(ANM) SS17 9LL The Manorway

Eclipse Power Generation at Tilbury

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
30 Nov 2025
Status
Accepted to connect
Customer
Eclipse Power Generation
Site name
(ANM) SS17 9LL The Manorway
Address
The Manor Way, Corringham, Stanford-Le-Hope, Essex, SS17 9LL
Grid reference
Easting 574431, northing 182333
Licence area
Eastern Power Networks (EPN)
Grid supply point
Tilbury
Bulk supply point
Coryton Grid 33kV
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Gas and other fossil
Energy source 1
Fossil - Gas, Engine (combustion / reciprocating): 20 MW registered
Energy source 2
Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 20 MW registered
Registered capacity
20 MW
Change to maximum export capacity
20 MW
Change to maximum import capacity
0 MW
Flexible connection
Yes
In a connection queue
Yes
Date accepted
28 Sep 2021
Date connected
Not stated
Distribution reinforcement reference
Not published by UKPN
Transmission reinforcement reference
033458-033458
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
13 Nov 2026
Tracked since
September 2026 edition

Change history

Tracked since the September 2026 edition, across 3 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Target energisation date moved from 30 Nov 2024 to 30 Nov 2025 (12 months later)

Also at Tilbury

GSP view

23 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 464 MW: 216 MW connected, 248 MW accepted to connect.

See all 23

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?