Great Wheatley Solar Farm

Aura Power Developments at Rayleigh

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
30 Mar 2026
Status
Accepted to connect
Planning consent
Granted on appeal 11 Mar 2024
Rochford, reference 22/00175/FUL · Source: REPD
Contract for Difference
Allocation Round 6
Customer
Aura Power Developments
Site name
Great Wheatley Solar Farm
Address
Rayliegh, Essex, SS6 9TU
Grid reference
Easting 579728, northing 190948
Licence area
Eastern Power Networks (EPN)
Grid supply point
Rayleigh
Bulk supply point
Rayleigh Local 33kV
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 20 MW registered
Registered capacity
20 MW
Change to maximum export capacity
20 MW
Change to maximum import capacity
0.4 MW
Flexible connection
No
In a connection queue
Yes
Date accepted
18 Mar 2020
Date connected
Not stated
Distribution reinforcement reference
Not published by UKPN
Transmission reinforcement reference
021847-021847
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
13 Nov 2026
Tracked since
September 2026 edition

Change history

Tracked since the September 2026 edition, across 3 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Target energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)

Also at Rayleigh

GSP view

45 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 1.1 GW: 0.5 GW connected, 0.6 GW accepted to connect.

See all 45

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition. QueueWatch matched the site to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.