LANDMARK FARM
At MELKSHAM GSP
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 23 Jan 2027
- Status
- Accepted to connect
- Customer
- Not stated
- Site name
- LANDMARK FARM
- Address
- LANDMARK FARM, WANSTROW, SHEPTON MALLET, SOMERSET, BA4 4TQ
- Grid reference
- Easting 371590, northing 142148
- Licence area
- Southern England (SEPD)
- Grid supply point
- MELKSHAM GSP
- Bulk supply point
- FROME
- Primary substation
- HOLWELL
- Connection voltage
- 11 kV
- Technology group
- Other or not stated
- Energy source 1
- OTHER, OTHER: 5.5 MW registered
- Registered capacity
- 5.5 MW
- Change to maximum export capacity
- 0.999 MW
- Change to maximum import capacity
- 0 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 21 May 2024
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- June 2024 edition
Change history
Tracked since the June 2024 edition, across 30 editions.
Changes to the details QueueWatch tracks, newest first.
- November 2025 editionTarget energisation date moved from 23 Sep 2024 to 23 Jan 2027 (28 months later)
- September 2024 editionTarget energisation date stated as 23 Sep 2024 (not stated in the August 2024 edition)
Also at MELKSHAM GSP
GSP view95 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 1.9 GW: 0.5 GW connected, 1.4 GW accepted to connect.
- SOLAR PV AND BATTERY 50MW IMPORT 50MW EXPORTLOW CARBON UK SOLAR INVESTMENT COMPANY LIMITED, SolarAccepted50 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?