MELVICH WIND ENERGY HUB

MELVICH WIND ENERGY HUB LIMITED at DOUNREAY

SSEN Embedded Capacity Register, October 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2033
Status
Accepted to connect
Customer
MELVICH WIND ENERGY HUB LIMITED
Site name
MELVICH WIND ENERGY HUB
Address
MELVICH WIND ENERGY HUB, MELVICH, THURSO, HIGHLAND, KW14 7RZ
Grid reference
Easting 284210, northing 964807
Licence area
North of Scotland (SHEPD)
Grid supply point
DOUNREAY
Bulk supply point
Not stated
Primary substation
DOUNREAY
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 86.4 MW registered
Energy source 2
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 45.474 MW registered
Registered capacity
86.4 MW
Change to maximum export capacity
45.474 MW
Change to maximum import capacity
45.474 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
16 May 2025
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
June 2025 edition

Change history

Tracked since the June 2025 edition, across 17 editions.

Changes to the details QueueWatch tracks, newest first.

  • September 2026 edition
    Export capacity changed from 86.4 MW to 45.474 MW
  • July 2026 edition
    Export capacity changed from 45.474 MW to 86.4 MW
  • May 2026 edition
    Export capacity changed from 86.4 MW to 45.474 MW
  • February 2026 edition
    Export capacity changed from 43.2 MW to 86.4 MW
  • November 2025 edition
    Target energisation date stated as 31 Oct 2033 (not stated in the October 2025 edition)

Also at DOUNREAY

GSP view

9 other sites at this grid supply point in the October 2026 edition, 7 of them at DOUNREAY, the same primary substation. In all, the sites here total 391 MW: 63 MW connected, 328 MW accepted to connect.

See all 9

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose