WORK FARM, WORK FARM
ORKNEY SUSTAINABLE ENERGY LTD at THURSO
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 30 Apr 2027
- Status
- Accepted to connect
- Customer
- ORKNEY SUSTAINABLE ENERGY LTD
- Site name
- WORK FARM, WORK FARM
- Address
- WORK FARM, WORK FARM, ST OLA, ORKNEY, ORKNEY ISLANDS, KW15 1UF
- Grid reference
- Easting 346748, northing 1012434
- Licence area
- North of Scotland (SHEPD)
- Grid supply point
- THURSO
- Bulk supply point
- Not stated
- Primary substation
- SCORRADALE
- Connection voltage
- 33 kV
- Technology group
- Wind
- Energy source 1
- WIND, ONSHORE WIND TURBINES: 1.5 MW registered
- Registered capacity
- 1.5 MW
- Change to maximum export capacity
- 1.5 MW
- Change to maximum import capacity
- 0.148 MW
- Flexible connection
- Yes
- In a connection queue
- Not published by SSEN
- Date accepted
- 28 Dec 2022
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- August 2023 edition
Change history
Tracked since the August 2023 edition, across 40 editions.
Changes to the details QueueWatch tracks, newest first.
- July 2026 editionFlexible connection stated as “yes” (not stated in the June 2026 edition)
- November 2025 editionTarget energisation date stated as 30 Apr 2027 (not stated in the October 2025 edition)
Also at THURSO
GSP view24 other sites at this grid supply point in the November 2026 edition, 8 of them at SCORRADALE, the same primary substation. In all, the sites here total 379 MW: 38 MW connected, 341 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?