HESTA HEAD WIND

NATURAL POWER CONSULTANTS at THURSO

SSEN Embedded Capacity Register, March 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
6 Apr 2029
Status
Accepted to connect
Customer
NATURAL POWER CONSULTANTS
Site name
HESTA HEAD WIND
Address
HESTA HEAD (LAND NEAR) ST MARGARETS HOPE, ORKNEY, ORKNEY ISLANDS, KW17 2RL
Grid reference
Easting 345727, northing 989355
Licence area
North of Scotland (SHEPD)
Grid supply point
THURSO
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 20.4 MW registered
Registered capacity
20.4 MW
Change to maximum export capacity
0.636 MW
Change to maximum import capacity
0.636 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
11 Apr 2024
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
August 2023 edition

Change history

Tracked from the August 2023 edition to the March 2026 edition, across 28 editions. Not found in the March 2024, April 2024, May 2025 and June 2025 editions.

Changes to its status, capacity, technology or customer, newest first.

  • April 2026 edition
    Not found in this edition by its MPAN, grid reference or name and postcode
  • June 2025 edition
    Not found in this edition by its MPAN, grid reference or name and postcode
  • May 2025 edition
    Not found in this edition by its MPAN, grid reference or name and postcode
  • April 2024 edition
    Not found in this edition by its MPAN, grid reference or name and postcode
  • March 2024 edition
    Not found in this edition by its MPAN, grid reference or name and postcode

No change to its status, capacity, technology or customer.

Also at THURSO

GSP view

25 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 379 MW: 38 MW connected, 341 MW accepted to connect.

See all 25

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose