QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

STRATH TIRRY WIND FARM

STRATH TIRRY WIND ENERGY 2021 LTD at LAIRG

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
19 Dec 2029
Status
Accepted to connect
Customer
STRATH TIRRY WIND ENERGY 2021 LTD
Site name
STRATH TIRRY WIND FARM
Address
STRATH TIRRY WIND FARM, STRATH TIRRY ENERGY PARK A836, LAIRG, HIGHLAND, IV27 4DN
Grid reference
Easting 255929, northing 912417
Licence area
North of Scotland (SHEPD)
Grid supply point
LAIRG
Bulk supply point
Not stated
Primary substation
LAIRG GRID
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 35 MW registered
Registered capacity
35 MW
Change to maximum export capacity
0.317 MW
Change to maximum import capacity
0.317 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
29 Jul 2025
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
August 2025 edition

Change history

Tracked since the August 2025 edition, across 16 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Export capacity changed from 35 MW to 0.317 MW
  • October 2026 edition
    Export capacity changed from 0.317 MW to 35 MW
  • September 2026 edition
    Export capacity changed from 35 MW to 0.317 MW
  • August 2026 edition
    Export capacity changed from 0.317 MW to 35 MW
  • February 2026 edition
    Export capacity changed from 34.8 MW to 0.317 MW
  • November 2025 edition
    Target energisation date stated as 19 Dec 2029 (not stated in the October 2025 edition)

Also at LAIRG

GSP view

5 other sites at this grid supply point in the November 2026 edition, 5 of them at LAIRG GRID, the same primary substation. In all, the sites here total 196 MW: 58 MW connected, 138 MW accepted to connect.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?