ETON COLLEGE PV
At IVER 132KV
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 3 Dec 2026
- Status
- Accepted to connect
- Customer
- Not stated
- Site name
- ETON COLLEGE PV
- Address
- ETON COLLEGE PV OPTION 1, COMMON LANE, ETON, BERKSHIRE, SL4 6PS
- Grid reference
- Easting 495957, northing 178259
- Licence area
- Southern England (SEPD)
- Grid supply point
- IVER 132KV
- Bulk supply point
- CHALVEY
- Primary substation
- CHALVEY
- Connection voltage
- 11 kV
- Technology group
- Solar
- Energy source 1
- SOLAR, PHOTOVOLTAIC: 3.96 MW registered
- Registered capacity
- 3.96 MW
- Change to maximum export capacity
- 0.05 MW
- Change to maximum import capacity
- 0.05 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 3 Dec 2025
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- December 2025 edition
Change history
Tracked since the December 2025 edition, across 12 editions.
Changes to the details QueueWatch tracks, newest first.
- November 2026 editionExport capacity changed from 3.96 MW to 0.05 MW
- September 2026 editionExport capacity changed from 0.05 MW to 3.96 MW
- August 2026 editionExport capacity changed from 3.96 MW to 0.05 MW
- April 2026 editionExport capacity changed from 0.05 MW to 3.96 MW
- February 2026 editionExport capacity changed from 3.96 MW to 0.05 MW
Also at IVER 132KV
GSP view19 other sites at this grid supply point in the November 2026 edition, 1 of them at CHALVEY, the same primary substation. In all, the sites here total 281 MW: 178 MW connected, 103 MW accepted to connect.
- LAKESIDE ENERGY FROM WASTE LIMITEDNFPA (APRIL 2DATA NOT AVAILABLE2DATA NOT AVAILABLE), Bioenergy and waste, LAKESIDE primaryConnected43.415 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?