QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Land At Harp Farm

BSR Applications Limited at Kingsnorth

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2027
Status
Accepted to connect
Customer
BSR Applications Limited
Site name
Land At Harp Farm
Address
Land At Harp Farm, Harp Farm Road, Maidstone, Kent, ME14 3ED
Grid reference
Easting 577414, northing 159926
Licence area
South Eastern Power Networks (SPN)
Grid supply point
Kingsnorth
Bulk supply point
Chatham Grid
Primary substation
Chatham Grid 33kV
Connection voltage
33 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 15 MW registered
Registered capacity
15 MW
Change to maximum export capacity
15 MW
Change to maximum import capacity
0.05 MW
Flexible connection
No
In a connection queue
Yes
Date accepted
30 Jan 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by UKPN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
13 Nov 2026
Tracked since
September 2026 edition

Change history

Tracked since the September 2026 edition, across 3 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Target energisation date moved from 30 Apr 2025 to 31 Oct 2027 (30 months later)

Also at Kingsnorth

GSP view

17 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 241 MW: 125 MW connected, 116 MW accepted to connect.

See all 17

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?