PEATTIE FARM PV

At FIDDES

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2033
Status
Accepted to connect
Customer
Not stated
Site name
PEATTIE FARM PV
Address
PEATTIE FARM, INVERBERVIE INVERBERVIE, MONTROSE, ANGUS, DD10 0PP
Grid reference
Easting 380711, northing 773140
Licence area
North of Scotland (SHEPD)
Grid supply point
FIDDES
Bulk supply point
Not stated
Primary substation
FIDDES
Connection voltage
33 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 49.7 MW registered
Registered capacity
49.7 MW
Change to maximum export capacity
49.7 MW
Change to maximum import capacity
0.8 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
11 Aug 2025
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
September 2025 edition

Change history

Tracked since the September 2025 edition, across 15 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Export capacity changed from 0.8 MW to 49.7 MW
  • October 2026 edition
    Export capacity changed from 49.7 MW to 0.8 MW
  • August 2026 edition
    Export capacity changed from 0.8 MW to 49.7 MW
  • July 2026 edition
    Export capacity changed from 49.7 MW to 0.8 MW
  • May 2026 edition
    Export capacity changed from 0.8 MW to 49.7 MW
  • February 2026 edition
    Export capacity changed from 49.7 MW to 0.8 MW
  • November 2025 edition
    Target energisation date stated as 31 Oct 2033 (not stated in the October 2025 edition)

Also at FIDDES

GSP view

18 other sites at this grid supply point in the November 2026 edition, 12 of them at FIDDES, the same primary substation. In all, the sites here total 456 MW: 86 MW connected, 370 MW accepted to connect.

See all 18

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?