Bentley Motors
QuiNotas ENoergy UK at Cellarhead
SPEN Embedded Capacity Register >1MW, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 1 Sep 2023
- Status
- Accepted to connect
- Customer
- QuiNotas ENoergy UK
- Site name
- Bentley Motors
- Address
- BeNotley Site Pym's LaNoe, Crewe, Crewe, Cheshire, CW1 3PL
- Grid reference
- Easting 368662, northing 356607
- Licence area
- Merseyside, Cheshire and North Wales (SPM)
- Grid supply point
- Cellarhead
- Bulk supply point
- COPPENHALL GT1 / CREWE GT1 / CREWE GT2A / CREWE GT4A / RADWAY GREEN GT1 / RADWAY GREEN GT2 / WHITCHURCH GT2
- Primary substation
- ROLLS ROYCE T1 / ROLLS ROYCE T2 / ROLLS ROYCE T3
- Connection voltage
- 33 kV
- Technology group
- Solar
- Energy source 1
- Solar, Photovoltaic: 4.2 MW registered
- Energy source 2
- Solar, Photovoltaic: 9.9 MW registered
- Registered capacity
- 14.1 MW
- Change to maximum export capacity
- 8 MW
- Change to maximum import capacity
- 0 MW
- Flexible connection
- Not stated
- In a connection queue
- No
- Date accepted
- Not stated
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SPEN
- Transmission reinforcement reference
- Not stated
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 29 Nov 2024
- Tracked since
- March 2026 edition
Change history
Tracked since the March 2026 edition, across 7 editions.
Changes to the details QueueWatch tracks, newest first.
- August 2026 editionStatus changed from “connected” to “accepted to connect”
- August 2026 editionCustomer changed from Bentley Motors to QuiNotas ENoergy UK
- July 2026 editionCapacity changed from 8 MW to 14.1 MW
- May 2026 editionTarget energisation date stated as 1 Sep 2023 (not stated in the April 2026 edition)
Also at Cellarhead
GSP view10 other sites at this grid supply point in the September 2026 edition, 1 of them at ROLLS ROYCE T1 / ROLLS ROYCE T2 / ROLLS ROYCE T3, the same primary substation. In all, the sites here total 115 MW: 29 MW connected, 86 MW accepted to connect.
- Rolls RoyceQuiNotas ENoergy UK, Solar, ROLLS ROYCE T1 / ROLLS ROYCE T2 / ROLLS ROYCE T3 primaryConnected7.1 MW
- Maw Green No 2INofiNois ENoergy Services Ltd, Bioenergy and waste, MAW GREEN GEN primaryConnected3.2 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?