Dunwan Dam Wind Farm
Wind Estate (UK) Ltd at Giffnock
SPEN Embedded Capacity Register >1MW, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Oct 2033
- Status
- Accepted to connect
- Planning consent
- Application submitted 15 Aug 2025
Glasgow City, reference 2025/0439/TP · Source: REPD - Customer
- Wind Estate (UK) Ltd
- Site name
- Dunwan Dam Wind Farm
- Address
- Dunwan Dam, Eaglesham, East Renfrewshire, G76 0QE
- Grid reference
- Easting 255914, northing 658506
- Licence area
- Central and Southern Scotland (SPD)
- Grid supply point
- Giffnock
- Bulk supply point
- Not stated
- Primary substation
- Not stated
- Connection voltage
- 33 kV
- Technology group
- Wind
- Energy source 1
- Wind, Onshore wind turbines: 24.8 MW registered
- Registered capacity
- 24.8 MW
- Change to maximum export capacity
- 24.8 MW
- Change to maximum import capacity
- 0.1 MW
- Flexible connection
- No
- In a connection queue
- No
- Date accepted
- 27 Feb 2024
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SPEN
- Transmission reinforcement reference
- SPT-RI-1741, SPT-RI-1968, SPT-RI-2520, SPT-RI-3490, SPT-RI-3924, SPT-RI-4034, SPT-RI-4035
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 1 Apr 2024
- Tracked since
- March 2026 edition
Change history
Tracked since the March 2026 edition, across 7 editions.
Changes to the details QueueWatch tracks, newest first.
- May 2026 editionFlexible connection changed from “yes” to “no”
- May 2026 editionIn a connection queue changed from “yes” to “no”
Also at Giffnock
GSP view6 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 118 MW: 6 MW connected, 112 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
Planning consent
The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.
How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.