Land south of Skeeby Substation

Skeeby Ph2 at Norton

Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
22 Jul 2026
Status
Connected
Customer
Skeeby Ph2
Site name
Land south of Skeeby Substation
Address
Land south of Skeeby Substation, Skeeby, Skeeby Solar, North Yorkshire, DL10 5DP
Grid reference
Easting 419543, northing 502556
Licence area
North East (Northern Powergrid)
Grid supply point
Norton
Bulk supply point
Leeming Bar/Skeeby
Primary substation
HESL Solar
Connection voltage
33 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 39.33 MW registered
Energy source 2
Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 33.9 MW registered
Registered capacity
73.23 MW
Maximum export capacity
39.33 MW
Maximum import capacity
Not stated
Flexible connection
No
In a connection queue
Not published by Northern Powergrid
Date accepted
25 Jan 2021
Target energisation date
Not published by Northern Powergrid
Distribution reinforcement reference
Not published by Northern Powergrid
Transmission reinforcement reference
Not published by Northern Powergrid
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
9 Jun 2026
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 9 editions.

Changes to the details QueueWatch tracks, newest first.

  • August 2026 edition
    Status changed from “accepted to connect” to “connected”
  • August 2026 edition
    Export capacity changed from 73.23 MW to 39.33 MW
  • June 2026 edition
    Capacity changed from 39.33 MW to 73.23 MW
  • June 2026 edition
    Export capacity changed from 39.33 MW to 73.23 MW

Also at Norton

GSP view

66 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 2.0 GW: 0.4 GW connected, 1.6 GW accepted to connect.

See all 66

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?