Hale Farm, Hulcott
EEB31 Limited at Sundon
UKPN Embedded Capacity Register 2 – 1MW and above, October 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 30 May 2025
- Status
- Accepted to connect
- Customer
- EEB31 Limited
- Site name
- Hale Farm, Hulcott
- Address
- Hale Farm, Hulcott, Aylesbury, Buckinghamshire, HP22 5AX
- Grid reference
- Easting 486031, northing 216311
- Licence area
- Eastern Power Networks (EPN)
- Grid supply point
- Sundon
- Bulk supply point
- Not stated
- Primary substation
- Not stated
- Connection voltage
- 132 kV
- Technology group
- Solar
- Energy source 1
- Solar, Photovoltaic: 45.3 MW registered
- Registered capacity
- 45.3 MW
- Change to maximum export capacity
- 45.3 MW
- Change to maximum import capacity
- 0.1 MW
- Flexible connection
- No
- In a connection queue
- Yes
- Date accepted
- 16 Nov 2018
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by UKPN
- Transmission reinforcement reference
- Not published by UKPN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 14 Jul 2026
- Tracked since
- September 2026 edition
Change history
Tracked since the September 2026 edition, across 2 editions.
Changes to its status, capacity, technology or customer, newest first.
No change to its status, capacity, technology or customer.
Also at Sundon
GSP view69 other sites at this grid supply point in the October 2026 edition. In all, the sites here total 1.1 GW: 0.5 GW connected, 0.6 GW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose