HILLHEAD OF GASK PV AND BESS

THE GREENSPAN AGENCY LIMITED at CARRADALE

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
22 May 2027
Status
Accepted to connect
Planning consent
Granted 8 Apr 2022
Aberdeenshire, reference APP/2021/2467 · Source: REPD
Contract for Difference
Allocation Round 7a
Customer
THE GREENSPAN AGENCY LIMITED
Site name
HILLHEAD OF GASK PV AND BESS
Address
HILLHEAD OF GASK SOLAR AND STORAGE PARK, PETERHEAD, ABERDEENSHIRE, AB42 0PT
Grid reference
Easting 408912, northing 840661
Licence area
North of Scotland (SHEPD)
Grid supply point
CARRADALE
Bulk supply point
Not stated
Primary substation
CARRADALE GRID
Connection voltage
132 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 14.2 MW registered
Registered capacity
14.2 MW
Change to maximum export capacity
5.8 MW
Change to maximum import capacity
5.8 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
22 Feb 2026
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
12 Jun 2026
Tracked since
June 2026 edition

Change history

Tracked since the June 2026 edition, across 6 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Export capacity changed from 14.2 MW to 5.8 MW

Also at CARRADALE

GSP view

21 other sites at this grid supply point in the November 2026 edition, 15 of them at CARRADALE GRID, the same primary substation. In all, the sites here total 694 MW: 188 MW connected, 506 MW accepted to connect.

See all 21

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition. QueueWatch matched the site to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.