QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

75MW WIND, PV AND BESS

At LUNANHEAD

SSEN Embedded Capacity Register, August 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2032
Status
Accepted to connect
Customer
Not stated
Site name
75MW WIND, PV AND BESS
Address
LAND AT KINNORDY ESTATE CASEWAYEND, KIRRIEMUIR, ANGUS, DD8 4RF
Grid reference
Easting 337806, northing 755397
Licence area
North of Scotland (SHEPD)
Grid supply point
LUNANHEAD
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Other or not stated
Energy source 1
OTHER, OTHER: 75 MW registered
Registered capacity
75 MW
Change to maximum export capacity
60 MW
Change to maximum import capacity
63.158 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
9 Aug 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
September 2023 edition

Change history

Tracked from the September 2023 edition to the August 2026 edition, across 36 editions.

Changes to its status, capacity, technology or customer, newest first.

  • September 2026 edition
    Not found in this edition by its MPAN, grid reference or name and postcode

No change to its status, capacity, technology or customer.

Also at LUNANHEAD

GSP view

14 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 452 MW: 7 MW connected, 445 MW accepted to connect.

See all 14

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose