QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

GLENKILN FARM

At CARRADALE

SSEN Embedded Capacity Register, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2034
Status
Accepted to connect
Customer
Not stated
Site name
GLENKILN FARM
Address
NEW SITE, GLENKILN FARM, BRODICK, NORTH AYRSHIRE, KA27 8NT
Grid reference
Easting 201447, northing 630540
Licence area
North of Scotland (SHEPD)
Grid supply point
CARRADALE
Bulk supply point
Not stated
Primary substation
CARRADALE GRID
Connection voltage
33 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 4 MW registered
Registered capacity
4 MW
Change to maximum export capacity
0.1 MW
Change to maximum import capacity
0.1 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
30 May 2025
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
June 2025 edition

Change history

Tracked since the June 2025 edition, across 16 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at CARRADALE

GSP view

21 other sites at this grid supply point in the September 2026 edition, 15 of them at CARRADALE GRID, the same primary substation. In all, the sites here total 694 MW: 188 MW connected, 506 MW accepted to connect.

See all 21

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose