199.9MW
SSEN Embedded Capacity Register, August 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Dec 2037
- Status
- Accepted to connect
- Customer
- Not stated
- Site name
- 199.9MW
- Address
- LAND AT FROG LANE, LITTLE LONDON, TADLEY, HAMPSHIRE, RG26 5EW
- Grid reference
- Easting 462321, northing 160207
- Licence area
- Southern England (SEPD)
- Grid supply point
- BRAMLEY (FLEE)
- Bulk supply point
- Not stated
- Primary substation
- Not stated
- Connection voltage
- 132 kV
- Technology group
- Other or not stated
- Energy source 1
- OTHER, OTHER: 100 MW registered
- Registered capacity
- 100 MW
- Change to maximum export capacity
- 100 MW
- Change to maximum import capacity
- 110.521 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 3 Nov 2023
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- December 2023 edition
Change history
Tracked from the December 2023 edition to the August 2026 edition, across 33 editions.
Changes to its status, capacity, technology or customer, newest first.
- September 2026 editionNot found in this edition by its MPAN, grid reference or name and postcode
No change to its status, capacity, technology or customer.
Also at BRAMLEY (FLEE)
GSP view68 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 1.6 GW: 0.4 GW connected, 1.2 GW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose