer
- O&G Group Limited
- Site name
- Land At Priesthawes Farm
- Address
- Land At Priesthawes Farm, Polegate, East Sussex, BN26 6QU
- Grid reference
- Easting 560728, northing 105876
- Licence area
- South Eastern Power Networks (SPN)
- Grid supply point
- Ninfield
- Bulk supply point
- Polegate Grid
- Primary substation
- Polegate Grid 33kV
- Connection voltage
- 33 kV
- Technology group
- Storage
- Energy source 1
- Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 15 MW registered
- Energy source 2
- Solar, Photovoltaic
- Registered capacity
- 15 MW
- Change to maximum export capacity
- 15 MW
- Change to maximum import capacity
- 8 MW
- Flexible connection
- Yes
- In a connection queue
- Yes
- Date accepted
- 14 Sep 2021
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by UKPN
- Transmission reinforcement reference
- 102348-204514
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 13 Nov 2026
- Tracked since
- September 2026 edition
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Change history
Tracked since the September 2026 edition, across 3 editions.
Changes to the details QueueWatch tracks, newest first.
- November 2026 editionTarget energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
Also at Ninfield
GSP view32 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 823 MW: 279 MW connected, 544 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?