99.9MW BESS TITCHFIELD LANE

At BOTLEY WOOD GSP

SSEN Embedded Capacity Register, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Jan 2027
Status
Accepted to connect
Customer
Not stated
Site name
99.9MW BESS TITCHFIELD LANE
Address
LAND ON THE EAST OF TITCHFIELD LANE WICKHAM, FAREHAM, HAMPSHIRE, PO15 6DZ
Grid reference
Easting 455631, northing 109009
Licence area
Southern England (SEPD)
Grid supply point
BOTLEY WOOD GSP
Bulk supply point
BOTLEY WOOD
Primary substation
Not stated
Connection voltage
132 kV
Technology group
Storage
Energy source 1
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 100 MW registered
Registered capacity
100 MW
Change to maximum export capacity
100 MW
Change to maximum import capacity
105.263 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
28 May 2025
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
June 2025 edition

Change history

Tracked since the June 2025 edition, across 16 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at BOTLEY WOOD GSP

GSP view

16 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 421 MW: 103 MW connected, 318 MW accepted to connect.

See all 16

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose