EYNSHAM ESTATE - PV & BESS

Name not shown at COWLEY GSP

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
29 May 2026
Status
Accepted to connect
Customer
Name not shown
Site name
EYNSHAM ESTATE - PV & BESS
Address
HILL FARM BARN, OXFORD ROAD, WITNEY, OXFORDSHIRE, OX29 6UY
Grid reference
Easting 438683, northing 210173
Licence area
Southern England (SEPD)
Grid supply point
COWLEY GSP
Bulk supply point
WITNEY
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 100 MW registered
Energy source 2
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 52.526 MW registered
Registered capacity
100 MW
Change to maximum export capacity
100 MW
Change to maximum import capacity
52.526 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
29 May 2025
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
June 2025 edition

Change history

Tracked since the June 2025 edition, across 18 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Export capacity changed from 52.526 MW to 100 MW
  • May 2026 edition
    Export capacity changed from 100 MW to 52.526 MW
  • April 2026 edition
    Export capacity changed from 52.526 MW to 100 MW
  • February 2026 edition
    Export capacity changed from 49.9 MW to 52.526 MW
  • November 2025 edition
    Target energisation date stated as 29 May 2026 (not stated in the October 2025 edition)

Also at COWLEY GSP

GSP view

71 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 2.0 GW: 0.4 GW connected, 1.6 GW accepted to connect.

See all 71

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?