HAMPRESTON SOLAR FARM

At MANNINGTON GSP

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
29 Mar 2030
Status
Accepted to connect
Customer
Not stated
Site name
HAMPRESTON SOLAR FARM
Address
MANOR FARM HOUSE, OLD HAM LANE, WIMBORNE, DORSET, BH21 7LP
Grid reference
Easting 404609, northing 99844
Licence area
Southern England (SEPD)
Grid supply point
MANNINGTON GSP
Bulk supply point
MANNINGTON BSP
Primary substation
Not stated
Connection voltage
132 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 40 MW registered
Registered capacity
40 MW
Change to maximum export capacity
0.421 MW
Change to maximum import capacity
0.421 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
2 Jun 2025
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
July 2025 edition

Change history

Tracked since the July 2025 edition, across 17 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Export capacity changed from 40 MW to 0.421 MW
  • September 2026 edition
    Export capacity changed from 0.421 MW to 40 MW
  • August 2026 edition
    Export capacity changed from 40 MW to 0.421 MW
  • May 2026 edition
    Export capacity changed from 0.421 MW to 40 MW
  • April 2026 edition
    Export capacity changed from 40 MW to 0.421 MW
  • November 2025 edition
    Target energisation date stated as 29 Mar 2030 (not stated in the October 2025 edition)

Also at MANNINGTON GSP

GSP view

92 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 1.9 GW: 0.5 GW connected, 1.4 GW accepted to connect.

See all 92

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?